CONSTRUCTION OF PROPOSED Doc.

No: LHP/MS/36
RESIDENTIAL PROJECT AT 104 CHITHRA Revision: 2
LANE, COLOMBO 5
FOR Date: 17//12/2019
ASIA BROADCASTING (PVT) LTD

METHOD STATEMENT FOR INSTALLATION OF BUILDING

EARTHING SYSTUM
OBJECTIVES: Installation of ground earth system to protect building due to lightening.

REFERANCE: Shop drawings

Data sheets/broachers in material approval/ IE regulations

Inspection

EQUIPMENTS: Digital Earth tester

Mamoty, crow bars, Shovels, pans

No Procedure Responsibility Checked by Records


1 Mark the location minimum 1.5 away from the Tec. Officer SEE
building.
2 Request for Inspection Tec. Officer SEE

3 Excavation for pits will be done manually at site Foreman Tec. Officer
using mamoty, crow bars, shovels etc.
1m x 1m x d (d to be decided at the site accord
to the soil condition and the earth resistance
but not less than 1.5.0m)
4 The copper rod buried and copper tapes / bare Tec. Officer SEE
copper conductors to will connecting using
necessary clamping system.
5 Cu tape and Cu rod will be connected inside the Tec. Officer SEE
320mm x 320mm x 190mm Concrete
Inspection pit
6 Request for Inspection Tec. Officer SEE
7 Using the digital earth tester, measure the Tec. Officer SEE
resistance of the electrodes in accordance with
the test equipment manufacturers’ instructions
and BS7430.
Testing will be carried out in accordance with
the requirements of clause 16 of BS7430.
Test electrodes will be installed in accordance
with BS7430.
8 Record the results on test sheet and reconnect Tec. Officer SEE
the earth conductor to the electrode.
9 Ensure the HSE during the entire process SEE PM

OUTPUT RECORDS:

1 Inspection

Prepared by Approved by
Signature
Name Pradeep Priyadarshane Prasanna Perera
Designation TO PM
Date 17-12-2019 17-12-2019