You are on page 1of 2

June 2011 • TA N K S T O R A G E FIRE SAFEtY

Aboveground storage tank fires are not common, but they do occur.
One expert looks at the major causes of tank fires and assesses how
some incidents may have been avoided

Cause and effect


L
ightning may be the most roof, seals and shunts are
common source of tank properly maintained
fires, and is more likely to 2) Avoiding refloating of
cause a fire in external floating landed roofs during weather
roof (EFR) tanks than internal where lighting is possible
floating roof (IFR) tanks. 3) Avoiding tank cleaning
Fires caused by lightning operations during weather
in EFRs typically occur due to where lighting is possible.
arcing between the floating
roof and shell structure, Static electricity
particularly in the vicinity
of perimeter seals. Arcing Tank operations tend to change
occurs when lightning-induced over time and it is advisable
currents encounter a path to periodically review practices
of high resistance due to to ensure compliance with API
imperfect bonding of metallic Recommended Practice 2003
shoe seals and shunts. and NFPA 77 ‘Recommended
The latest editions of API Practice on Static Electricity’.
2009 Bayamon, Puerto Rico: Multiple tank fires caused by
RP Recommended Practice overfilling one tank
Static electricity is also a
545 ‘Recommended Practice concern during maintenance
for Lightning Protection of Incorporation of these are open during heavy and measurement activities but
Aboveground Storage Tanks for requirements into API precipitation (to avoid the focus is on tank operations.
Flammable and Combustible Standards 650 and 653 is sinking the roof) Sparks from static electricity
Liquids’ and NFPA 780 currently being balloted 6) Consideration of can cause ignition of flammable
‘Standard for the Installation of in the API Subcommittee supplementary lightning vapours. For static electricity
Lightning Protection Systems’ on Aboveground Storage protection systems such to be a source of ignition, the
present conclusions drawn from Tanks (SCAST). strike termination devices following conditions must be
lightning simulation testing The results of the lightning 7) Installing a metallic fixed present:
commissioned by the API and simulation testing assume roof over the EFR. 1) A means of generating
the Energy Institute London. the floating roof is floating. a charge
API 545 replaces the It is not clear whether the iFR tanks 2) A means of accumulating
lightning protection new requirements increase a charge
requirements of API or decrease the risk of a Fires caused by lightning in 3) A spark gap
Recommended Practice 2003 landed floating roof with IFR’s typically occur when 4) An ignitable vapour-air
‘Protection Against Ignitions flammable vapours beneath flammable vapours exist at mixture in the spark gap.
Arising Out of Static, Lightning it. This scenario is most the top of the tank around Risk of ignition can be
and Stray Currents’. significant for tanks in ‘drain- vents. IFR’s handling low mitigated by eliminating one
New requirements: dry’ operation and the issue vapour pressure products or or more of these conditions.
1) Applicable to new is being worked through in-service tanks with properly
construction the API balloting process. maintained floating roofs with Switch loading
2) Floating roof shunts (at the tight-fitting seals are not likely
perimeter seals) must be EFR tanks to have flammable vapours Switch loading is the most
located at least one foot at atmospheric vents unless frequently cited cause of
below the liquid level The likelihood of lightning fires being refilled from empty. static incidents when handling
3) Bypass conductors (away in EFR’s can be reduced by: The fixed roof shields the bulk hydrocarbons.
from perimeter seals) are 1) Following API 545 and tank internal space from Switch loading can be
required in addition to shunts NFPA 780 guidelines lightning-induced currents. defined as loading a low
4) Perimeter seal assemblies 2) Ensuring that the floating These currents will travel near conductivity, low vapour
above the liquid level must roof, seals and shunts are the outside surface of the pressure product (such as
be electrically insulated from properly maintained fixed roof and shell to ground. diesel or jet fuel) into a tank
the rest of the floating roof 3) Avoiding refloating of The arcing at perimeter which previously contained
5) Retrofit is acceptable if landed roofs during weather seals that can occur in EFRs a high (such as petrol) or
existing shunts above the where lighting is possible is not a concern for IFRs. intermediate vapour pressure
liquid level are removed 4) Avoiding tank cleaning The likelihood of product (such as toluene). The
6) Gauge poles must be operations during weather lightning fires in IFR’s introduction of lower sulphur
electrically insulated where lighting is possible can be reduced by: products such as low- and
from the floating roof. 5) Ensuring that roof drains 1) Ensuring that the floating ultra-low sulphur diesel has

57
FIRE SAFEtY TA N K S T O R A G E • June 2011

resulted in significantly lower petrol filled the entire tank


conductivity of these products. with flammable vapours,
When switch loading, which magnified the incident.
charge accumulation can Other conclusions and
be significant because of issues identified by the
low product conductivity investigation as significant:
and the high probability of 1) Flow rates had changed
flammable vapours being over time without
present. If sufficient charge is adequate review
generated and a spark gap is 2) The strapping table
present, ignition is possible. was not accurate
Loading an intermediate 3) Multiple low leg settings
vapour pressure product with were found in a floating
low conductivity can also be roof leg recovered after the
viewed as switch loading for incident
the purposes of this discussion. 4) The splash plate over
These products often produce the drain-dry sump (also
flammable vapours at ambient used for filling) did not
temperatures and many completely cover the sump 2005 Cushing, oklahoma: Aftermath of an external floating roof fire
have low conductivity. 5) Credit may not be
taken for diffusers in diffusers used to slow the 9) Check for spark promoters
2003 Glenpool, Oklahoma incident determining flow velocity inlet velocity into the tank (metallic structures pointed
6) IFR bonding cables are 3) Provide a minimum downward in the tank) such
This incident involved an important for dissipation 30 second residence as floating roof drain tubes
80,000 barrel tank that of static electricity, time downstream of that extend below pontoons
exploded and burned for 21 especially when non- micro-pore filters 10) Consider strapping table
hours, causing significant conductive seals are used. 4) Check for ungrounded loose updates and avoid multiple
damage to adjacent tanks and The detailed report of the NTSB or floating objects in the low leg settings on
facilities. The tank was being investigation can be found at tank (such as loose gauge floating roof legs.
filled with low sulphur diesel www.ntsb.gov/publictn/2004/ floats and sample cans)
(LSD) following removal of par0402.pdf 5) Avoid pumping substantial Overfill
petrol. The probable cause amounts of air or
was ignition of a flammable Control of charge generation other gas into the tank Much has been written recently
fuel-air mixture within the tank though the liquid about tank overfills, particularly
by static electricity discharge. When flammable vapours 6) Consider limiting maximum about the incidents at
The tank had an aluminum could be present, the fill rate after the initial Buncefield, UK and Bayamon,
IFR that was landed in petrol following protective measures fill rate is complete Puerto Rico. API 2350 ‘Overfill
service. The tank was partially may be taken to control to 33ft/s or less. Protection for Storage Tanks
emptied, the floating roof re- charge generation: in Petroleum Facilities’ is being
floated with petrol and then 1) Avoiding splash filling Risk mitigation and control of revised and significant changes
drained dry. The tank was then and upward spraying other factors: can be expected, partially as
re-filled with LSD at rates up 2) Limit flow velocity in the the result of the Buncefield
to 9ft/s in the fill line. Just inlet pipe to 3ft/s (1m/s) 1) Minimise or eliminate incident. Buncefield incident
prior to re-floating the roof, an until the floating roof is switch loading reports are available at www.
explosion occurred in the tank. completely floated or, in 2) Consider using inert gas buncefieldinvestigation.
An investigation concluded the case of a tank without if switch loading cannot gov.uk. A report on the
that the following issues a floating roof, until the be avoided (including Bayamon incident by the US
may have contributed to the inlet pipe is submerged by intermediate vapour Chemical Safety Board will
incident and its severity: two pipe diameters or 2ft pressure products) be issued in the near future.
1) Fill velocity exceeded (61cm), whichever is less. 3) Review filling operations
industry standards Flow rate restriction should to ensure flow rates are Other causes
2) Floating roof drain tubes apply to all piping segments appropriate and line fill
may have extended within 30 seconds upstream is properly handled when Other causes of tank fires
below the pontoons of the tank fill opening – switching products in a tank include but are not limited
3) Partial emptying/filling of credit may not be taken for (to avoid mixing of products) to hot work, tank cleaning
4) Consider purging flammable and adjacent fires. Consult
vapours before introducing ANSI/API Standard 2015
a low conductivity, low ‘Requirements for Safe Entry
vapour pressure product and Cleaning of Petroleum
5) Minimise or eliminate Storage Tanks’ and ANSI/
landing of floating roofs API Recommended Practice
during normal operations 2016 ‘Guidelines and
6) Ensure floating roofs are Procedures for Entering and
in metallic contact with Cleaning Petroleum Storage
the shell by bonding Tanks’ for guidance on tank
cables or other method cleaning operations. Both
7) Consider using full contact documents are scheduled for
floating roofs when major revisions beginning
handling intermediate later in 2011. n
vapour pressure products
8) Ensure mixers are not For more information:
This article was written by Craig B. Meier,
operated such that Baker Consulting Group,
jets cannot break the craig.meier@bakercgi.com,
2003 Glenpool, oklahoma: Remains of the tank after the incident surface of the liquid www.bakercgi.com

58

You might also like