Professional Documents
Culture Documents
D4FC42 Environmental SI PDF
D4FC42 Environmental SI PDF
Name: David Collett/Daniel Lash The University of Exeter’s Environment and Sustainability
Institute (ESI) is a £30m interdisciplinary centre leading
Company Leadbitter/University of Exeter cutting-edge research into solutions to problems of
Emai: davidcollett@leadbitter.co.uk/ environmental change. It is based on the University’s
d.lash@exeter.ac.uk Cornwall Campus, near Falmouth. Its aim is to facilitate
teaching, research and commercial application of
Tel: 01752 671430/01392 724143
environmental and sustainability knowledge. As such,
General project information it is being built to the highest sustainability standards
(BREEAM Outstanding) and will have to be “living proof” of
Name of project: Environmental Sustainability Institute its credentials. This extends to being fully adaptable to the
Location of project: Penryn, Cornwall effects of climate change. The building will contain a mix
of spaces including offices, laboratories, communal and
Type of project: New build workshop spaces, and as such the specific challenges to
Cost of project: £30m each of these spaces will make the findings of this work
directly relevant to a large number of future buildings. The
Project team total gross internal area of the building is about 3200 sqm.
Client: University of Exeter
Project timescales and dates
Designer: Stride Treglown
Design and assessment period (pre-planning): August 2009
Contractor: Leadbitter
to April 2010
Other organisations involved (and their role): Method (M&E),
Construction period (post-consent): April 2011 to August 2012
Halcrow (structural engineers), University of Exeter (building
physicists and dissemination) Operation and monitoring period: August 2012 to July 2013
D4FC Factsheet 42 1
Further project details
zz adaptation risks and adaptations have been investigated zz the work is still ongoing and so a full list of
as individual sub-tasks within the project. Output from recommendations has not been finalised
each of these tasks has been communicated from the zz for adopting recommendations, the client has agreed
task investigator via the principal contractor and client to the installation of a larger rainwater harvesting tank
project manager. RFIs have been produced where it in order for expected performance of the system to be
has been agreed by the client to make changes to the the same under future climate (and also extended dry
design. This element of the project was communicated periods) as under today’s climate
mainly through email, which was found to work well
zz recommendations were made that would have required
zz the adaptation study on this building was undertaken significant updating of the site drainage, however this
during the construction phase of the project. Under ideal was rejected by the client because it would not have
circumstances adaptation would have been considered been feasible at this stage.
at this level of detail far earlier in the design stage. Had
this been the case design team meetings would have 5 What were the major challenges so far in doing this
been expected to play a greater and more useful role for adaptation work?
communicating risks and recommendations.
zz aswith any project, incentivising performance that goes
beyond minimum regulatory standards (of which there
D4FC Factsheet 42 2
are none specifically aimed at adaptation, though there interventions could be made. The building as
D4FC Factsheet 42 3