You are on page 1of 1

Name of Project: Preparation for the Temporary Interment Area Date:

16.5 x 60.0 m Road/Bed/Embank Width:


Pavement Width :
Bridge/Other Structures :
Location: Brgy. Dona Orani, Bataan Type of Substructures :

Appropriation: Type of Superstructures:


Source of Fund: No of Span/Storey:
Classification: No of Pier/No of Abutts.:
Limits: Starting Time:
Net Length: No of Days to Complete: 8 days

DESCRIPTION OF EQUIPMENT
% OF TOTAL DESCRIPTION
WORK TO BE DONE Needed Available
Site preparation 12.05% Pay loader 1
Base Course 51.69% Road Grader 1
Temporary Fence 36.27% Road Roller 1

TOTAL 100.00%
Spec's
Description Unit Quantity Unit Cost Total Cost
Item No.
I. Site preparation sq.m 990.00 25.25 25,000.00
II. Base Course Cu.m 99.00 1,083.33 107,250.00
III. Temporary Fence L.m. 93.00 809.19 75,255.00

APPROVED BUDGET FOR THE CONTRACT 207,505.00


Direct Cost 100.00% 207,505.00 A.]Estimated Material Cost 143,984.00
Indirect Cost B.]Estimated Labor Cost 24,521.00
Const Eng'g. & Admin. C.]Equipment Fuel Consumption 39,000.00
Total Estimated Cost 100.00% 207,505.00 TOTAL ESTIMATED COST 207,505.00

Prepared by:

JESS NOEL LAGUATAN


R.T.O.