PROJECT: PROJECT NAME SITE NO.

CHECK SHEET FOR TESTING AND COMMISSIONING EARTHING AND Sheet No.
EARTH BONDING
SUBCONTRACTOR:

EQUIPMENT NO. : SEQUENCE NO. :


SERIAL NO. : DATE :
LOCATION : COMMISSIONED ON :

Checked
ITEM POINTS TO BE CHECKED by REMARKS
1 PHYSICAL CHECKS
a. Check the earth electrodes in earth pits for proper
installation and connection.
b. Check the protective conductors from the earth
installation and connection.
2 EARTH ELECTRODE RESISTANCE
a. Remove the conductor connection from the
electrodes.
b. Measure earth electrode resistance by using an
earth meggar.
c. Repeat (1) and (2) above for all pits and tabulate
readings.
3 CONTINUITY TEST
a. Check proper earth bonding by checking continuity
of protective conductor by a D.C. ohm meter.
b. The above to be checked for all protective
conductors to various equipment.
c. Check continuity resistance between the main
earth terminal of the MDB/DB and the farthest
equipment by a DC ohm meter.

THE ABOVE POINTS HAVE BEEN CHECKED AND FOUND TO COMPLY WITH CONTRACT
SPECIFICATIONS.

CHECKED BY SUBCONTRACTOR: _____________________


Signature

WITNESSED BY CLIENT: ______________________


Signature

WITNESSED / ACCEPTED BY CONSULTANT: ____________________


Signature