Agenda

1.0 Foundation stone laying


1.1 04nos piles to be concreted in 4/H, 5/H,
1.2 Fill the area with quarry dust
1.3 Construct a concrete pit 1.0m x 1.0m x 600mm deep to lay foundation stone
1.4 Ladder or step to go to foundation laying area
1.5 Canopy
1.6 Table
1.7 Chairs for 05 nos priests

2.0 Progress
2.1 Pile concreting 71%
No of piles finished 37 Nos
Total number of Piles 49 + 03 at +0.0 level
No. of piles ready for conc. 04 [02 screed done + 02 PDA]
Date of completion of all pile 07-06-2017 [According to programme]

2.2 Quarry dust filling, Tie beams & slab concreting


Total completion date 16-06-2017 [According to programme]