Professional Documents
Culture Documents
a. 3-5%
b. 10-15%
c. 5-10%
d. 1-5%
a. 10%
b. 15%
c. 5%
d. 5-10%
a. 7 cd and 15 cd respectively
b. 7 cd and 14 cd respectively
c. 7 cd and 28 cd respectively
d. 7 cd and 21 cd respectively
6. The processing by the Implementing Office of Variation
Orders from its preparation to approval shall not exceed A RIGHT 1
_____ calendar days.
a. 30 cd
b. 45 cd
c. 60 cd
d. 20cd
a. Beyond 30 cd up to 60 cd
b. Beyond 60 cd up to 90 cd
c. Beyond 120 cd
d. Beyond 90 cd up to 120 cd
a. Beyond 30 cd up to 60 cd
b. Beyond 60 cd up to 90 cd
c. Beyond 120 cd
d. Beyond 90 cd up to 120 cd
32. Contract with Negative Slippages of 15% or More A RIGHT 1
a. D.O No. 142 Series of 1989
b. D.O No. 124 Series of 1989
c. D.O No. 142 Series of 1988
d. D.O No. 124 Series of 1988
33. The contractor must file a written notice prior to the
expiration of contract time and within ______ calendar days
after additional work involved has been started or after the B RIGHT 1
circumstances leading to such claim have arisen.
a. 15
b. 30
c. 45
d. 60
a. 14 working days
b. 5 working days
c. 7 working days
d. 10 working days
a. Aluminum guardrails
b. Reinforcing Steel Bars
c. Galvanized Steel Sheets and coils
d. Steel Pipes
48. Sampling of soil aggregates in a big stockpile shall be done
by: A RIGHT 1
a. taking sample from the bottom, middle and top of the
stockpile
b. shoveling-off the surface at the bottom of the stockpile and
taking full sample thereat
c. shoveling-off the surface at the middle of the stockpile and
taking full sample thereat
d. None of the above
49. When taking three (3) or more samples of aggregates to
be combined for one (1) material sample, D RIGHT 1
a. the small samples must be packed in separate sample bags.
b. the small samples must be obtained from dfferent lots
c. the small samples should of approximately equal size
d. None of the above
50. Sample of aggregate base course material when tested for
quality passed the requirements except grading , what will D RIGHT 1
you recommend?
a. Reject the material
b. Replace the material
c. Accept the material at an adjusted price
d. Reprocess the material by blending
51. The purpose of driving test piles? A RIGHT 1
a. To determine the required pile length
b. To determine the cross-sectional area of the pile
c. To determine the actual number of piles needed
d. None of the above
52. Test reports on thirteen (13) concrete beam samples
indicate that loading was stopped after reaching the required A RIGHT 1
flexural strength of 550 psi. This practice is:
a. Improper because test procedure provides that the test
should be carried out to failure
b. Improper because test procedure was stopped without
basis.
c. Proper because the strength specification for concrete
pavement is 550 psi.
d. Proper because the test should not be carried out to failure
since the machine may be damaged
53. Which of the following is true regarding the rebound
hammer (Schmidt) test for concrete? B RIGHT 1
a. The test is used to determine the uniformity of concrete
b. Can be used as a substitute to direct methods of
compressive strength determination such as tests on cored
samples
c. Is a simple and versatile test method which can be used
even on rough concrete surfaces.
d. all of the above
54. What is not the most commonly accepted measure of the
hardness of concrete? C RIGHT 1
a. Soundness Test
b. L.A Abrasion Test
c. Petrographic Test
d. Fractured Face Test
55. The purpose of capping concrete cylinders prior to testing
for compression is to: B RIGHT 1
a. Protect the ends of the cylinder from premature breaking
resulting from improper application of load
b. Provide smooth, flat ends that are perpendicular to axis of
the sample
c. Prevent cylinder from tilting
d. To maintain the verticality of the cylinder
56. The amounts of materials passing the No. 50 and No. 100
sieves are important to concrete aggregates because: B RIGHT 1
62. What is the minimum test requirement for riprap boulders B RIGHT 1
a. Stone size and specific gravity
b. Stone size or weight test and inspection report on
assessment of stone soundness
c. Stone size or weight test and abrasion test
d. None of the above
63. Consolidation test is usually performed on ________
samples. B RIGHT 1
a. Disturbed
b. Undisturbed
c. Consolidated
d. Both a and b
a. 25 Mpa
b. 30 Mpa
c. 20 Mpa
d. 28 Mpa
65. The following are generally true in the production of high
strength concrete, except: D RIGHT 1
a. Coarse aggregate should be obtained from crushed rock to
give the best cement/ particle bond.
b. Smaller-size aggregates are preferred as more area is
available for cement bonding
c. Admixtures include accelators and retarders.
d. all of the above
66. The following properties of asphalt mix can be
determined in a core sample, except for: A RIGHT 1
a. Index of Retained Strength
b. Asphalt Content
c. Grading
d. Specific Gravity
67. In how many hours should concrete core samples be
submerged in water before subjecting them to compression C RIGHT 1
test?
a. At least 30
b. At least 35
c. At least 40
d. At least 45
68. The apparent omission of a detailed description or
definition concerning the quality of materials in the plan and B RIGHT 1
specification shall be regarded to mean that:
a. Any material can be used
b. Materials of first class quality are to be used
c. Materials that are recommended by the contractor can be
used
d. None of the above
69. Stability of an asphalt pavement is the ability to resist
shoving and rutting under traffic loads B RIGHT 1
a. more medium size sand
b. angular and rough aggregates
c. more asphalt
d. b and c
a. 2 hours
b. 4 hours
c. 6 hours
d. 8 hours
71. The following can be used to help stabilize slope except: C RIGHT 1
a. Vetiver grass hedgerows
b. Legumes
c. Grass Cover
d. Trees
72. In bituminous plant-mix surface course, the temperature
of the mix shall have an allowable of: D RIGHT 1
a. ± 5 Degrees Celcius
b. ± 10 Degrees Celcius
c. ± 15 Degrees Celcius
d. ± 20 Degrees Celcius
a. Abrasion Test
b. Triaxial Test
c. Consolidation Test
d. CBR Test
77. It is essential to soil mechanics work that dying ovens are
preset to a temperature of: A RIGHT 1