CADANGAN PEMBINAAN SEBUAH PUSAT KOMUNITI DI PPR SEMARAK DI ATAS SEBAHAGIAN LOT 4248, JALAN AIR KEROH, MUKIM

SETAPAK, KUALA LUMPUR

CARTA JADUAL KERJA BAGI PERMOHONAN LANJUTAN MASA PERKHIDMATAN KERANI TAPAK MEKANIKAL & ELEKTRIKAL

2016 2017 2018 2019 2020


NO DESCRIPTION

MAC APR MEI JUN JUL OGS SEPT OCT NOV DIS JAN FEB MAC APR MEI JUN JUL OGS SEPT OCT NOV DIS JAN FEB MAC APR MEI JUN JUL OGS SEPT OCT NOV DIS JAN FEB MAC APR MEI JUN JUL OGS SEPT OCT NOV DIS JAN FEB MAC APR MEI JUN JUL OGS SEPT OCT NOV DIS

1 Tender (4 Minggu) [3 Mac 2016 - 31 Mac 2016 ]

2 Penilaian Tender (1.5 Minggu) [25 Apr 2016 - 06 Mei 2016 ]

Tender Board dan Perlantikan Kontraktor (3.5 Minggu) (07 Mei 2016 - 31 Mei
3
2016)

4 Pembinaan Asal ( 72 Minggu) [01 Jun 2016 - 30 Nov 2017 ]

5 E.O.T (196 hari) [30 Nov 2017 - 13 Jun 2018] E.O.T 1: 196 HARI

6 E.O.T 2 (224 hari) [14 Jun 2018- 23 Jan 2019] E.O.T 2: 224 HARI

7 E.O.T 3 (126 hari) [24 Jan 2019 - 29 Mei 2019] E.O.T 3: 224 HARI

8 Inspection & Handing Over (4 Minggu) [30 Mei 2019 - 27 June 2019 ]

9 Defects Liability Period (52 Minggu) [28 June 2019 - 26 June 2020 ]

10 Tempoh Masa Asal Kerani Tapak (Okt 2016 - Nov 2017) + 3 Bulan DLP TEMPOH ASAL DILULUSKAN (OKT 2016-NOV 2017 + 3 BULAN DLP)

11 Lanjutan Masa Kerani Tapak Dipohon (Dis 2017 - Jun 2018) + 3 Bulan DLP TAMBAHAN MASA DIPOHON + 3 BULAN DLP

12 Lanjutan Masa Kerani Tapak Dipohon (Jun 2018 - Jan 2019) + 3 Bulan DLP TAMBAHAN MASA DIPOHON + 3 BULAN DLP

12 Lanjutan Masa Kerani Tapak Dipohon (Jan 2019 - May 2019) + 3 Bulan DLP TAMBAHAN MASA DIPOHON + 3 BULAN DLP

13 Final Account (8 Minggu) [27 June 2019 - 22 Aug 2019 ]