Professional Documents
Culture Documents
Causesofinefficientsitecostmanagement PDF
Causesofinefficientsitecostmanagement PDF
net/publication/301769907
CITATIONS READS
0 312
3 authors, including:
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Zaher Youssef on 02 May 2016.
Abstract
The cost of construction projects has a long history of exceeding the planned cost. At the
project level, this is termed as “Project Cost over Run”. This research reviews the main
causes of the inefficiency in the existed cost management systems applied by the Arabian
Gulf Contracting Companies at the construction stage. The requirements of having an
efficient cost management system (recording, monitoring and controlling functions) have
been collected from previous researches to be used in a field survey on the construction
companies in the Arabian Gulf to highlight the main causes behind inefficient
management functions (monitoring and controlling of site costs in the construction
projects in the region. This research is the first part of a M.Sc. research work which has
been taken place on Saudi Arabian and Bahraini contracting companies to identify the
efficiency of existed cost monitoring and control methods applied by these companies in
their projects. The highlighted causes will assist project management of the construction
companies in the Arabian Gulf region, as well as the other contracting companies, in
evaluating and improving their monitoring and controlling their site cost at the
construction stage.
JoCETM (2014) 31-45 © STM Journals 2014. All Rights Reserved Page 31
Causes of Inefficient Site Cost Management Systems Al-Rawi et al.
costs and performance according to the up-to- (C/SCSC). Though, Earned Value has gained
date project costs and work progress. several names such as: performance
measurement tool, the Planned Value of Work
COST CONTROL METHODS Accomplished (PVWA), the Cost/Schedule
Generally, a few researches have been Planning Control Specification (C/SPCS) [2].
conducted on the construction cost control,
however, studies on cost control systems are US federal agencies implemented Earned
very rare. For simplification, the paper has Value Method. More organizations seem to be
classified the cost control systems into two more inclined to use EV Technique as the
main types: a separate cost-schedule methods market is becoming more competitive [3]. The
and the integrated cost-schedule control concept of earned value was illustrated by one
methods, as shown in Table 1. of researcher “The measurements of physical
performance against the planned, thus, predict
EARNED VALUE TECHNIQUE EVT the final cost and the schedule results.”
The concept of earned value has been around However, as a control tool, earned value is
for many years; however, 30 years have considered an integrated cost/schedule control
passed since it was part of what so-called: system [4].
cost/schedule control system criteria
- It considers the cost of activities at its earliest start and latest start
- Latest cost curve represents the minimum cost to the contractor
- The earliest cost curve represents the maximum cost
Integrated Cost/Schedule - The space between the two curves depends on the floats of the
Methods activities
- Cost-to date curve expresses the actual cost of the work completed
Cost Envelope - Value-to-date represents the value of work that is carried out in
accordance to the original estimate
- Critical activities must be sped up or slowed down according to
the difference
- The vertical intercept between the ends of value-to-date and cost-
to-date curves will determine whether the work is carried out
more or less than the estimated cost
JoCETM (2014) 31-45 © STM Journals 2014. All Rights Reserved Page 32
Journal of Construction Engineering, Technology and Management
Volume 4, Issue 3
ISSN: 2249-4723 (online), ISSN: 2347-7253 (print)
In addition to the projects volume criteria, is based on other criteria Table 6 which is
Saudi Companies classification takes into developed from Ministry of Works’
consideration technical and financial factors as classification criteria. All the items listed in
per Saudi Arabian classification of the sampling frame are related to the research
contractor’s agency updated on 21/09/2011 by topic after excluding the irrelevant cases, so
The Ministry of Rural and Municipality Affair that the building contractors were chosen as
as shown in Table 4. Appendix C provides a representative of construction companies in
list of the contractors obtained from general due to the fact that the contractors
contractors’ classification agency of Saudi classification does not classify companies as a
Arabia. Ministry of Works classifies the general construction type, rather, the current
construction companies based on the classification considers the contractor
maximum project value as shown in Table 5. specialization in more detailed activities.
However, Bahraini contractors’ classification
JoCETM (2014) 31-45 © STM Journals 2014. All Rights Reserved Page 33
Causes of Inefficient Site Cost Management Systems Al-Rawi et al.
JoCETM (2014) 31-45 © STM Journals 2014. All Rights Reserved Page 34
Journal of Construction Engineering, Technology and Management
Volume 4, Issue 3
ISSN: 2249-4723 (online), ISSN: 2347-7253 (print)
Table 7 shows the classification of Saudi and Bahrain and grade one and two in Saudi
Bahraini contractors into different construction Arabia where applying a cost control system
segments. The research is concerned with seem to be feasible.
building contractors in Bahrain and Saudi
Arabia (Eastern provinces and Riyadh). By using stratified sampling, (2 strata), two
Precisely, the research is also limited to samples have to be draw from the population,
contractors classified as grades AA and A in as shown in Table 8.
By using the proportionate allocation to strata as per the ratio given bellow:
Fn n 62
R= = = =0.42
Nn N 148 (1)
Where Fn is the sampling fraction for stratum h, the calculation is shown in Table 9 below.
JoCETM (2014) 31-45 © STM Journals 2014. All Rights Reserved Page 35
Causes of Inefficient Site Cost Management Systems Al-Rawi et al.
(ii) Category questions. (ii) Identify the question types and the
(iii) Scale or rating questions: Express the variables which are needed to be
respondent opinion in ranking order. measured.
In order to ensure that the designed questions (iii) Design the scale of measurement.
meet the objectives of the research, the
following steps have been followed: The above information has been compiled in a
(i) Break down each research question into data requirement table as shown in Table 10.
more detailed investigative questions.
Characteristics of the Research Sample It is clear that 74.4% of the sample has
The research is applied to the building projects value above 50 million US dollars,
companies according to the official and the majority of them (51.2%) are building
classification of the contractors. Table 11 contractors, however, 67.4% of total sample
shows the construction type for each company are building companies carrying out projects
in the sample (Saudi Arabia) with its of different values.
associated average project value.
JoCETM (2014) 31-45 © STM Journals 2014. All Rights Reserved Page 36
Journal of Construction Engineering, Technology and Management
Volume 4, Issue 3
ISSN: 2249-4723 (online), ISSN: 2347-7253 (print)
Table 11: Construction Type * Projects Value Average Cross Tabulation (Saudi Arabia).
Project Value Average
Construction Type 1–10 20–30 30–40 40–50 Above 50 Total
Million Million Million Million Million
Count 2 1 1 3 22 29
Building
% of Total 4.7% 2.3% 2.3% 7.0% 51.2% 67.4%
Count 0 0 1 0 1 2
Industrial
% of Total .0% .0% 2.3% .0% 2.3% 4.7%
Count 0 0 0 1 1 2
Transportation
% of Total .0% .0% .0% 2.3% 2.3% 4.7%
General Count 0 1 0 1 7 9
construction % of Total .0% 2.3% .0% 2.3% 16.3% 20.9%
Count 0 0 0 0 1 1
Infrastructure
% of Total .0% .0% .0% .0% 2.3% 2.3%
Count 2 2 2 5 32 43
Total
% of Total 4.7% 4.7% 4.7% 11.6% 74.4% 100.0%
Table 12: Construction Type against Projects Value Average Cross Tabulation (Bahrain).
Project Value Average
Construction Type 1–10 10–20 20–30 30–40 Above 50 Total
Million Million Million Million Million
Count 2 3 1 2 5 13
Building
% of Total 12.5% 18.8% 6.3% 12.5% 31.3% 81.3%
Count 0 0 0 0 1 1
Industrial
% of Total .0% .0% .0% .0% 6.3% 6.3%
General Count 0 0 1 0 1 2
construction % of Total .0% .0% 6.3% .0% 6.3% 12.5%
Count 2 3 2 2 7 16
Total
% of Total 12.5% 18.8% 12.5% 12.5% 43.8% 100.0%
JoCETM (2014) 31-45 © STM Journals 2014. All Rights Reserved Page 37
Causes of Inefficient Site Cost Management Systems Al-Rawi et al.
performance, while 16.3% ignore the (9) Although the profit/losses valuation (not
cost estimate in favor of work value considered as a real cost control method)
resulted from the periodical valuation. is still used by18.6% of the contractors.
Additionally, 2.2% of contractors do not Similarly, the cash flow method is used
have any kind of cost baseline. by 2.3% of the contractors.
(3) In breaking down the project into cost (10) Earned value method, which involves the
elements, 37.2% of the Saudi contractors comparison between actual costs of work
use WBS. However, the bill of quantities performed (ACWP), and budgeted cost
given by the client during bidding stage of work scheduled (BCWS) and budget
are being used in cost control by 34.9% cost of work performed (BCWP) is used
which further is broken down into its by only 9.3%.
constituents of material, manpower and (11) In addition to the main cost reports. The
plant. Eleven point six percent of the research survey shows the following cost
contractors are observed to depend on reports that are in use by the construction
breaking down the item into material, companies;
manpower and plants during planning, a) Thirty four point nine percent of the
however 7% of contractors do not contractors produce manpower reports
address detailed cost elements. showing budgeted man-hours against
(4) There are two methods of preparation actual man hours. Yet, 16.3% of
cost breakdown structure, the pre- contractors use the comparison of actual
defined item by the company or direct and indirect cost of labor force
international standards. This method is with the budgeted direct and indirect
used by the majority of the contractors cost. Eleven point six percent of the
(32.6%), while 30.2% use the method of contractors use the unit rate of labor
developing WBS for each project. force cost comparing with the standard
(5) Sixty two point eight percent of the unit cost or norms, while 20.9% of the
contractors produce the cost monitoring contractors do not have any manpower
reports on monthly basis, 16.3% produce cost reports.
a cost summary at project close out, b) Not very often, the contractors produce
4.7% of contracts produce both weekly material cost report: 39.5% of
and monthly cost reports, while the contractors who utilize material report
remaining 4.6% of contractors are cost of purchased item against actual
divided equally over yearly and quarterly cost of delivered item. 23.3% of
cost reports. contractors produce cost report taking
(6) Thirty nine point five percent of the into consideration the actual unit cost
contractors rely on a standard cost codes, versus budgeted unit cost measurement.
another 39.5% of contractors adopt On the other hand, 37.2% of contractors
project cost codes developed specifically don’t produce any material cost reports.
for a project. The rest of 20.9% remain c) Thirty two point six percent of the
without setting any cost codes system. contractors don’t have any equipment
(7) The contractors observe different reports, however, 46.5% of the
methods in this comparison. The most contractors record the total expenditures
common method (46.5%) is that the of equipment and compare it with the
budget is what do you mean? achieved planned expenditures. The remaining
quantity at the time of study is 20.9% deal with the unit cost and
calculated, and then the comparison is compare it against the planned unit cost
carried out between the actual costs and of a specific plant.
the budgeted cost of quantity achieved to (12) The results of the research field survey
date. of the actual used methods to calculate
(8) Sixteen point three percent of the actual costs have shown the following
contractors adopt the unit cost as a way indications:
of comparison. This method ignores the a) Forty four point two percent of the
actual performance against scheduled. contractors use time sheets to allocate
man-hours to specific cost codes, but
JoCETM (2014) 31-45 © STM Journals 2014. All Rights Reserved Page 38
Journal of Construction Engineering, Technology and Management
Volume 4, Issue 3
ISSN: 2249-4723 (online), ISSN: 2347-7253 (print)
23.3% utilize time sheets to allocate the define which part of work contributes to
man-hours to work item. However, cost overrun [7–11].
18.7% allocate cost inaccurately by
charging work hours cost to the whole For Bahraini Construction Companies
project either by an amount agreed by (1) The field survey of cost control methods
planning department or by in Bahraini contractors is summarized as
approximation. Eleven point six percent follows:
of the companies ignore charging a) Sixty two point five percent of the
manpower cost all together. When Bahraini companies produce cost reports
transferring man-hours into monetary on weekly, monthly basis, and yearly
terms, 62.8% of contractors calculate reports are less likely to be produced
basic wages based on the payroll, and 12.5% of contractors produce weekly
then adding the indirect cost like reports, 6.3% yearly reports. Some
travelling expenses and medical companies produce reports at two time
treatment cost. However, 18.6% of intervals either weekly or monthly (6.3%)
contractors have different methods or monthly and yearly (12.5%).
including multiplying the total man- b) Eighty one point three percent of the
hours charge by the general hourly rate respondents are depending on their cost
defined during estimation. The control systems on tender cost estimate.
remaining 4.7% of contract ignore this However, only 12.5% of them are
item. depending on cost standards which are
b) Forty eight point eight percent of the developed from past records, while 6.3%
contractors utilize time sheet for of them use cost indices in their
allocating equipment hours to a specific comparison process through their cost
cost center. In case the equipment’s are control systems
leased, the contractor charges monthly c) Break down structure (WBS) is a common
hours to the project on basis of lease way to break down the project works into
records. This method accounts for 27.9% the managerial elements in the estimation
of contractors. When transferring the stage. The researcher found that 37.5% of
plants hours into monetary terms, 39.5% the contractors are still depending on bill
of the companies charge the actual of quantities as cost control elements.
payment incurred by equipment usage, Some contractors had adopted work
only 20.9% consider the ownership and package and use them as elements of cost
depreciation, while 4.7% allocate fixed control. In addition to estimation and
amount decided by their planning procurement, 12.5% of the participants
department. concentrate on breaking down the project
c) In order to obtain the actual cost of items into equipment, materials and
material used in construction, 62.8% of manpower for preparing the breakdown
the construction firms utilize structure. Thirty seven point five percent
approximate methods by using the of them are depending on pre-defined
purchase orders and invoice values. standard item whilst 62.5% develop each
Field quantity report or material usage project breakdown structure tailored for a
against purchased value is another specific project.
method seems used by 25.6%. d) By a comparison between target cost and
(13) Despite of that 81.4% of contractors actual cost, we found out that 56.3% of the
stated that they can define the cost contractors use the dominant method
problems, or the operation causing cost which is comparing budgeted cost against
overrun, but in most cases there is no actual cost of work performed. For those
any systematic way in defining cost companies that prefer unit costing, the
overrun area. They are depending on the comparison between BOQ unit cost versus
experience. The other 18.6% of the actual unit cost is carried out when there is
companies reiterated that they could not no real cost control system. The only
financial control system they use which is
JoCETM (2014) 31-45 © STM Journals 2014. All Rights Reserved Page 39
Causes of Inefficient Site Cost Management Systems Al-Rawi et al.
JoCETM (2014) 31-45 © STM Journals 2014. All Rights Reserved Page 40
Journal of Construction Engineering, Technology and Management
Volume 4, Issue 3
ISSN: 2249-4723 (online), ISSN: 2347-7253 (print)
each criterion. Tables 13 and 14 summarize standard deviation and variance. Similarly,
the five criteria, and the descriptive statistics Tables 15 and 16 show the same details for
of the respondents rating score for Saudi Bahrain Construction Companies.
construction companies. They show the mean,
Table 13: Saudi Companies Descriptive Statistics for Efficiency of Cost Control Methods.
Criteria N Minimum Maximum Mean Std. Deviation Variance
The cost control system should be able to
41 2.00 5.00 3.8250 .90263 .815
monitor the current cost level
Variance between actual cost, budgeted cost
41 2.00 5.00 3.6750 .91672 .840
and expected cost
The cost control system must be reliable 41 2.00 5.00 3.7073 .95509 .912
The ability to make spotting on the area of
41 1.00 5.00 3.8750 1.01748 1.035
cost overrun
The cost statement can be read in the light of
41 2.00 5.00 3.7250 1.03744 1.076
the project schedule
JoCETM (2014) 31-45 © STM Journals 2014. All Rights Reserved Page 41
Causes of Inefficient Site Cost Management Systems Al-Rawi et al.
JoCETM (2014) 31-45 © STM Journals 2014. All Rights Reserved Page 42
Journal of Construction Engineering, Technology and Management
Volume 4, Issue 3
ISSN: 2249-4723 (online), ISSN: 2347-7253 (print)
normally higher than the projects handled head office as a simple method followed
by Bahraini contractors of same by some companies. Whilst the Bahraini
classification grade. Although the contractors use a common method of
contractors showed a high diversity in recording the lease rates and hours for
using a cost control method to the extent leasing machines as more frequently
that, in some cases some, details are Bahraini contractors rely on hiring. The
adapted to match the special requirements important thing that can be seen when the
of contractors. equipment is owned by the contractor is
(2) Although, the most contractors are that rarely the ownership cost and
forming the WBS during the estimation depreciations are considered upon
phase. There is much depended on obtaining equipment cost especially by
B.O.Q. which is provided by the clients. Saudi contractors. In Bahrain, higher
It is evident that no sufficient details in percentages of contractors consider these
(WBS) are worked out to exert better factors.
control of the elements of the project. (7) The majority of contractors use invoices
Work package is also used by small to allocate materials cost. This method
numbers of contractors as a controlling has drawbacks as the entire purchased
element starting from planning stage, quantities are not necessarily used in
procurement and construction cost construction. However, very few
control. contractors use the field quantity report
(3) The general method of setting WBS is the which expresses the actual quantity of
standard one and pre-defined typically for materials consumed against each item.
similar projects. Yet, in Saudi contractors (8) In obtaining cost variance the most
where projects are expected to be more dominant method is to use a budgeted
complex, the minority is using the cost versus actual cost of work done. In
project–tailored break down structure “unit costing method,” the comparison is
WBS. carried out by the cumulative unit cost;
(4) Contractors don’t seem to be wildly this method is totally dependent on
familiar with the concept of cost codes. quantity achieved without proper linkage
This phenomenon can be clearly to project schedule.
highlighted among Saudi contractors. (9) The cost statements, including cost
Generally, using pre-defined standard variances, are produced in most cases on
cost codes are the common method. This a monthly basis. In certain cases, and
practice can be validated for simple according to senior management
building construction, but, for more requirement, cost statements are produced
complex projects it would suffer from weekly or quarterly in addition to the
serious shortcomings. yearly reports.
(5) Less than half of the contractors in Saudi (10) There is no evidence that the users of
Arabia use the site time sheet to allocate current cost control methods can deduct
work hours to cost codes. They usually the cost variance integrated with schedule
use approximate methods and personal variance as the majority of Saudi
judgment in recording site hours, for contractors stated, except for Earned
equipment and material in particular. Value and PERT/cost method. Thus, there
More frequent use of accurate method is no adequate explanation of how this
was found in Bahraini companies. could be achieved in practice. Bahraini
However, in transferring man-hours into respondents have consistent answers
monetary terms, the direct and indirect regarding the inability to integrate cost
costs are considered. and schedule variance when the method
(6) Comparing with man-hours recording, has limited applicability to achieve this
book keeping the equipment working combination.
hours is taking less attention by the (11) The main function of a successful cost
contractors. In this case, some contractors control is to highlight the cost overrun
charge the project a fixed amount by the zone. Yet, most contractors expressed that
JoCETM (2014) 31-45 © STM Journals 2014. All Rights Reserved Page 43
Causes of Inefficient Site Cost Management Systems Al-Rawi et al.
the cost control system is having the research results in such a way that the
application to detect cost overrun area details of the used cost control methods of
from cost variances obtained. There is no the majority of the contracts don’t seem
adequate explanation about how this to comply with the criteria of effective
could be achieved in reality. cost control method such as; integration
(12) Most of the contractors demonstrated that of cost and schedule, the possibility of
unless cost variance is read in estimation of the cost at completion, and
coordination with the schedule status, it in addition to the feedback and corrective
won’t give full sense. The fact is that actions. These results can be explained by
most of prevailing cost control methods the following:
do not integrate cost and schedule a) Poor level of knowledge of the cost
variances in a quantitative measure. control tools.
Instead contractors rely on visual b) Most companies don’t have a specialized
observation and approximation methods department for project control that can
to cover this function. Additionally, in adopt the most effective methods.
case of a negative cost variance, no (16) The concept of integrated cost and
evidence that they use a systematic schedule control is not widely recognized
analysis in finding causes of undesired by cost control participants in the
cost variances. No any document to prove research.
that has been there corrective action. (17) One important conclusion is that even the
(13) The lack of a cost management plan that concept of Earned Value that was
summarizes how variance should be emerged decades ago, yet, it is not widely
handled is a major problem. However, recognized among cost control
investigating the causes of cost growth practitioners in construction companies in
and making corrective action by most this region. Furthermore, the concept of
contractors is made through informal earning value is often understood as the
methods such as, site meetings, without “value of the work” which means “cash
having to go deeply into the causes of the in” as it might be implied by the name
problem. The lack of proper connection itself. This misunderstanding clearly
between costing department and site appeared through the inconsistency
management seems to be evident and between the method title and the details
reduces the cost control outcome of the method as indicated by some
expectation. participants. Even though the interviewer
(14) Hybrid cost control methods including did try to influence the participants'
different methods applied on resource answers, the interview questions have
categories: manpower, equipment and introduced further clarification on the
materials. These methods are more methods details through the questionnaire
noticeable among Bahraini contractors appendixes. Remarkably, nearly half of
than Saudi contractors. This would imply the sample declared that they don’t know
that more cost control in Bahraini projects any details of the earned value
is being exercised. Noticeably, the techniques.
limitation of financial resources in (18) Lack of knowledge in terms of cost
Bahrain can be the reason beyond control methods must be highlighted,
exerting tight cost monitoring and control especially that the contractors who
over resources. participated in the research belong to the
(15) The objective of this research is to higher grade of classification (Grade I, II)
evaluate the effectiveness of cost control where the magnitude of potential over-
methods that are in use. One of the budgeting can’t be overlooked, and where
evaluation is by the respondents who are the need for more sophisticated methods
directly involved in cost control. The is urgent.
results of the evaluation indicated that, for (19) The cost control concept is not
all criteria most respondents ranked the sufficiently addressed in construction
cost control methods used by them as companies and usually misinterpreted
effective. This result contradicts with the with the financial control terms.
JoCETM (2014) 31-45 © STM Journals 2014. All Rights Reserved Page 44
Journal of Construction Engineering, Technology and Management
Volume 4, Issue 3
ISSN: 2249-4723 (online), ISSN: 2347-7253 (print)
(20) The degree of cost-awareness among 3. Eldin NN. Cost Control System For
project management team needs to be PMT Use, American Association of
upgraded. Cost Engineers. viewed Jan 14, 2011
(21) Lack of correlation between estimation (http://www.ascelibrary.org).
standards and used cost control methods 4. Harris F, McCaffer R., Modern
used in reality. The lack of coordination Construction Management. 6th Edn.
between estimation and cost control is Blackwell Publishing: UK; 2006.
affecting the effectiveness of the project 5. Potts K. Construction Cost
performance. Management: Learning from Case
(22) There is no specialized Cost control Studied, USA & CANAD. Taylor &
department and to create it is not always a Francis e-Library. SAGE Publications,
main part of the construction company. In Inc.: USA; 2008.
some projects, one may take the role of 6. Halpin WD, Bolivar A, Senior.
cost controller reporting to project Financial Management and Accounting
manager, and no clear coordination is Fundamentals of Construction. John
established with site project team or with Willy & Sons Inc.: New Jersey, USA;
other projects. 2009.
(23) The employed control method is suffering 7. Hwang YS. Proactive Planning and
from lack of a performance measurement Control of Construction Productivity
tool that compares between the planned and Cost Using Time Series Data, PhD
and the actual performance. Thesis University of Illinios, USA;
(24) Generally, the applied control methods do 2007.
not integrate cost into the schedule in 8. Oberlender DG. Project Management
quantitative measurement. This makes the for Engineering and Construction. 2nd
cost variance meaningless. The budgeted Edn. Mc Graw Hill: Singapore; 2000.
cost of work performed to date is the 9. Pilcher R. Principals of Construction
main tool for comparison. Management, McGraw-Hill Book
(25) Calculation of the actual cost is not in all Company: UK; 1976.
cases accurate, especially in calculating 10. Pilcher R. Project Cost Control in
material and equipment costs. They Construction. Mac Kay of Chatham:
mostly depend on approximate methods. Kent, UK; 1985.
(26) In most cases the cost variance is not 11. Ritz JG. Total Construction Project
connected quantitatively to schedule. It Management, McGraw-Hill; 1994.
may depend on quantity achieved without 12. Saunders M, Lewis P, Thornhill A.
considering the project progress. Research Methods for Business
(27) Although the lack of knowledge of Students. 3rd Edn., Pearson Education
Earned Value Technique cannot be Limited: London, UK; 2003.
overshadowed, there is a tendency to 13. Sears KS, Sears AG, Clough HR.
apply this technique. Yet, there has been a Construction Project Management: A
lack of the practical steps to be followed Practical Guide to Field Construction
by interviewing construction experts. Management. 5th Edn. John Willy &
Sons, Inc.: New Jersey, USA; 2008.
REFERENCES 14. Zamel AS. Cost Control in Eastern
1. Corby C. GCC Powers of Construction. Province Of Saudi Arabia. M.Sc.
Deloitte Financial Advisory Service, Thesis, King Fahd University for
Dubai Financial Centre, viewed March Petroleum and Minerals, Saudi Arabia;
29, 2012 (http://www. deloitte. com). 1991.
2. Halpin WD. Construction Management.
3rd Edn. John Wiley & Sons, Inc.:
USA; 2006.
JoCETM (2014) 31-45 © STM Journals 2014. All Rights Reserved Page 45