Meeting
Meeting
2.0 Progress
2.1 Pile concreting 71%
No of piles finished 37 Nos
Total number of Piles 49 + 03 at +0.0 level
No. of piles ready for conc. 04 [02 screed done + 02 PDA]
Date of completion of all pile 07-06-2017 [According to programme]