Professional Documents
Culture Documents
Compaction of Asphalts
Compaction of Asphalts
Compaction of asphalts
8.1. Preamble
Laying asphalts involves a number of processes which can all profoundly
affect the life of a pavement. Each is important but it is the compaction
process which commands particular attention as failure by either the
surfacing contractor or the engineer to understand and adequately address
the key issues may lead to a substantial reduction in the life of the road.
Compaction is the densification of material by the application of
pressure, initially from the screed of the paver and subsequently from the
rollers. An increase in the density of an asphalt improves the resistance to
permanent deformation and to fatigue cracking along with an increase in
elastic stiffness, all desirable improvements.
This Chapter sets out general observations about compaction and
justifies these by reference to published work on the effect of compaction
on the performance of a pavement. It also covers rolling methods,
compaction plant and other factors including environmental aspects. It
examines the current standard UK compaction specification and considers
the practical application of compaction technology.
Table 8.1. Comparison of typical coated macadams and hot rolled asphalts
Sieve size Percentage by weight passing each sieve
28 mm 100
20 mm 95-100 100
14 mm 65-85 90-100
10 mm 52-72 65-100
6.3 mm 39-55
3.35 mm 32^6 N/A
2.36 mm N/A 35-55
600/im N/A 15-55
300 fim 7-21 N/A
212^m N/A 5-30
75/im 2-9 2-9
Difficult to compact
High stone content
High crushed
aggregate content
Flaky aggregate
Hard binder
Easy to compact
Low stone content
High natural sand content
Rounded aggregate
Soft binder
High binder content
Fig. 8.2. Typical road core of wearing course (chipped HRA) and basecourse
(DBM)
COMPACTION OF ASPHALTS 335
_L _L _L _L
60 80 100 120 140 160 180
Mix temperature: °C
— Rolled asphalt
Asphaltic
concrete
8 32 128 512
Number of passes of roller
Bitumen content: %
Measured directly
80
• 3-0 on the roadbase
A 4-0
• 5-2
70
Adjusted for 38 mm
'hot rolled asphalt'
60
50
30
8 12 16
Void content: %
values of air void content and/or voids in the mineral aggregate (VMA)
against deflection, with values being adjusted to include HRAs. Some of
their findings are illustrated in Fig. 8.5.
Air voids are defined as 'the total volume of air between the coated
aggregate particles of the compacted mixture'. This does not include air in
the aggregate pores trapped beneath the binder films. VMA is defined as
'the volume occupied by the air voids and the amount of binder not
338 ASPHALTS IN ROAD CONSTRUCTION
absorbed into the pores of the aggregate'. Both air voids and VMA are
expressed as percentages of the total volume of the compacted specimen.
The methods of determination of these parameters can be found in
Chapter 9 (Section 9.4.3) and the importance of air voids content is
discussed in Chapter 4 (Section 4.7.3).
As a result of their work, Lister and Powell9 concluded that worthwhile
extensions in the life of the pavement could be obtained with increased
compaction.
2-44
2-40
2-36
© 2-32
10 §
2-28
12
2-24
10 20 30 40
Lateral position: m
100
98
12-5 t vibratory ^ *
96 L ~*
10-51 vibratory
g 94
°- 6-51 vibratory
92 L. 801 static
88
5 10 20
Number of roller passes
Or Or
40
80
120
20 2-1 2-2 2-3 2-4 2-5 1-9 20 2-1 2-2 2-3 2-4 2-5
Density: Mg/m3 Density: Mg/m3
Dense bitumen macadam Rolled asphalt
otherwise have been the case. This would arise if the roadbase was
inadequately compacted. If the basecourse and/or wearing course were
inadequately compacted then they would require replacement earlier than
would otherwise have been the case. If the wearing course is a chipped
HRA then the results may be apparent very shortly after laying — it may
not retain the precoated chippings. This is likely to occur soon after the
road is opened to traffic if the material has not been compacted at
temperatures high enough to ensure bonding of the precoated chippings
with the parent asphalt layer.
Lister and Powell9 scanned cores in order to ascertain how density
varies through layers of an asphalt. Figure 8.8 shows their findings for a
DBM and a HRA used in a roadbase or a basecourse. This illustrates how
the temperature of an asphalt affects the final level of compaction
achieved. Since the upper and lower portions cool faster than the centre of
a layer, the final densities at the top and bottom of the layer are
correspondingly lower. Unchipped and chipped materials cool by the
same mechanisms, but the chipped analysis is much more complex due to
the effects of the addition of precoated chippings to the latter.
Atmosphere
Radiation
Convection Convection
-
Hot layer of bituminous mixture
Conduction
. 20 mm i
i \
20 mm
Chippings
^Contractors are often afforded the option of employing a 50 mm thick wearing course with
a consequent 5 mm reduction in the basecourse thickness — sometimes a very attractive
alternative.
COMPACTION OF ASPHALTS 345
rrChippings
Basecourse
Roadbase
Table 8.2. Temperature values in a 40 mm thick chipped hot rolled asphalt wearing
course layer with different chipping densities
Distance from surface Temperature* at 12kg/m 2 Temperature* at 15kg/m 2
0 70 53
5 75 57
10 80 61
15 83 65
20 85 70
25 85 72
30 83 74
35 80 73
40 75 70
:
Temperature at 1 min after chipping impregnation.
12kg/m2
15kg/m2
6 7 8 9 10
Time after deposition: min
Fig. 8.12. Heat contents in a 40 mm thick chipped hot rolled asphalt wearing
course layer with different chipping densities
Or
40 mm layer
10
20
30
40
70 80 90 100
Temperature: °C
The temperatures are around 10°C lower for the 35 mm layer. Hence
the reason why the thinner the layer, the more difficult it becomes to lay
satisfactorily. Some years ago, the standard thickness of HRA wearing
course was raised from 40 mm to 45 mm — a tacit recognition of the
difficulties associated with embedding a 20 mm chipping into a layer that
may be as little as 35 mm thick.
which dictates the way that specifications are prepared. This raises the
status of this document to one which is quasi-contractual which means
that it is, in effect, a contract document.
Where a Clause is preceded by a '#', this indicates that one of the
'Overseeing Organizations' other than the Highways Agency (i.e. the
Scottish Executive, the Welsh Office and the Department of the
Environment for Northern Ireland) has a substitute National Clause.
either wholly or partially as required, when the load is discharged into the
paver. Experience shows that this is extremely effective although material
at the tailgate (the flap at the rear end of the lorry) can be cold upon
discharge. Every effort should be made to retain heat in the material and
the adoption of sheeting which has greater insulation properties is strongly
recommended.
Clause 901.14 dictates that compaction begins as soon as the
uncompacted asphalt 'will bear the effects of the rollers without undue
displacement or surface cracking' and 'shall be substantially completed
before the temperature falls below the minimum rolling temperatures
given in BS 594: Part 2 and BS 4987: Part 7. This Clause has little
meaning for two reasons. Firstly, the specification for measuring such
temperatures, BS 598: Part 10929 (specified in BS 594: Part 2 2 and BS
4987: Part 24) requires measurements to be taken as near as possible to the
midpoint of the layer. Even if that is achieved their relevance is
questionable since the temperature varies throughout the layer, as
demonstrated earlier in this Chapter. It is the lowest temperature in the
mixture which is important, not the mid-layer temperature which is liable
to be close to the maximum. Secondly, there is no indication of what
constitutes 'substantial' compaction. Rolling (and therefore compaction)
has to continue far below the temperatures listed to eliminate roller marks.
Clause 901.15 specifies the use of
'8-10 tonnes deadweight smooth wheeled rollers having a width of roll
not less than 450 mm, or by multi-wheeled pneumatic-tyred rollers of
equivalent mass, or by vibrating rollers or a combination of these
rollers. Wearing course and basecourse material shall be surface
finished with a smooth-wheeled roller which may be a deadweight
roller or a vibratory roller in non-vibrating mode. Vibratory rollers
shall not be used in vibrating mode on bridge decks.'
Vibrations can affect elements of a structure.30 At particular frequencies
they can, depending on the type of bridge and its configuration, break
bonding of concrete, loosen bolts or cause cracking in welds.
Clause 901.16 qualifies the use of vibrating rollers by specifying that
they 'may be used if they are capable of achieving the standard of
compaction of an 81 deadweight roller'. They must be fitted with meters
which indicate the frequency of vibration and the speed. Such meters must
be readable from the ground. The performance of vibrating rollers is to be
assessed either by site trials in accordance with the requirements laid
down in BS 598: Part 10929 or by the contractor producing evidence of
independent trials which prove that the proposed vibrating roller achieves
a degree of compaction which is equivalent to that which would be
obtained by using an 81 dead weight roller. In relation to the former, BS
598: Part 10929 sets out a trial area which is split into two areas
longitudinally. One area is compacted by an 81 dead weight roller and the
adjacent area is compacted by the proposed vibrating roller. Specified
cores are taken and the densities obtained in accordance with the
procedure given in BS 598: Part 104.31 The mean density of the proposed
COMPACTION OF ASPHALTS 351
• the average in situ air voids content of each pair of cores <9%
• the average refusal air voids content of each pair of cores > 1 %
• the average binder volume at each location is >7%
• the aggregate grading and binder content comply with the contractor's
suggested target
• horizontal alignments, surface levels and surface regularity comply
with Clause 702.
If compliance is not achieved then a new grading and binder content
are proposed by the contractor and the testing is repeated until all the
above requirements are met.
Thereafter, the permanent works are checked by means of a NDG and
the testing of cores. In each lane, pairs of cores are to be taken every 500 m
and in situ air voids content and refusal air voids content obtained in
accordance with BS 598: Part 104.31 Using the NDG, readings are taken
every 20 m in alternate wheel tracks starting at a location where cores are
to be taken. Additional NDG readings are to be taken 300 mm from the
edge of the mat adjacent to each core location. Further compaction is
required if the NDG shows low densities provided the material is above the
minimum rolling temperature specified in BS 4987: Part 2. 4 In fact, there is
good reason to prohibit further compaction. As discussed in Section 8.5
below, over-compaction may result in crushing of the coarser aggregate
fractions. If this happens then the attributes of the mixture may well be
significantly reduced. Each NDG is initially calibrated against the trial
area cores and then each is re-calibrated against the results from loose
samples and the cores taken every 500 m if the individual gauge shows a
different bias. Loose samples are taken from the paver augers in
accordance with BS 598: Part 100.33 Note that NDGs only measure down
to about 80 mm. If the mat is much thicker then the core is to be inspected
visually for signs of increased voidage towards the interface. NDGs are
discussed in detail in TRL Supplementary Report 754. 36
The permanent works are acceptable if, for each mixing plant
• the average in situ air voids content from any six consecutive NDG
readings <8%, if not then cores are taken and the same criterion
applied
• the average in situ air voids content of each pair of cores taken every
500 m <9%
• the average refusal air voids content of any three consecutive pair of
cores taken every 500 m >Vi%, if not then new grading and binder
content must be suggested by the contractor
• the aggregate grading and binder content resulting from compositional
analysis undertaken in accordance with BS 598: Part 102 comply
with BS 4987: Part I 3 with additional requirements for HDMs
• horizontal alignments, surface levels and surface regularity comply
with Clause 702.
There are additional requirements for basecourse macadams placed below
porous asphalt wearing courses.
COMPACTION OF ASPHALTS 353
40
5 10 15 20 25
Air temperature: °C
Fig. 8.14. Limiting weather conditions for laying porous asphalt containing
200pen bitumen with natural rubber22
40
-
10 15 25
Air temperature: °C
Fig. 8.15. Limited weather conditions for laying porous asphalt containing
100pen bitumen with natural rubber "
356 ASPHALTS IN ROAD CONSTRUCTION
Condition A
Condition B
CO
<D Permitted under the specification
X 2
8 10 12
Time after deposition: min
Fig. 8.16. Heat content off chipped hot rolled asphalt wearing course under
varying physical conditions 88
while the condition which results in the lower heat content would be
permissible. Such is the complexity of the interaction of all the parameters
involved in heat flow from a hot asphaltic layer, it is suggested that simple
diagrams such as those above do not adequately reflect all prevailing
circumstances. Accordingly, the use of such diagrams is inappropriate.
100
Vibrating roller
96
Static roller
94
I
92
90
Number of passes
102
r- Vibrating roller x g
100
98
96
94
0)
92
90
86
4
Number of passes
In the UK, it is not unusual for contractors to use one or more vibrating
rollers on surfacing operations but to employ them in static mode only,
keeping the vibratory option for occasions when areas of the mat appear
to be under-compacted. This is inefficient and a waste of the potential of
vibrating rollers. This is also illustrated in Fig. 8.17. By contrast, Fig. 8.18
depicts the dangers of over-compaction.
'Bouncing' occurs when a particular material has been compacted to
refusal. The effect of further compactive effort is that the density of the
material oscillates about a particular value. Further compactive effort will
be felt through the steering of the roller with difficulty in retaining
control. Bouncing starts before it is felt through the steering. What is
particularly undesirable about this phenomenon is that it can result in the
aggregate crushing. This means that a portion of the aggregate is uncoated
and the mixture takes on the characteristics of an unbound material. In
essence, vibrational compaction will result in more efficient compaction
but it must be used with care. Over-compaction may adversely affect the
performance of the layer quite significantly.
It is important to study not only the price of the equipment but also its
performance characteristics. All manufacturers supply statistics on their
rollers.
COMPACTION OF ASPHALTS 359
Basecourse
(a)
Basecourse
(b)
De-densified asphalt
Basecourse
(c)
^ « Re-densified asphalt
Basecourse
Fig. 8.19. The stages of compacting chipped hot rolled wearing course: (a) hot
rolled asphalt wearing course laid on basecourse; (b) chippings placed on top of
hot rolled asphalt wearing course; (c) chippings partially embedded; (d)
chippings fully embedded
COMPACTION OF ASPHALTS 361
Fig. 8.20. The fretting of chipped hot rolled asphalt wearing course
8.6. Summary
This Chapter has examined the subject of compaction. Published work
supports the view that this process is fundamental to the successful
construction of pavements and that greater care is necessary in ensuring
adequate and homogeneous compaction across the full width of laid mats.
The differences between static and vibrational rolling were discussed,
along with the economic benefits of vibrational compaction. The
importance of amplitude — with the emphasis on training including the
adoption of rolling patterns — was advocated.
Surfacing contractors now have at their disposal the first of many
packages which will assist in exercising greater control on the surfacing
operation. These will ensure that compaction is based on knowledge and
experience and not guess work. Already, some rollers have a meter in the
operator's cabin which shows, by visual inspection, the degree of
compaction achieved as the roller passes over the material being
compacted. The same system could be extended to record detailed
information about the levels of compaction which are actually achieved
on a carriageway. Until these refinements become commonplace,
engineers and surfacing contractors will have to continue to exercise
great care when controlling the compaction of asphalts.
References
1. BRITISH STANDARDS INSTITUTION. Hot Rolled Asphalt for Roads and
other Paved Areas, Specification for Constituent Materials and Asphalt
Mixtures. BSI, London, 1992, BS 594: Part 1.
2. BRITISH STANDARDS INSTITUTION. Hot Rolled Asphalt for Roads and
other Paved Areas, Specification for the Transport, Laying and Compaction
of Rolled Asphalt. BSI, London, 1992, BS 594: Part 2.
3. BRITISH STANDARDS INSTITUTION. Coated Macadam for Roads and
other Paved Areas, Specification for Constituent Materials and for Mixtures.
BSI, London, 1993, BS 4987: Part 1.
4. BRITISH STANDARDS INSTITUTION. Coated Macadam for Roads and
other Paved Areas, Specification for Transport Laying and Compaction. BSI,
London, 1993, BS 4987: Part 2.
5. KLOUBERT H-J. Compaction of Bituminous Materials. Bomag-Menck
GmBH, Boppard, Germany, November 1997.
6. MARSHALL CONSULTING & TESTING LABORATORY. The Marshall
Method for the Design and Control of Bituminous Paving Mixtures. Marshall
Consulting & Testing Laboratory, Mississippi, 1949.
7. BRITISH STANDARDS INSTITUTION. Sampling and Examination of
364 ASPHALTS IN ROAD CONSTRUCTION
Bituminous Mixtures for Roads and other Paved Areas, Method of Test for
the Determination of Wheel-Tracking Rate and Depth. BSI, London, 1998,
BS 598: Part 110.
8. JACOBS F. A. Properties of Rolled Asphalt and Asphaltic Concrete at
Different States of Compaction. TRL, Crowthorne, 1977, Supplementary
Report 288.
9. LISTER N. W. and W. D. POWELL. The Compaction of Bituminous Base
and Base-Course Materials and its Relation to Pavement Performance. TRL,
Crowthorne, 1977, Supplementary Report 260.
10. LEECH D. and N. W. SELVES. Modified Rolling to Improve Compaction of
Dense-Coated Macadam. TRL, Crowthorne, 1976, LR 274.
11. HIGHWAYS AGENCY et al. Design Manual for Roads and Bridges,
Pavement Design and Maintenance, Traffic Assessment. TSO, London, 1996,
7.2.1, HD 24/96.
12. HUNTER R. N. An Examination of the Fretting of Hot Rolled Asphalt
Wearing Course. Heriot-Watt University, MSc thesis, Edinburgh, 1983.
13. DAINES M. E. Tests for Voids and Compaction in Rolled Asphalt Surfacing.
TRL, Crowthorne, 1995, PR 78.
14. POWELL W. D. and D. LEECH. Compaction of Bituminous Road Materials
using Vibratory Rollers. TRL, Crowthorne, 1983, LR 1102.
15. CORLEW J. S. and P. F. DICKSON. Methods for Calculating Temperature
Profiles of Hot-Mix Asphalt Concrete as Related to the Construction of
Asphalt Pavements. Proc. Tech. Sess. Asphalt Paving Tech., 1996, 35, 549-
50.
16. JORDAN P. G. and M. E. THOMAS. Prediction of Cooling Curves for Hot-
Mix Paving Materials by a Computer Program. TRL, Crowthorne, 1976, LR
729.
17. DAINES M. E. Cooling of Bituminous Layers and Time Available for their
Compaction. TRL, Crowthorne, 1985, RR 4.
18. HUNTER R. N. Calculation of Temperatures and their Implications for
Unchipped and Chipped Bituminous Materials During Laying. Heriot-Watt
University, PhD thesis, Edinburgh, 1988.
19. HUNTER R. N and G. R. MCGUIRE. Are Texture and Density in Hot
Rolled Asphalt Wearing Courses Incompatible? Journal of the Inst. of
Asphalt Tech., 1988, 40, 29-31.
20. HUNTER R. N. Cooling of Bituminous Materials During Laying. Journal of
the Inst. of Asphalt Tech., 1986, 38, 19-26.
21. BRITISH STANDARDS INSTITUTION. Sampling and Examination of
Bituminous Mixtures for Roads and other Paved Areas, Methods for
Determination of the Condition of the Binder on Coated Chippings and for
Measurement of the Rate of Spread of Coated Chippings. BSI, London,
1990, BS 598: Part 108.
22. HIGHWAYS AGENCY et al. Specification for Highway Works, Manual of
Contract Documents for Highway Works. TSO, London, 1998, 1.
23. HIGHWAYS AGENCY et al. Manual of Contract Documents for Highway
Works. TSO, London, 1998, 0-6.
24. HIGHWAYS AGENCY et al. Manual of Contract Documents for Highway
Works, Notes for Guidance on the Specification for Highway Works. TSO,
London, 1998, 2.
25. HIGHWAYS AGENCY et al. Design Manual for Roads and Bridges. TSO,
London, various dates, 1-15.
26. HIGHWAYS AGENCY et al. Design Manual for Road and Bridges,
COMPACTION OF ASPHALTS 365