Programme of windows painting

3RD FLOOR
Programme
Item No Description Start Finish
1 Surface preparation 6-Jan-20 15-Jan-20
2 Rasin barrier application 10-Jan-20 20-Jan-20
3 Glass fixing 20-Jan-20 30-Jan-20
4 1st Under coat application 22-Jan-20 10-Feb-20
5 2nd Under coat application 31-Jan-20 13-Feb-20
6 1st top coat application 5-Feb-20 18-Feb-20
7 Final coat application later later

2ND FLOOR
Programme
Item No Description Start Finish
1 Surface preparation 10-Jan-20 22-Jan-20
2 Rasin barrier application 15-Jan-20 28-Jan-20
3 Glass fixing 1-Feb-20 15-Feb-20
4 1st Under coat application 5-Feb-20 20-Feb-20
5 2nd Under coat application 12-Feb-20 25-Feb-20
6 1st top coat application 20-Feb-20 29-Feb-20
7 Final coat application Later later
1ST FLOOR
Programme
Item No Description Start Finish
1 Surface preparation 20-Jan-20 2-Feb-20
2 Rasin barrier application 25-Feb-20 2-Mar-20
3 Glass fixing 28-Feb-20 12-Mar-20
4 1st Under coat application 1-Mar-20 15-Mar-20
5 2nd Under coat application 5-Mar-20 20-Mar-20
6 1st top coat application 25-Mar-20 7-Apr-20
7 Final coat application Later Later

GROUND FLOOR
Programme
Start Finish
1 Surface preparation 20-Jan-20 2-Feb-20
2 Rasin barrier application 25-Feb-20 2-Mar-20
3 Glass fixing 28-Feb-20 12-Mar-20
4 1st Under coat application 1-Mar-20 15-Mar-20
5 2nd Under coat application 5-Mar-20 20-Mar-20
6 1st top coat application 25-Mar-20 7-Apr-20
7 Final coat application Later Later