Ref No.: VCS/IGL/2018-19/1186 DATE- 13 Nov. 2019
To,
M/s. G.L Golden
Plot No. 698/22, Street No. 15,
Shivaji Park,
Gurugram, Haryana - 122001
Subject: Status of Physical Verification of Material, Material Consumption and RA-bill for the
month of October-19.
Dear Sir,
With reference to awarded work P.O for laying of steel pipeline in NCT of Delhi & NCR region, following are
the status of RA bill, submission of documents & reports for the month of October-19.
It is found that you have failed to submit RA bill of PO 6500005287, 6500004622 & 6500004774 and
Material Consumption Report of PO 6500005287 & 6500004774 as well as Material Physical Varification
Report of PO 6500005287, 6500004616, 6500004622 & 6500004774 of October month even after several
follow up and mail reminders.
As discussed with M/s IGL & as per tender Clause “The contractor shall raise invoices, Material consumption
and Physical verification on monthly basis for works carried out duly certified by Engineer-in-Charge within
one month.
As per tender Clause “The contractor shall raise invoices on monthly basis for works carried out duly
certified by Engineer-in-Charge. The contractor to ensure that the invoices of completed work should be
raised & duly certified by Engineer-in-charge within one month to avoid any statutory penalties on delay in
paying taxes”
As per SCC clause 18.2 “You will be liable to withhold the 200% amount from upcoming RA Bill for the
balance material as shortfall”
Hence, you are instructed to submit monthly reports and bills on regular basis, otherwise you will be liable to
take action along with penalties as per the tender terms & conditions.
You’re sincerely,
Rahul Aditya
Project Coordinator (Steel)