Professional Documents
Culture Documents
CUSTOMER
EQUIPMENT DETAILS
SITE
STATUS
SR NO
CHECK POINT O.K NOT O.K
1) MECHANICAL INSTALLATION
Check that the cabinet parts are clean and dust free.
f)
Check that each shipping section was erected with correct type of joining
g) arrangements like side plates, channels, connecting bus bar (AC, DC and PE) etc.
k) The cooling air is able to flow freely and cooling air volume is sufficient
Bus bars
2)
Electrical components
3)
Check that the quantity, make, type and rating of components are as per BOM.
a) Check visually that the components are not damaged
Check that all the components are marked with visible labels. If any label missing
b) please arrange the same
Check that all modules are according to the BOM with correct option codes
c)
ELECTRICAL INSTALLATION
4)
b) The AC line voltage matches the nominal output voltage of the inverter
f) The AC power cable connections at L1,L2 and L3 and their tightening torques are OK
The DC power cable connections at UDC+ and UDC- and their tightening torques are
g) OK
Check that short links on TB’s and loop chaining are done according to scheme
e)
Check that fuses are placed tightly in the middle of the fuse socket / fuse base.
c)
Check that the doors for open and close without rubbing or noise when open and close.
d)
Check the door defeat function. When fuse switch or disconnecting switch is closed,
e) the cabinet door cannot be opened.
7) Start-Up Preparation
Acceptance Date
Contractor Engineer
Consultant Engineer
Client Engineer
TRANSFORMER ERECTION CHECK LIST
Customer:-
Equipment Details:-
Site:-
Status
Sr. No. Check Point O.K NOT O.K
1) AVAILABILITY OF DOCUMENTATION
2) RECEIPT OF TRANSFORMER
3) RECEIPT OF ACCESSORIES
4) ERECTION
b) Conservator mounted
Buchholz relay and oil surge relay mounted (arrow
c) marked should be towards conservator)
e) HV Bushings mounted
f) LV Bushing mounted
g) Tertiary Bushing mounted (if applicable)
k) Diaphragm checked
l) MOLG mounted
m) Radiator mounted
n) Fans mounted
4) OIL FILLING
5) MULTICORE CABLE
6) BREATHERS
7) FANS
8) CONTROL PANELS
Acceptance Date
Contractor Engineer
Consultant Engineer
Client Engineer
SCB ERECTION CHECK LIST
Customer:-
Equipment Details:-
Site:-
Status
Sr. No. Check Point O.K NOT O.K
Equipment
2)
c) DC switch operational
Electrical Connections
3)
d) Gland tighting
Documentation
4)
Acceptance Date
Contractor Engineer
Consultant Engineer
Client Engineer