Professional Documents
Culture Documents
(EE 468)
Dr. A. Kirubakaran
Assistant Professor,
Electrical Engineering Department,
NITW, Warangal
CHAPTERS
1) Introduction
5) Induction Generators
6) Storage Systems
1
1. Introduction
Past
3
Present
2
By the year 2024, the global population is projected to be
8.0 billion.
I=PxCxT
• Power Generation-India
State
Sector
Private
31%
Sector
44%
Central
Sector
25%
3
1.1. Power Generation-India
25-35%
98-99%
95%
4
Efficiency:
Thermal Power Plant : 25-35 % (based on size, age, and capacity
utilization)
Transmission Efficiency: 98-99 % (transformer efficiency is usually
98-99%)
Sub transmission Efficiency: 96% (Envisaged losses 4%)
Distribution Efficiency: 95% (Envisaged losses 5%)
Total system efficiency from the output of transmission and
distribution: (.98*.96*.95) = 89 %
At the end user the standard technical losses are around 17%
(Efficiency: 83%).
But in many literatures, it is in the ranges from 17-50%. All these
may not constitute the technical losses, since un-metered and
pilferage are also accounted in this loss.
Fuel constraints
10
5
Power Demand?
Peak power deficit in January 2013 was 11.4 per cent. The power
demand then was 1,32,948 MW against a supply of 1,17,790 MW,
according to the Central Electricity Authority (CEA) data.
1400
1221
1200 1134
1000
800
570
600 510
400 329
262 235
202181
200 137 165163
89
45 47 48
7 22
0
Industry Transport Agriculture Commercial Residential Total
6
Global Warming
13
7
Nitric oxide
6% CFC Chlorofluorocarbon
14%
CO2
50% Methane
18%
Ozone
12%
Gasses in the Atmosphere
15
Domestic heating
5% Pow er Stations
15%
Transport Industry
60% 20%
16
8
It was agreed that
the developed nations of the world must reduce
their greenhouse gas emissions
17
18
9
19
• Wind Power:
- The average wind farm requires 17 acres to produce 1MW of
electricity (about enough electricity for 750 to 1000 homes)
• Solar Power
- Solar thermal generation requires large tracts of land, and this
affects natural habitat.
10
• Bio-power:
- The organic matter that makes up plants is known as biomass
- Four sets of programmes are being implemented with the aim to
generate competitively priced bio power and/or heat from
agricultural, agro-industrial residues and plantations and urban &
industrial wastes. These are:
- Biomass power / bagasse cogeneration
- Non-bagasse cogeneration
- Biomass gasifier
- Urban & Industrial wastes
21
11
• To regulate power, voltage, speed, and frequency, each method
depends on matching, instantaneously, load to generation.
Losses?
24
12
1.3. Distributed Generation
13
• The need for argumentation of fossil fuels is neglected.
14
Comparison of Different DGs
Sustained Interruptions
Voltage Regulation
Voltage Ride Through
Harmonics
Voltage Sags
Load Following
Power Variation
15
Interconnection of DG
Voltage Deviation:
Interconnection system response to Abnormal Voltages per IEEE 1547
Frequency variation
Current Harmonics
16
DG Integration Schemes
Useful for long-term outage and without projecting loads from any
short-term and voltage fluctuations.
A typical diesel generator takes 10 seconds for supplying power to
loads
17
3. Primary DG system with Power Quality Support
to Priority Loads
• The CHP operates in parallel with the utility grid to provide low cost
electric and thermal energy.
18
5. DG with intermittent Solar PV within power
quality environment
19
7. Ultra-high reliability scheme using dual link DC
bus
Operated as
main power supply
Advantages
1. Source voltage failure don’t draw power from other sources.
20
1.4 Renewable Energy Economics
• New electricity infrastructures have been set up to provide high
penetration levels of up to 100% electricity from renewable sources.
21
• The full-load hours represent the equivalent time of full operation for
a year.
• In the case of wind energy, the full-load hours are determined by the
wind speed distribution and the rated wind speed of the machines.
22
• New Plants: Electricity generation costs consist of variable
costs and fixed costs.
Generation costs are given by
Fixed costs occur whether or not a plant generates electricity. These costs are
determined by investment costs (I) and the capital recovery factor.
23
• Capital Recovery Factor The capital recovery factor allows
investment costs incurred in the construction phase of a plant to
be discounted.
• The amount depends on the interest rate and the payback time
of the plant.
• Both short-term marginal costs (i.e., variable costs) and fixed costs
must be considered for new plants.
24
1.5 Energy Recovery Time
• The cost of electricity depends entirely, or largely, on the size of
power stations
• Between 1960 and 1980, the ideal size of a station rose from 400
MW to 1000 MW.
• The lower the specific energy content, the more energy intensive is
the conversion process.
25
• The recovery time for power stations fired by gas and oil is 0.09 of a
full-load year (approximately 0.13 of a calendar year); for coal-fired
power stations, it is 0.15 of a full-load year (approximately 0.21 of a
calendar year).
• The recovery time of 0.7 full-load year for gas- or oil-fired power
stations, which is approximately one calendar year. Coal fired power
stations have a longer recovery time.
26
1.6 Modern Electronic Controls of Power
Systems
• Power electronics is a part of electronic application systems that
encompasses the entire field of power engineering, from generation to
transmission and distribution to transportation, storage systems, and
domestic services.
• The variable output from renewable energy devices also means that
power conditioning and control equipment is required to transform this
output into a form (i.e., voltage, current, and frequency) that can be
used by electrical appliances. Therefore, energy must be stored and
power electronics used to convert this energy.
27