Professional Documents
Culture Documents
Improve Performance and Reduce Costs of Wastewater Treatment Plants
Improve Performance and Reduce Costs of Wastewater Treatment Plants
Plant
Fresh water
To WWTP
1st 2nd 3rd
Unit 3 effect effect effect
CW out CW in
Unit 4
Fresh water
Unit 5 Pit
Centrifuge Salt
(Unit 6)
Concentrated organics
level. Based on this data, the proposed lumped into a single contaminant, and composite curves. Once the target is de-
modification can be evaluated. As shown wastewater target flow for recycle and fined, the water network can be optimized
later, the considered contaminants can be discharge can be obtained via source-sink to ascertain if any stream can be reused or
recycled. Further explanation on water
TABLE 1. Source streams pinch analysis and source-sink composite
curves can be found in literature.1, 2, 3
Number Flow, kg/hr Concentration, ppm Load, mg/hr Stream name
After the optimum water network is de-
1 950 0 0 Fresh veloped, the reused or recycled streams are
2 2,000 50 100,000 Evaporator 1 combined with the internal plant’s Excel-
3 1,900 500 950,000 Evaporator 2 based mass balance to check if the solution
4 1,000 600 600,000 Evaporator 3 has any effect on the product quality.
5 50 1,000 50,000 Dryer
The produced wastewater stream from
the plant with the reused or recycled
Current water network stream(s) will then be sent to a proprie-
4,650 kg/hr 650 2,000 Collection tary evaporator model to check if the con-
Fresh water Unit 1 Evaporator 1 vessel 1 centration of the stream(s) to be reused
Water cost (thousand €/yr): 37 or recycled will be affected. The overview
650 1,900
Unit 2 Evaporator 2 of this integrated model (Excel plant mass
Collection 4,950 kg/hr WWTP
vessel 2 balance, proprietary evaporator and pinch
50 1,000 Wastewater cost
Unit 3 Evaporator 3 (thousand €/yr): 40 analysis models) is shown in FIG. 4.
Total cost (thousand €/yr): 77
1,300 50 Data collection. Data collection was
Unit 4 Dryer
performed via intense communication
1,200 with plant personnel. Some of the lines
Unit 5
lack flowmeters, so their flowrates are es-
800 timated based on mass balance.
Unit 6 To check if the water reuse/recycle is
acceptable, the chemicals involved can be
FIG. 2. Schematic of the existing water network.
lumped into a common property: TOC.
Proposed design This lumping approach simplifies the
2,650 kg/hr 650 2,000 Collection problem and makes water pinch analysis
Fresh water Unit 1 Evaporator 1 vessel 1 via source-sink composite curves possible.
Water cost (thousand €/yr): 21 Lists of available water streams (source
Combined water (ppm): 22 650 1,900
Unit 2 Evaporator 2 542 ppm streams), required water streams (sink
Collection 2,950 kg/hr WWTP
vessel 2
streams) and their corresponding concen-
50 1,000 Wastewater cost
Unit 3 Evaporator 3 (thousand €/yr): 24 trations are listed in TABLE 1 and TABLE 2.
Total cost (thousand €/yr): 45
1,300
Unit 4 Dryer
50 Reduction: 42% Analysis of proposed modification.
Based on the collected data, an analysis
1,200 was performed on the proposed modifica-
Unit 5
tion. The condensed water from the first
800 effect evaporator (Evaporator 1) is indeed
Unit 6 the “purest” stream, and it has a TOC of
approximately 50 ppm. However, Unit
FIG. 3. Proposed modification to the wastewater treatment system.
1 and Unit 2 have stricter water require-
Condensed water from Evaporator 2 ments of 10 ppm and 20 ppm, respective-
ly. Therefore, the proposed modification
Condensed water from Evaporator 1 of combining the condensed water with
the freshwater stream cannot be justified.
To keep the required concentrations
in Unit 1 and Unit 2, only 1,800 kg/hr
Plant of water can be recycled instead of the
Freshwater Multiple-effect Wastewater
proposed 2,000 kg/hr, resulting in a cost
Excel mass- evaporator model
balance model reduction of only 38%. This scenario is
illustrated in FIG. 5, where the freshwater
intake is 2,850 kg/hr and the wastewater
discharge is 3,150 kg/hr.
This short analysis answers the ques-
FIG. 4. Interaction between the calculation models.
tion of whether or not the proposed modi-
76 DECEMBER 2015 | HydrocarbonProcessing.com
Water Management
fication is acceptable. To investigate if a • Higher wastewater discharge To solve this issue, the “fresh” waste-
better solution is available, the source-sink • Higher energy required for the water stream directly from the pit is used
composite curves are made (FIG. 6). The evaporator. to wash the centrifuge. This stream is rela-
target for the freshwater intake is far below
Modified proposed design
the present consumption, which is 910 kg/ 1,800
hr. The wastewater discharge is also re-
2,850 kg/hr 650 2,000 Collection
duced by 79% to 1,210 kg/hr. Fresh water Unit 1 Evaporator 1 vessel 1
As outlined by the source-sink com- Water cost (thousand €/yr): 23
650 1,900 200
posite curves, these targets are used as the Combined water (ppm): 20 Unit 2 Evaporator 2 511 ppm
benchmark prior to any water network de- Collection 3,150 kg/hr WWTP
vessel 2
sign. To determine how the water network 50
Unit 3 Evaporator 3
1,000 Wastewater cost
(thousand €/yr): 25
should be designed, a superstructure of the Total cost (thousand €/yr): 48
sources and sinks is developed considering 1,300 50 Reduction: 38%
Unit 4 Dryer
all possible connections between all water
sources and all water sinks. 1,200
Based on this superstructure, mathemat- Unit 5
ical formulations are developed and solved 800
to minimize freshwater consumption (i.e., Unit 6
total cost involved). Details on how the su-
perstructure is built and the mathematical FIG. 5. Proposed design modified due to contaminant constraint.
programming are explained in literature.1, 2, 3
1,600,000
One of the optimum water networks Wastewater discharge
is shown in FIG. 7. The diagram shows the Source composite curve
1,400,000 Sink composite curve
result of a preference for condensed water
from Evaporators 1 and 2, as an additional 1,200,000
practical constraint. This option is pre-
1,000,000
ferred due to their relatively lower contain-
Load, gr/hr
Plant
Fresh water
To WWTP
1st 2nd 3rd
Unit 3 effect effect effect
CW out CW in
Unit 4
Unit 5 Pit
Centrifuge Salt
(Unit 6)
Concentrated organics
78 DECEMBER 2015 | HydrocarbonProcessing.com