CONSTRUCTION OF PROPOSED Doc.

No: LHP/MS/020
RESIDENTIAL PROJECT AT 104 CHITHRA Revision:0
LANE, COLOMBO 5
FOR Date: 30/06/2017
ASIA BROADCASTING (PVT) LTD

METHOD STATEMENT FOR FIXING FW FOR RETAINING WALL


OBJECTIVES: To formulate guide lines for erecting formwork for retaining wall.

REFERANCE: Drawings

Inspection

Method statement

EQUIPMENTS: Form ties

25 mm ‘P’ cones

Pipe supports

‘U’ Jacks & ‘T’ Jacks

Claw hammers

Mobile crane

No Procedure Responsibility Checked by Records


1 Fabricate the frame work by fixing 50mm x 50 Foreman AE
mm timber members to 15mm thick ply board TO
2 Transport the shuttering formwork to the Foreman AE
location by using mobile crane. TO
3 Fix the shuttering formwork on one side as per Foreman AE
the attached drawing TO
4 Fix the ‘P’ cone on to a timber formwork & Foreman AE
complete fixing form ties one side. TO

5 Join the formwork in one side with nails Foreman AE


TO
6 Place the formwork on other side Foreman AE
TO

7 Using a drill machine make necessary holes to Foreman AE


fix ‘P’ cone on the adjoining side TO
8 Complete the FW with necessary pipe supports Foreman AE
& locking arrangements TO

9 Check the alignment with reference to grid line Foreman AE


or off line pre established. Checks the plumb. TO
Necessary adjustment in plumbing done by
adjusting pipe supports
10 Erect flat form to checking, pouring of Foreman AE
concrete. TO

11 Call for inspection AE SM

9 Ensure the HSE during the entire process Safety officer SM

OUTPUT RECORDS:

1 Inspection

Prepared by Approved by
Signature
Name Haritha Jayasinghe Rohith Thirimavithana
Designation AE PM
Date 30-06-2017 30-06-2017