You are on page 1of 12

BORDER ROAD ORGANISATION / PROJECT BRAHMANK

Survey, investigations and preparation of Detailed Project Report Final Detailed Project Report
for improvement of road MIGGING – TUTTING from km 13.560 to
35.00 to NH double lane specifications in upper Siang Dist. of Volume 3 - Material Report
Arunachal Pradesh

TABLE OF CONTENTS
3.1 Introduction............................................................................................................................ 2
3.2 Programme of Investigations .............................................................................................. 2
3.3 Investigation Procedure....................................................................................................... 2
3.4 Investigation of Existing Pavement.................................................................................... 5
3.5 Materials for Embankment and Sub grade ....................................................................... 7
3.6 Sand, Aggregate, High Grade Fill and Granular Sub Base Material ............................ 8
3.7 Other Construction Materials .............................................................................................. 8
3.8 Miscellaneous ....................................................................................................................... 9

APPENDIX 1: THE DETAILED LABORATORY INVESTIGATION RESULTS

Spectrum Techno Consultants Pvt. Ltd. in JV with 1


LRP Consultant Consortium Pvt. Ltd.
BORDER ROAD ORGANISATION / PROJECT BRAHMANK FINAL DETAILED PROJECT REPORT
Survey, investigations and preparation of Detailed Project Report
for improvement of road MIGGING – TUTTING from km 13.56 to Volume 3 - Material Report
35.00 to NH double lane specifications in upper Siang Dist. of
Arunachal Pradesh

3.0 SOIL AND MATERIAL INVESTIGATIONS

3.1 Introduction

3.1.1 The project located in North-Eastern state of Arunachal Pradesh starts at


chainage from Pango location and ends 15 Km before Tutting village, near
Ningging village as a section of highway, along the Moying- Gelling border road.

3.1.2 The proposed alignment starts at Design chainage Km 15.00 near Pango Village
and end at chainage Km 35.00 near Ningging village, 15 kms away from Tuting.
The entire length road stretch passes through Hilly/Mountainous terrain and
almost travels parallel to Siang River, which is a tributary of River Brahmaputra.

3.1.3 The soil and material investigations for entire stretch of project road were
undertaken in accordance with TOR requirements, so as to identify potential
sources of construction materials, their quality and availability at site. This section
deals with the nature of investigations, procedures adopted and the tests
conducted on the soil, fill materials, borrow areas, aggregates and other materials
of construction. All tests were done in accordance with procedures and standards
described in BIS/IRC/AASHTO/BS standards wherever applicable.

3.2 Programme of Investigations

3.2.1 The programme for Soil and Materials investigations has been broadly divided
into the following groups:
a. Investigations of existing pavement.
b. Investigation of materials for embankment, sub grade, sub-base and Base
c. Investigation for Quarry sites and construction materials.
d. Investigations for availability of Water
f. Investigations for availability of Fly ash

3.3 Investigation Procedure

3.3.1 The material investigations were carried as under:-

(i) Soil samples were taken by digging trail pits of size1.0 m x 1.0 m and 1.0
m on the toe of the embankment to get natural moisture content, in-situ
density and other physical characteristics of the subgrade soil, including
CBR both at its natural moisture content and in-situ density by statically
compacting the samples.
Spectrum Techno Consultants Pvt. Ltd. in JV with 2
LRP Consultant Consortium Pvt. Ltd.
BORDER ROAD ORGANISATION / PROJECT BRAHMANK FINAL DETAILED PROJECT REPORT
Survey, investigations and preparation of Detailed Project Report
for improvement of road MIGGING – TUTTING from km 13.56 to Volume 3 - Material Report
35.00 to NH double lane specifications in upper Siang Dist. of
Arunachal Pradesh

(ii) Trial pits were dug on the existing pavement, one in each km to study the
pavement structure. Samples were taken from various layers of the sub-
grade soil to determine natural moisture content and in-situ density. DCP
tests were conducted on the subgrade to determine the CBR at in-situ
density and field moisture content.

(iii) Investigations on borrow materials were carried out to select material for
embankment construction and for granular sub-base.

(iv) Aggregates from the quarry’s sites were tested for their suitability and use
in various layers of the pavement, concrete and bitumen mixes.

(v) Identification of sand quarries.

(vi) The sources of other construction materials such as, cement, bitumen and
steel were identified.

(vii) Locating sources of water and its suitability for construction of road
pavements, including concrete for bridges and other structures.

3.3.2 For all the above investigations, the samples of soil, sand, crushed rock and
gravel for construction of pavement, bridges and culverts were tested as per the
laid down procedures and conforming to the Terms of Reference.

3.3.3 The quantum of investigations and extent of testing done to achieve the desired
objectives of the Feasibility Study/Preliminary Design Report are also indicated in
this section. The trial pits were dug up to sub-grade level so as to study the
pavement composition, field density and moisture content. Bulk samples were
collected for detailed study of the sub-grade soil. The various types of
investigations were carried out and are summarized below:

(i) Trial pits were excavated adjacent to toe of the embankment on natural
ground for collection of soil samples.

(ii) Condition Survey and determination of pavement composition by digging


trial pits along the stretch of road.

(iii) Conducting Dynamic Cone Penetration (DCP) tests on sub-grade and

Spectrum Techno Consultants Pvt. Ltd. in JV with 3


LRP Consultant Consortium Pvt. Ltd.
BORDER ROAD ORGANISATION / PROJECT BRAHMANK FINAL DETAILED PROJECT REPORT
Survey, investigations and preparation of Detailed Project Report
for improvement of road MIGGING – TUTTING from km 13.56 to Volume 3 - Material Report
35.00 to NH double lane specifications in upper Siang Dist. of
Arunachal Pradesh

embankment.

(iv) Statistically determine the CBR of the soil at natural moisture and in-situ
density by the use Dynamic Cone Pentameter (DCP).

(v) Identification of borrow areas for soil and granular sub-base.

(vi) Aggregates from various quarries were tested for specific gravity,
absorption, AIV, stripping tests, soundness etc.

(vii) Sources of sand for construction were identified and tested.

(viii) Investigations for water sources.

3.3.4 The standard test procedures were followed for soil sampling, field and laboratory
testing.

3.3.5 Codes adopted for testing are given as under :-

Type of Test Standards


Field dry density using sand replacement method IS 2720 Part 28 - 1974
Field dry density using core cutter method IS 2720 Part 29 -1975
Moisture content determination IS 2720 Part 2 (Section I)-
1973
Atterberg limits IS 2720 Part 5 -1985
Sieve analysis
- natural soils IS 2720 Part 4 -1985
- rock aggregates IS 2386 Part 1 -1963
Compaction test (Heavy Compaction) IS 2720 Part 8 - 1983
CBR and Swell IS 2720 Part 16 -1987
Aggregate impact value IS 2386 Part 4 -1963
Coating and stripping of Bitumen aggregate mixtures IS 6241-1971
Soundness of Aggregates IS 2386 Part 5 -1963
Flakiness and Elongation Index IS 2386 Part 1-1963
Water Absorption and Specific Gravity of aggregate IS 2386 Part 3 -1963
Stone Polishing Value BS 812 Part 114 -1989
10% Fines Value for Aggregate BS 812 Part 111 –1975

Spectrum Techno Consultants Pvt. Ltd. in JV with 4


LRP Consultant Consortium Pvt. Ltd.
BORDER ROAD ORGANISATION / PROJECT BRAHMANK FINAL DETAILED PROJECT REPORT
Survey, investigations and preparation of Detailed Project Report
for improvement of road MIGGING – TUTTING from km 13.56 to Volume 3 - Material Report
35.00 to NH double lane specifications in upper Siang Dist. of
Arunachal Pradesh

3.3.6 Soil classification was done according to Indian Soil Classification System (IS
1498).

3.4 Investigation of Existing Pavement

3.4.1 Test pits of size 1.5m x 1.5m x 1.5m were dug up at the edges and centre of the
proposed carriageway to know details of original ground level, soil type and
strength of soil.

3.4.1.1 The detailed study has however been carried out to take samples at each km,
developed moisture density curves for the samples and determined soaked CBR
value at 100% modified Proctor Densities. Selected samples were also molded
with varying compactify effort at OMC and curves developed for density soaked
CBR values. This study helps us to get CBR when densities are between 95-
100% of Modified Proctor Densities.

3.4.1.2 Observations on field moisture content and in-situ density are given in
Table- G/1-1& G/1-2 in Appendix -1. Moisture in the original ground level
varies from 8.9% to 31.7%. CBR values of the original ground level lies in
between 11.7% to 30.2% at their natural moisture content and at in-situ
densities.

3.4.2 Field Tests

3.4.2.1 Field Density Test

The field dry density of original ground level layer has been determined by sand
replacement method / core cutter method according to IS:2720 part 28 or 29
respectively. Bulk density of original ground level is determined at site by
weighing the sample using pan balance and moisture determination by speedy
moisture tests as well as by oven dry method in Laboratory by collecting original
ground level soil in airtight container. Although the samples have been collected
throughout the project stretch. The results of optimum moisture content,
Maximum Dry density, Atterberg’s Limits, sieve analysis and CBRs are given in
Table- G/1-1 & G/1-2 in Appendix -1.

3.4.3 Laboratory Test

3.4.3.1 Moisture Content

Field moisture content of original ground level samples was determined by oven
dry method as per IS:2720 (Part 2) for every test pit location and test results are
Spectrum Techno Consultants Pvt. Ltd. in JV with 5
LRP Consultant Consortium Pvt. Ltd.
BORDER ROAD ORGANISATION / PROJECT BRAHMANK FINAL DETAILED PROJECT REPORT
Survey, investigations and preparation of Detailed Project Report
for improvement of road MIGGING – TUTTING from km 13.56 to Volume 3 - Material Report
35.00 to NH double lane specifications in upper Siang Dist. of
Arunachal Pradesh

given in Table- G/1-1 & G/1-2 in Appendix -1.

3.4.3.2 Grain Size analysis

3.4.3.2.1 Grain size analysis was carried out for each soil sample after drying the fraction
passing 4.75mm IS Sieve but retained on 75 micron IS sieve after washing
(IS:2720 (Part -4) - 1985.

3.4.3.3 Atterberg Limits

3.4.3.3.1 The plasticity indices of subgrade soil were determined as per IS:2720 (Part 5)
using liquid limit device (Casagrande). Typical variation of liquid limit and
plasticity index along the longitudinal profile at a depth of 1m is shown in Table-
G/1-1 & G/1-2 in Appendix -1.

3.4.3.3.2 Based on grain size analysis and Atterberg limits, the subgrade soil is classified
according to IS:1498 - 1987. From particle size distribution of the soil curves were
drawn between particle size (mm) and the percentage passing, The soils are thus
classified into two main groups C1 & C2. The typical Grain Size Distribution
Curve (Group C1 & C2) is shown in from Fig. G/1 to Fig G/5 in Appendix -1 along
with the range of various fractions in the soils.

3.4.3.4 Modified Proctor Test


The original ground soil samples from each location were tested by modified
proctor test for maximum dry density (MDD) and Optimum Moisture Content
(OMC) as per IS:2720 (Part 8). Results of all these tests are given in Table-
G/1-1 & G/1-2 in Appendix -1. Typical curve between Field Dry Density and
Maximum Dry Density is shown in Fig. G/6 to Fig G/22 in Appendix -1.

3.4.3.5 CBR Value Test


CBR tests were conducted by remolding soil samples by dynamic compaction
method at MDD and OMC. The samples thus obtained were tested for getting the
CBR values at MDD and OMC. In addition, the samples were tested by
compacting them with 10 blows, 35 blows and 60 blows at FMC or OMC
whichever was higher in accordance with ASTM D-1883-1987. With the
relationship established between moisture dry densities and CBR, the behavior of
the sample, its strength and sensitivity with variation in moisture content was
studied. Most of the samples tested did not show very high sensitivity in change
of CBR values with change of moisture content determined. The Static

Spectrum Techno Consultants Pvt. Ltd. in JV with 6


LRP Consultant Consortium Pvt. Ltd.
BORDER ROAD ORGANISATION / PROJECT BRAHMANK FINAL DETAILED PROJECT REPORT
Survey, investigations and preparation of Detailed Project Report
for improvement of road MIGGING – TUTTING from km 13.56 to Volume 3 - Material Report
35.00 to NH double lane specifications in upper Siang Dist. of
Arunachal Pradesh

Compaction method was adopted for remolding the samples at MDD and FMC or
OMC whichever higher and soaked CBR determined in a normal manner. The
test results are given in Table in Appendix -1. Typical curve between Penetration
(mm) and Unit Load Kg/Sq.cm is shown in Fig. G/23 to Fig G/39 in Appendix -1.

3.5 Materials for Embankment and Sub grade

It is necessary to develop the entire work to 2 lane with shoulder from existing
intermediate lane within the available right of way (ROW) as far as possible. This
would entail additional earth material. The project stretch project stretch passes
through hill/mountainous terrain, hence most of the requirement will meet from
cut section material within ROW. Based on the earthwork calculation, it was seen
that adequate quantities of high-grade fill is available for preparing top 500mm of
the sub-grade.

The CBR value of test pit samples collected within ROW are presented in below
Table 3.1 and Figure 3.1
Table 3.1: CBR Value
Location / Soaked CBR
Chainage Value %
17.000 28.2
19.000 27.9
21.000 13.4
23.000 12.9
25.000 21.8
27.000 25.5
29.000 12
31.000 26.2
33.000 20.9
34.998 11.7

Figure 3.1: CBR Values of Borrow Material (within ROW) in Soaked Condition

Spectrum Techno Consultants Pvt. Ltd. in JV with 7


LRP Consultant Consortium Pvt. Ltd.
BORDER ROAD ORGANISATION / PROJECT BRAHMANK FINAL DETAILED PROJECT REPORT
Survey, investigations and preparation of Detailed Project Report
for improvement of road MIGGING – TUTTING from km 13.56 to Volume 3 - Material Report
35.00 to NH double lane specifications in upper Siang Dist. of
Arunachal Pradesh

It is observed that the samples collected within ROW shows CBR in the range of
11.70% to 30.2 %. It is recommended to use borrow material of minimum 8 %
CBR value. Hence the available material from borrow areas can be used for
Embankment and subgrade.

3.6 Sand, Aggregate, High Grade Fill and Granular Sub Base Material

The Consultant conducted field investigation for location of quarry sites for
obtaining suitable construction materials mainly sand, aggregate, high grade fill,
and Granular material.

The Consultant in locating the quarry sites used the following criteria.
• Ease in developing quarry face
• Overburden
• Outcrops with minimum variability in strength
• Closeness to alignment and with access road
• Available quantity

Based on these general criteria two quarry sites are identified along the project
roadway alignment which have been tabulated in Table 3.1. The Location and
Chart of both Quarry are presented in Figure 3.2 & 3.3.

Table 3.2 Quarry Sites for Surface Aggregates and Base Course
Station (Ex. Ch.) Quarry name Source of Availability
Material of material
for Project
Km 0.000 (Start of Project)
Km 20.000 Palsi Quarry Stone/Sand Yes
Km 35.000 (End of
Project)
Km 45.210 Palsi Quarry Sand/Aggregate Yes

The above quarry has adequate quantities of material in all types of grading and
at very convenient distances from the road.

3.7 Other Construction Materials

The other construction materials such as Bitumen, Cement, steel, etc. are
available from two source:
• Open market of nearby cities such as Itanagar and Pasighat, etc.
• Through BRO departmental store.

Spectrum Techno Consultants Pvt. Ltd. in JV with 8


LRP Consultant Consortium Pvt. Ltd.
BORDER ROAD ORGANISATION / PROJECT BRAHMANK FINAL DETAILED PROJECT REPORT
Survey, investigations and preparation of Detailed Project Report
for improvement of road MIGGING – TUTTING from km 13.56 to Volume 3 - Material Report
35.00 to NH double lane specifications in upper Siang Dist. of
Arunachal Pradesh

The project site is located far from the major cities of Arunachal Pradesh, hence
the material procured from the market needs to be an additional cost of lead and
transportation in the material cost.

Also, the construction material can be available through BRO departmental


resources with some royalty charges.

3.8 Miscellaneous

3.8.1 Water
Water is sufficiently available in vicinity of project site.

3.8.2 Brick Kilns


Brick Kilns are available in abundance along the project stretch.

3.8.3 Fly Ash


No Fly ash is available in vicinity of project site.

3.8.4 Labour Availability and Amenities


Sufficient laborers are not available at local, hence labour required to be import
from nearby states Assam/ Jharkhand/Bihar/Orissa.

Spectrum Techno Consultants Pvt. Ltd. in JV with 9


LRP Consultant Consortium Pvt. Ltd.
BORDER ROAD ORGANISATION / PROJECT BRAHMANK FINAL DETAILED PROJECT REPORT
Survey, investigations and preparation of Detailed Project Report
for improvement of road MIGGING – TUTTING from km 13.56 to Volume 3 - Material Report
35.00 to NH double lane specifications in upper Siang Dist. of
Arunachal Pradesh

Figure 3.2: Quarry Chart for Aggregate and Boulder at Palsi Quarry

Total Road Length = 20.00 km

PROJECT LENGTH= 20.00 km

PALSI
QUARRY
Km 278.40

9.40 km 10.6 km

START OF PROJECT END OF PROJECT


(NEAR SINGGING H.Q.) (NEAR TUTTING H.Q.)
Km 00.00 / Km 269.00 Km 20.00 / Km 289.00

Spectrum Techno Consultants Pvt. Ltd. in JV with 10


LRP Consultant Consortium Pvt. Ltd.
BORDER ROAD ORGANISATION / PROJECT BRAHMANK FINAL DETAILED PROJECT REPORT
Survey, investigations and preparation of Detailed Project Report
for improvement of road MIGGING – TUTTING from km 13.56 to Volume 3 - Material Report
35.00 to NH double lane specifications in upper Siang Dist. of
Arunachal Pradesh

Figure 3.3: Quarry Chart for Sand, Aggregate at Palsi Quarry

Total Road Length=20.244 kms

Spectrum Techno Consultants Pvt. Ltd. in JV with 11


LRP Consultant Consortium Pvt. Ltd.
BORDER ROAD ORGANISATION / PROJECT BRAHMANK FINAL DETAILED PROJECT REPORT
Survey, investigations and preparation of Detailed Project Report
for improvement of road MIGGING – TUTTING from km 13.56 to Volume 3 - Material Report
35.00 to NH double lane specifications in upper Siang Dist. of
Arunachal Pradesh

APPENDIX 1: THE DETAILED LABORATORY


INVESTIGATION RESULTS
(REFER APPENDIX E – MAIN REPORT)

Spectrum Techno Consultants Pvt. Ltd. in JV with 12


LRP Consultant Consortium Pvt. Ltd.

You might also like