25-Jan-20
31-Jan-20
25-Jan-20
31-Jan-20
25-Feb-20
8-Mar-20
25-Mar-20
30-Mar-20
7-Mar-20
15-Mar-20
20-Mar-20
27-Mar-20
10-Apr-20
24-Apr-20
30-Apr-20
17-May-20
30-May-20
15-Jun-20
Progress of windows painting up to 2020.02.17
3RD FLOOR
Total Progress
Item No Description Sash Frame Sash Frame
1 Surface preparation 48 24 47 20
2 Rasin barrier application 48 24 47 20
3 1st Under coat application 48 24 47 20
4 2nd Under coat application 48 24 47 20
5 1st top coat application 48 24 20 20
6 Final coat application 48 24 0 0
2ND FLOOR
Total Progress
Item No Description Sash Frame Sash Frame
1 Surface preparation 54 24 43 18
2 Rasin barrier application 54 24 43 18
3 1st Under coat application 54 24 43 18
4 2nd Under coat application 54 24 43 18
5 1st top coat application 54 24 43 18
6 Final coat application 54 24 0 0
1ST FLOOR
Total Progress
Item No Description Sash Frame Sash Frame
1 Surface preparation 32 17 20 12
2 Rasin barrier application 32 17 20 12
3 1st Under coat application 32 17 20 12
4 2nd Under coat application 32 17 20 12
5 1st top coat application 32 17 0 0
6 Final coat application 32 17 0 0
GROUND FLOOR
Total Progress
Sash Frame Sash Frame
1 Surface preparation 32 17 20 5
2 Rasin barrier application 32 17 20 0
3 1st Under coat application 32 17 20 0
4 2nd Under coat application 32 17 20 0
5 1st top coat application 32 17 0 0
6 Final coat application 32 17 0 0