Professional Documents
Culture Documents
Version: 0.2
Date of Issue: 20/12/2016
CDRL Line Number: N/A
Document Control
This is a controlled document.
Printed versions are uncontrolled.
Full document version history and draft iterations are available through viewing server properties on
the JHR IMS where this document is stored.
Version History
Version No Date Prepared By Reviewed By Approved By
1.0 20/12/2016 Iain Murray Stewart Rendell James Zeaiter
David Mackney
Description of Changes
– Initial version – compilation of extant procedures into one manual
Description of Changes
–
Disclaimer. This document was prepared for use on the CRN Network only. John Holland Rail Pty Ltd (JHRPL) makes
no warranties, express or implied, that compliance with the contents of this document shall be sufficient to ensure safe
systems or work or operation. It is the document user’s sole responsibility to ensure that the copy of the document it is
viewing is the current version of the document as in use by JHRPL. JHRPL accepts no liability whatsoever in relation to
the use of this document by any party, and JHRPL excludes any liability which arises in any manner by the use of this
document.
Copyright. The information in this document is protected by Copyright and no part of this document may be reproduced,
altered, stored or transmitted by any person without the prior consent of JHRPL.
Engineering
management
procedures
1.2 Application
This Manual sets out general policy and requirements for the Engineering Design Management
System to be implemented on JHR CRN designs.
The requirements of this manual shall apply to all design work performed by or for JHR CRN, as
defined within Section 2 of this Manual. The Principal Discipline Engineer/s or the Manager
Engineering Services may modify the requirements of this manual to suit the design task based on
an assessment of the complexity, number of interfaces, technology and safety criticality of the
asset/system.
2 REQUIREMENTS
2.1 Classification and Referral
For the purposes of defining the significance of a design task and the volume of work required to
deliver that task, the following definitions have been developed to allow classification and facilitate
resource allocation.
Minor Task — a minor task is one that can be completed in less than 40 hours of design effort and
can either be completed entirely within one discipline or requires only minor inputs from other
disciplines. Telephone inquiries and processing of simple design changes or repair schemes are
examples.
Minor Project — Minor Projects are those where:
– The expected design completion time is assessed as between 40 and 150 hours of design effort,
and/or
– A significant level of design input is required by two or more disciplines,
Major Project — Major projects are those where:
– The expected design completion time is estimated to exceed 150 hours of design effort, and/or
– A substantial level of input is required by two or more disciplines, and/or
– A safety critical system is involved or new/novel technology is being applied to a safety critical
system and/or
– The complexity of the project e.g. New Train communication system is assessed as requiring
major project planning and reporting disciplines and visibility.
Task requests shall be referred to the Manager Engineering Services who shall arrange for an initial
assessment and determination of the likely classification of each request. This will set out the level
of detail required and the appropriate steps to follow from this manual. The default minimum steps
in this process are development of a) concept design, b) preliminary design and c) detailed design
although this can be varied so long as there is visibility and justification to do so. Where there is a
potential change to the functionality of the CRN the proposal must be approved for development by
the Configuration Control Board.
If the request requires a Project Manager, the Manager Engineering Services and Infrastructure
Manager will confer and appoint one.
Design Interfaces
Design Brief Develop Concept design (2.8.1)
(2.8.6) (2.10.1)
Use and
Construction
Maintain
Configuration
Management As-built Design
records (2.11.1) Records (2.12)
2.3.3 Registration
The Project Manager shall register each request as a proposal in the Design Projects Register (DPR)
on receipt and then proceed to:
– Establish whether the scope of the project is adequately defined, and
– Prepare an offer of service
The Manager – Engineering Services shall maintain a project register (DPR), to be used for
registering all Minor and Major projects.
Typical inputs:
– Identified operational / functional objectives
– Identified stakeholder inputs
– Confirmed existing asset configuration
– Desktop survey, geotechnical, environmental, property and services assessments,
– Concept engineering
– Existing operational interfaces
– Comments log
Outputs
– Concept design Options report
Design Management Manual | 19
– Identification of all (typically 2-6) potential options
– Identification of pros and cons for each option
– Comparison of options – scope, configuration, operation, hazards, risks etc.
– Concept design drawings - Schematics, concept sketches for each option
– Project schedule estimate (for each option if required) to a +/- 50% accuracy, including all design,
procurement and construction works
– Project cost estimate (for each option if required) to a +/- 50% accuracy, including all design,
procurement and construction works
Appendix B
Roles and Responsibilities
Appendix C
Engineering Specifications
Appendix D
Requirements Analysis,
allocation & Traceability
Appendix E
Design Standards
Appendix F
Interface Definition and
Management
Appendix G
Hazard and Risk Analysis
CRN-MAN-ENG-001 Appendix H
Design Management Reliability, Maintainability &
Manual Availability
Appendix I
Design Approval
Appendix J
Design Verification
Appendix K
Design Validation
Appendix L
Technical Design Reviews
Appendix M
Design Change Management
Appendix N
Design Documentation &
Records
Appendix O
Integrated Support
Requirements
Appendix P
Maintenance Requirements
Analysis
Figure 3
Activity Method Statement (AMS) Linked to the WRA. The AMS considers risks and
controls at an activity level. It is a component of the
JHR SQE RM process
Principal Risk Register (PRR) A register of the high level hazards, contributing factors
and controls applying to the operation of the JHR CRN.
The PRR is used as a source document to identify
hazards and controls.
Task Risk Assessment A step in the SQE RM process where the tasks to be
undertaken are reviewed in the field by staff
undertaking the task to check that hazards have been
properly identified and assessed and that the proposed
controls are effective. The TRA is used to capture any
modifications required due to site constraints
subsequently identified and form a component of the
site briefing.
Validation Design validation is the process of ensuring that the
final product conforms to defined user (client) needs
and/or requirements. (AS/NZS ISO 9001: 2008).
Variance A Variance (alternative terms are Deviation, Waiver,
and Concession) is used to approve a departure from
the approved “For-Construction” design baseline.
Variances are normally approved for a specific number
of items or for a limited period. If a Variance is to be
permanent it must be processed as a DCN.
Verification The verification process is carried out to ensure that
the output of a design stage (or stages) meets the
design stage input requirements. (AS/NZS ISO 9001:
2008).
Workplace Risk Assessment (WRA) A high level assessment of hazards, risks, and controls
associated with a scope of works. It is a component of
the JHR SQE RM process.
Corrosion The item shall be capable of operation The item shall be constructed of 18-8
Resistance in corrosive environments (specify). grade stainless steel.
Reliability The system shall achieve an MTBF of The system shall incorporate redundant
24000 Hours when operated within the widgets in all circuits.
specified environment.
Environmental The item shall withstand temperatures The item shall be fitted with thermal
Design Criteria ranging from –20°C to + 60°C without insulating blankets and a fan capable of
damage (specific output).
Performance
specification
Software Interface
Detail technical
development specifications or
specifications
specifications drawings
Product or
Software product
process
specifications
specifications
The following table provides a summary description of the types of specification and potential uses
within JHR CRN.
Performance Used to define the operating performance and Establish key operating
Specifications characteristics of complete systems, sub-systems parameters for new
or items. Generally used for development of a new infrastructure.
system, sub-system or item.
Detail Used to define the detailed technical requirements Development specifications
Specifications / of sub-systems or items. Generally used for new for inclusion in an RFT.
Software development of an item or sub-system. Specifications for
Development development of a new JHR
Specifications CRN standard item.
Product Used to define detailed technical characteristics of JHR CRN Standards
Specifications developed items, processes or materials. Particular Specifications
Generally used for further procurement of
Material Specifications.
equivalent items or to define specific requirements
or characteristics within a Functional or Detail Specifications or Drawings for
Specification. Standard Designs
Relevant
Customer / user standards & other
specification compliance
Requirements analysis
requirements
Functional &
Validation
performance
requirements &
requirements
methods
to be met by
design output
Allocate functions
Traceability
and requirements
to systems, sub-
systems &
Requirements allocation
configuration
Establish
items
additional
(derived)
requirements &
characteristics of
design solution Establish
design &
validation
requirements
database
Item 1A-2
Item 1-1
Item 1A-3
Requirement 1
Item 1-2
System 1
Requirement 2 Item 1-3
Item 1-4
Requirement 3
Interface
Requirement 4 requirements Sub-system 2A Item 2A-1
Item 2-4
Operational,
Management &
Safeworking
Procedures
Physical &
Operational Functional Interfaces
Conditions of Use eg. within the same system
Speed Axle, Loading [may be Hardware,
Vehicle Configuration, Software, Electrical,
Traffic Density Data]
Phyiscal
Interfaces with
Interfaces Installations on CRN
with Regulatory Agencies property owned by other
eg. ITSR Electrical Agencies eg.
Pipelines, Private
Management Systems Crossings, Roads
Interfaces eg. Ramsys,
PCR, GIS, Maximo
PRR and
Impact assessed
Asset need Subsidiary Risk
Infrastucture Management
Configuration
Brainstorm
Management
Assists with the
planning Initial WRA
process
Y Is Project N
End
viable?
Engineering Procedures
Transfer N
Close Out
hazards?
Engineer design
cycle (Fig 2)
Informs Interactive Y
process through
design
Transfer hazards
and mitigation
Infrastructure
Management
Transfer Y Maintain
Informs Delivery
hazards? and operate
N
SQERM ARM
AMS TRA
Close Out
The process map in shows the progressive identification and analysis of hazards and risks aligned
to each major stage of design, as well as the primary processes and support tools to be used. The
process map represents the most complex case, that of a major project, but less complex design
tasks shall incorporate one or more of the major steps, as defined within this Manual.
OBTAIN
SPECIFICATION &
REQUIREMENTS
CARRY OUT
END
FMECA
PREPARE
DETAILED
DESIGN CARRY OUT
MAINTENANCE
REQUIREMENTS
ANALYSIS
CRITICALLY
REVIEW THE
DETAILED
DESIGN
FORMULATE FORMULATE
PROCEDURES, SCHEDULED
CONTROLS & MAINTENANCE
TRAINING PROGRAM
HAZARD SOURCES
FROM FROM
FROM THE
DANGEROUS HAZARDOUS
ENVIRONMENT
GOODS SUBSTANCES
RISKS
TO TO
TO THE
MAINTENANCE CONSTRUCTION
PUBLIC
STAFF STAFF
TO
TO TO THE
OTHER
OPERATORS ENVIRONMENT
EQUIPMENT
The set of potential hazards and risks shown in Figure 10 form the basis for analysis and action
during the design phases. For major new projects this will involve progressive identification and
refinement as the design evolves. Assessing changes to an existing design involves the same range
of considerations but may be accomplished by review of existing data and limiting the analysis to
take account of the effect of the changes.
The scope of the processes to be applied in each set of circumstances is set out in the following
paragraphs.
Total Time
for a continuously operating system.
Total Time
OR, in terms of Reliability (MTBF) and Maintainability (MTTR) measures, as:
(A t) = MTBF
MTBF+ MTTR
H-5 Reliability
Designing for reliability is essentially an iterative process. It involves several key steps that are
applicable for all minor and major projects, as follows:
• Determine the targets or level of performance to be achieved. This should normally be
included in the engineering specification, and is typically specified at major system or installation
level e.g. Track, signaling, or Tunnel Ventilation system
– Establish a mathematical model (or models) to represent the architecture selected for the design.
This will be used to test the predicted performance of selected equipment against target levels
– Allocate targets to progressively lower levels within the design architecture. The ultimate
requirement is to establish the predicted level of reliability or maintainability characteristic for each
major item (or groups of items, such as OHW section insulators). Targets established for
systems, sub-systems and individual items are commonly referred to as reliability budgets
– Select equipment based on established targets
– Test the predicted level of performance against targets. Identify shortfalls
– Introduce improvements to the design or to the proposed architecture to meet the required target.
ITEM C
R (t) = 0.95
ITEM A
R (t) = 0.9
ITEM B ITEM C
R (t) = 0.99 R (t) = 0.95
ITEM A
R (t) = 0.9
ITEM C
09 Simple Reliability Block Diagram V1.0 18 Nov 2002
R (t) = 0.95
Primary responsibility for the reliability performance of designs rests with the designer. Support from
Subject matter experts must be a highly interactive process, with continuous input from designers to
ensure that:
– The mathematical reliability model is representative of the actual design of the infrastructure
– Selection of equipment and other relevant changes in the design architecture is promptly advised
to the ISU
– Failure rate data to be used in the model is derived from the best available source and is
consistent with the intended environment in which the item is to be used. Data may either be
from manufacturer’s predictions for new equipment, or from the failure data available for CRN
equipment, or a combination of the two
– Data used in the modelling and estimation process is representative for the intended use of the
equipment. Estimates obtained from manufacturers for new equipment, or data for existing items
that are to be used in a more severe environment, may need to be factored or de-rating factors
applied to ensure that it is representative.
Reliability reports and models developed as part of the design process shall be maintained as part
of the design record for the equipment.
H-9 Maintainability
Maintainability requirements may also be included in the specification, either directly in the form of
MTTR targets for specific equipment or in general terms, such as a requirement to perform all
scheduled maintenance during access windows, which may directly influence characteristics of the
design. These may include tolerance to failures, through the incorporation of redundant features
(which also affect reliability performance) and/or fault diagnosis methods and accessibility features,
to permit rapid isolation and correction of problems.
Maintainability characteristics are typically assessed through a systematic review of the design, to
assess infrastructure support requirements including fault finding, scheduled maintenance and
repair/replacement and to identify areas that do not meet the general criteria included in Appendix
G. The key consideration in each case is to assess how a task may be accomplished and the safety
and efficiency with which it may be performed.
Estimates of maintainability (i.e. MTTRs) are also used in conjunction with reliability predictions to
assess the likely availability of the system. Clear definition of the rules for measuring MTTR are
essential where the parameter is used for this purpose, or in any situation where achievement of
specific MTTR values forms part of the design validation process.
The most appropriate definition of MTTR for validation purposes is that it includes only the time taken
for direct fault finding and repair of faults. Administrative components of total downtime, such as the
delay in attending a fault or time awaiting spares or other resources, are generally outside of the
control of designers and are normally excluded from the estimates of MTTR.
H-15 Tendering
Equipment reliability or availability is to be used as a selection criterion for new equipment wherever
possible. This typically forms part of the Life Cycle Cost assessment carried out in the tender
selection phase, to establish the alternative which will provide the lowest cost of ownership over the
expected life of the infrastructure.
Tender specifications typically include an Engineering Specification (see Appendix C) and a contract
Statement of Work. The following requirements should be considered for inclusion in the tender
documentation in support of the reliability program:
– A requirement for the design Contractor to develop reliability models for nominated sections of
the design, and to report on the predicted reliability for the infrastructure in advance of technical
reviews, or
– A requirement for the Tenderer to provide specific reliability information for the product offered in
response to the JHR CRN specification
– A requirement for the Contractor to complete and deliver a FMECA, which will be used to validate
reliability models, to support Safety and Hazard Analysis and as a basis for establishing
programmed maintenance requirements
– An availability model that takes account of predicted reliability and maintainability characteristics
(reactive repair times as well as completion times for scheduled maintenance inspections).
Additional information must be requested as part of the tendering process to provide a basis for
comparative assessment of bids received.
Requirements
analysis &
allocation
Verification of
stage output
Design stage
Verification of
stage output
Design stage
Verification of
stage output
Design
Design stage
approval
Verification of
stage output
“For-construction
baseline” Design output Validation
“As-built” baseline
Final design
K-4 Similarity
Some designs for items or systems may be validated by comparison with similar equipment
performing an equivalent purpose and operating in an equivalent environment. This method is
particularly relevant for validation of configuration changes for existing infrastructure, or where type-
approved items or standard designs are to be incorporated in a new system or application.
Similarity may be employed as a validation method provided that the following specific conditions
are met:
– The item used for comparison has already been type-approved by JHR CRN or by a test facility
accredited by NATA or equivalent authority, and
– The intended conditions of use for the equipment can be shown to be equivalent to the conditions
under which previous validation tests were carried out, and
– Evidence of the results of previous tests or other validation method is available. This shall be in
the form of actual test results or certificates issued by an accredited test facility, demonstrating
that the requirements, performance indices, physical characteristics, constraints or functions of
the equipment tested have been met, or
– There is detailed information available to demonstrate the performance of the item within the
CRN/ARTC/Sydney Trains system when operated for an equivalent purpose under equivalent
conditions. Such information shall be compiled and incorporated as part of the validation record
for the equipment.
The use of similarity as a validation method shall be justified and documented in each and every
case and supporting evidence incorporated in the validation record for the equipment or system. An
existing type-approval does not automatically qualify the item for use within a new design, particularly
where the operating environment or conditions of use are different. The use of existing type approved
equipment or designs must be re-validated for the intended application in every case.
K-7 Testing
K-7-1 General Requirements
Testing is the preferred method of design validation, either stand alone or in combination with
analysis techniques where it is not possible or feasible to test over the entire operating spectrum.
Testing is applicable to both hardware and software products and to integrated hardware and
software designs.
Tests shall be designed to validate performance characteristics of the design against specification
requirements. Testing may be carried out on discrete items or on systems/installations during
integration or commissioning, dependent on the scope and purpose of the test. Examples of test
activities include functional tests, physical tests, testing of materials to establish performance in
corrosive environments and environmental tests.
Validation testing shall be designed to demonstrate the performance of the item over the full set of
operating conditions covered by the specification. This includes tests designed to demonstrate the
ability of the item to operate satisfactorily over the specified design life, such as the use of tests at
elevated levels of temperature and/or vibration to simulate accelerated life conditions.
K-8 Commissioning
Commissioning may contribute to the total validation process but is not itself a form of validation.
The purpose of commissioning as part of the validation process shall be to ensure that:
– Elements of the design e.g. individual components & equipment, have been separately validated
through one or more of the methods defined in Appendix C and that detailed results are available
Develop project
concept & define
Develop & refine functional baseline
requirements
Develop
engineering System concept
specification & review (major
RFT (where project only)
applicable)
Requirements
System definition
Establish development baseline
Production (As-built)
baseline
Project enters
service
Figure 13: Complete technical review process for JHN CRN application
Table 3 summarizes the types of Technical Review that may be conducted for JHR CRN design
projects. The following paragraphs provide an outline of the purpose and application of individual
reviews.
System Concept Before Engineering Major projects only. Ensure that the specification and
Review (SCR). Specification and RFT contract SOW are complete and
are finalised properly represent client
requirements
System Early in preliminary Major and Minor Ensure that Specification
Definition Design Phase Projects. requirements are complete and
Review (SDR) unambiguous.
Preliminary Completion of Major projects. Verify that preliminary approach
Design Review Preliminary Design May be combined with is consistent with specified
(PDR) CDR for Minor projects. requirements.
Critical Design Completion of Detail Major Projects. Verify that detail design appears
Review (CDR) Design The requirement may to meet design intent for the
be met by a simplified project.
process for Minor Provides a major input for final
Projects acceptance of sub-contract
design projects.
System Construction Major and Minor Verify that all testing and
Verification Projects verification action is complete
Review (SVR) prior to final commissioning and
project acceptance.
Physical Construction / Major and Minor Comparison of “as-built”
Configuration Commissioning Projects configuration with design
Audit (PCA) documents.
YES
Major Change?
See Paragraph 5.3
YES
Design Approved
“for Construction”?
NO
Submit Change to Delivery
Manager for Action
No DCN
Required
JHR CRN will also adopt ASA CAD Resource Files listed at the ASA website
In adopting the ASA CAD Manual and Resources the following modifications apply:
References to ASA will be replaced with JHR CRN
Titles and Title Blocks ASA will be replaced by JHR – CRN and the Transport NSW logo will
be replaced by the JHR – CRN logo.
Configuration change
management (see ED
0015)
Analysis
software
Change in Change in
facilities or training
tools? requirements?
Maintenance
requirements &
TMP? (see ED
Change in 0019)
Change in
operating or
spares support
maintenance
required?
procedures?
Integrated Support
analysis
O-9 Training
The introduction of new assets, or changes to the design of existing infrastructure, may create the
need to train operators and/or maintenance staff on the use and maintenance/repair of the
equipment.
The ILS Manager, in conjunction with the design engineers responsible for a task or project, shall
carry out a preliminary assessment of the change, to determine whether the scope of the change
warrants additional or different staff competencies from those currently specified.
Assistance shall be sought from the Manager Organisational Development to conduct detailed
training needs analysis to determine the best option to acquire the required competencies. The
needs of existing field staff and the training of new employees are to be considered in making this
assessment, to ensure that training requirements are maintained in line with the approved
infrastructure configuration.
In conjunction with Manager Organisational Development, Engineering Services staff shall develop
guidelines and instructions for On-the-Job Training where this will adequately meet the need.
Requirements for training are to be included in the incorporation instructions for any approved
configuration change or for projects introducing new equipment.
Maximo
Task requirements
Effect of failure/
criticality
(What happens if it
does?)
Maintenance task
list
Maintenance task
options
(What can be done?)
Lack of lubrication
Machine binds or
jams Bearing failure No output
Misalignment EFFECT OF
FAILURE MODE FAILURE
CAUSE OF FAILURE