WHR FINISHING WORKS SCHEDULE

REV 00 17TH OCT 2019

ID Task Name Duration Start Finish Sep '19 Oct '19 Nov '19 Dec '19 Jan '20 Feb '20
29 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 2 9 16 23
1 WHR FINISHING WORK SCHEDULE 88 days October 18, 2019 February 18, 2020
2 WHR P&G Building 88 days October 18, 2019 February 18, 2020
3 20 mm Base Plaster on Exterior 20 days October 18, 2019 November 14, 2019
4 Walls
10 mm Thick Groove Plaster 30 days November 6, 2019 December 17, 2019
5 Fixing Marble Window Sill 20 days December 4, 2019 December 31, 2019
6 Fabrication Aluminum Windows 20 days October 25, 2019 November 21, 2019
7 Fixing Aluminum Windows 14 days December 23, 2019 January 9, 2020
8 Weather Shield Paint 23 days January 17, 2020 February 18, 2020
9 Fabrication of steel Doors 15 days October 25, 2019 November 14, 2019
10 Fixing Steel Doors 10 days November 8, 2019 November 21, 2019
11 Laying Ceramic Tiles 10 days November 22, 2019 December 5, 2019
12 Applying Vinyle Emulsion Paint 10 days December 11, 2019 December 24, 2019
13 Installing Gypsum False Ceiling 12 days December 25, 2019 January 9, 2020
14 AQC Boiler 16 days October 25, 2019 November 15, 2019
15 Fabrication Steel Doors 10 days October 28, 2019 November 8, 2019
16 Fixing Steel Doors 5 days November 11, 2019 November 15, 2019
17 Fixing Marble Window Sill 5 days October 25, 2019 October 31, 2019
18 Fabrication Aluminum Windows 7 days November 4, 2019 November 12, 2019
19 Fixing Aluminum Windows 3 days November 13, 2019 November 15, 2019
20 Chemical Water Treatment Building 75 days October 23, 2019 February 4, 2020

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: WHR Finishing Works R Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
WHR FINISHING WORKS SCHEDULE
REV 00 17TH OCT 2019

ID Task Name Duration Start Finish Sep '19 Oct '19 Nov '19 Dec '19 Jan '20 Feb '20
29 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 2 9 16 23
21 Fabrication Steel Doors 10 days October 23, 2019 November 5, 2019
22 Fixing Steel Doors 7 days November 6, 2019 November 14, 2019
23 Laying Ceramic Tiles 7 days November 15, 2019 November 25, 2019
24 Groove Plaster 14 days November 4, 2019 November 21, 2019
25 Fixing Marble Window Sill 7 days November 22, 2019 December 2, 2019
26 Fabrication Aluminum Windows 10 days November 6, 2019 November 19, 2019
27 Fixing Aluminum Windows 5 days December 3, 2019 December 9, 2019
28 Applying Vinyle Emulsion Paint 12 days January 6, 2020 January 21, 2020
29 Weather Shield Paint 15 days January 15, 2020 February 4, 2020
30 Wartisla Boiler 43 days October 25, 2019 December 24, 2019
31 Fabrication Steel Doors 7 days October 25, 2019 November 4, 2019
32 Fixing Steel Doors 4 days November 5, 2019 November 8, 2019
33 Groove Plaster 10 days November 11, 2019 November 22, 2019
34 Fixing Marble Window Sill 5 days November 25, 2019 November 29, 2019
35 Fixing Aluminum Windows 7 days December 2, 2019 December 10, 2019
36 Applying Vinyle Emulsion Paint 7 days December 11, 2019 December 19, 2019
37 Weather Shield Paint 10 days December 11, 2019 December 24, 2019
38 Cooling Tower & Waste Water Tank 49 days October 18, 2019 December 25, 2019
39 Balance Rcc Structure 10 days October 18, 2019 October 31, 2019
40 Removal of Form Work 10 days November 14, 2019 November 27, 2019

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: WHR Finishing Works R Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2
WHR FINISHING WORKS SCHEDULE
REV 00 17TH OCT 2019

ID Task Name Duration Start Finish Sep '19 Oct '19 Nov '19 Dec '19 Jan '20 Feb '20
29 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 2 9 16 23
41 Plaster in Waste Water Tank 8 days October 29, 2019 November 7, 2019
42 Plaster in Cooling Tower 10 days November 28, 2019 December 11, 2019
43 Polymer Water Proofing, Tank 10 days December 12, 2019 December 25, 2019
44 Cooling Tower, Room 80 days October 18, 2019 February 6, 2020
45 Balance Rcc Structure 10 days October 18, 2019 October 31, 2019
46 Removal of Form Work 8 days November 1, 2019 November 12, 2019
47 Earthfill / Compaction / Flooring 12 days November 13, 2019 November 28, 2019
48 Brick Masonry 8 days November 29, 2019 December 10, 2019
49 Fixing of Steel Door 6 days December 11, 2019 December 18, 2019
50 Interior / Exterior Plaster 10 days December 19, 2019 January 1, 2020
51 Fixing Marble Window Sill 5 days January 2, 2020 January 8, 2020
52 Fixing Aluminum Windows 8 days January 9, 2020 January 20, 2020
53 Applying Vinyle Emulsion Paint 7 days January 27, 2020 February 4, 2020
54 Weather Shield Paint 7 days January 29, 2020 February 6, 2020

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: WHR Finishing Works R Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 3