Republic of the Philippines

Department of the Interior and Local Government


BUREAU OF FIRE PROTECTION

PROJECT PROCUREMENT MANAGEMENT PLAN


FY 2021
Station: _____________________________
General Description (Program/ Activities/ Projects) Quantity / Schedule / Milestone of Activities (4)
Estimated Budget
(P/A/Ps) Size Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
(1) (2) (3)
A.I. GENERAL ADMINISTRATION SERVICES

A.I.a General Management & Supervision

Activity 1

Activity 2
...

Activity nth

Sub-total A.I.a

A.I.b Administration of Personnel Benefits

Activity 1

Activity 2
...

Activity nth

Sub-total A.I.b

BFP-QSF-PPD-002 Rev. ØØ (05.24.18) 1 of 4


General Description (Program/ Activities/ Projects) Quantity / Schedule / Milestone of Activities (4)
Estimated Budget
(P/A/Ps) Size Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
(1) (2) (3)
TOTAL A.I (A.I.a+A.I.b)

A.II OPERATIONS

A.II.a Fire Prevention Management Program

A.II.a.1 Enforcement of Fire Safety Laws,


Rules, Regulations and Others

Activity 1

Activity 2
...

Activity nth

Sub-total A.II.a.1

A.II.a.2 Information, Education and


Communication (IEC) Activities

Activity 1

Activity 2
...

Activity nth

Sub-total A.II.a.2

TOTAL A.II.a (A.II.a.1+A.II.a.2)

A.II.b Fire and Emergency Management Program

A.II.b.1 Fire Operations Activities

BFP-QSF-PPD-002 Rev. ØØ (05.24.18) 2 of 4


General Description (Program/ Activities/ Projects) Quantity / Schedule / Milestone of Activities (4)
Estimated Budget
(P/A/Ps) Size Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
(1) (2) (3)
Activity 1

Activity 2

...
Activity nth

Sub-total A.II.b.1

A.II.b.2 Non-Fire Response Activities

Activity 1

Activity 2
...

Activity nth

Sub-total A.II.b.2

A.II.b.3 Fire Investigation Activities

Activity 1

Activity 2
...

Activity nth

Sub-total A.II.b.3

TOTAL A.II.b (A.II.b.1+A.II.b.2+A.II.b.3)

TOTAL A.II (A.II.a+A.II.b)

GRAND TOTAL (A.I + A.II)

BFP-QSF-PPD-002 Rev. ØØ (05.24.18) 3 of 4


General Description (Program/ Activities/ Projects) Quantity / Schedule / Milestone of Activities (4)
Estimated Budget
(P/A/Ps) Size Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
(1) (2) (3)

Note:
1- A.I Proposed Program/Activities/Projects in your AOR to include Seminars/Workshops
1- A.II Project/Programs/Activities involving the Enforcement of Fire Code and Fire Prevention Activities
1- A.II. Project/Programs/Activities involving Fire Operations to include the modernization of our Fire Suppression and EMS Equipment and Fire Stations
2- The corresponding needs of the Program/Activities/Projects in your AOR
3- Budget needed in the Proposed Program/Activities/Projects
4- Highlight the box on what month the Proposed/Program/Activities/Projects to be implemented

BFP-QSF-PPD-002 Rev. ØØ (05.24.18) 4 of 4