You are on page 1of 16

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/301769907

Causes of Inefficient Site Cost Management Systems in Arabian Gulf


Construction Companies

Article · January 2014

CITATIONS READS

0 312

3 authors, including:

Dr. Orabi Al-Rawi Zaher Youssef


Isra University, Jordan King Fahd University of Petroleum and Minerals
26 PUBLICATIONS   26 CITATIONS    1 PUBLICATION   0 CITATIONS   

SEE PROFILE SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Soils’ Organic Content View project

Mode choice Modelling of Riyadh commuters View project

All content following this page was uploaded by Zaher Youssef on 02 May 2016.

The user has requested enhancement of the downloaded file.


Journal of Construction Engineering, Technology and Management
ISSN: 2249-4723 (online), ISSN: 2347-7253 (print)
Volume 4, Issue 3
www.stmjournals.com

Causes of Inefficient Site Cost Management Systems in


Arabian Gulf Construction Companies
Orabi Al-Rawi1, Raji Al-Ani2*, Zaher A. Yousef3
1
Civil Engineering Dept., Isra University, Hyderabad, Sindh, Pakistan
2
Civil Engineering Department, Isra University, Jordan
3
Department of Construction Engineering, Senior Engineer in Joannou & Paraskevaides (J&P)
Overseas Contracting Company, Saudi Arabia

Abstract
The cost of construction projects has a long history of exceeding the planned cost. At the
project level, this is termed as “Project Cost over Run”. This research reviews the main
causes of the inefficiency in the existed cost management systems applied by the Arabian
Gulf Contracting Companies at the construction stage. The requirements of having an
efficient cost management system (recording, monitoring and controlling functions) have
been collected from previous researches to be used in a field survey on the construction
companies in the Arabian Gulf to highlight the main causes behind inefficient
management functions (monitoring and controlling of site costs in the construction
projects in the region. This research is the first part of a M.Sc. research work which has
been taken place on Saudi Arabian and Bahraini contracting companies to identify the
efficiency of existed cost monitoring and control methods applied by these companies in
their projects. The highlighted causes will assist project management of the construction
companies in the Arabian Gulf region, as well as the other contracting companies, in
evaluating and improving their monitoring and controlling their site cost at the
construction stage.

Keywords: project management, construction management, cost management, site


management

*Author for Correspondence E-mail: raji.alani@iu.edu.jo

INTRODUCTION such problem?” This paper is discussing the


The Construction industry is among the reasons behind this deficiency, and how can
world’s most growing sectors. In the Gulf the project management overcome these
Cooperation Council Countries (GCC); deficiencies on site. The research work in the
construction has been booming for long time, paper has been divided into two parts. The first
with the total value of projects in these part is discussing the evaluation of the existed
countries planned or underway on 20 July, site cost control methods, in order to identify
2009 totaling 2,677 billion USD [1], and the deficiency features. The second part of the
obviously, the project cost growth in this paper is discussing how these features were
sector will be deeply influential. With this then implemented in a proposed site control
rapid increase in the projects’ costs and management system for project managers in
complexity, the construction industry in these the GCC construction industry to assist them
countries is still suffering from a deficiency in to overcome any expected cost overrun on the
the applied site controlling systems. This site. The proposed site cost control system is
deficiency has caused excessive increases in promised to fulfill the needs of the GCC
the project completion costs. No previous construction industry for having an efficient
researches have tried to answer the question of site cost control system by using Earned Value
“why are the GCC construction projects Technique which has the ability to track site
suffering from increases in their completion construction cost and performance status, and
costs, and how it will be possible to eliminate give expectations of forwarded completion

JoCETM (2014) 31-45 © STM Journals 2014. All Rights Reserved Page 31
Causes of Inefficient Site Cost Management Systems Al-Rawi et al.

costs and performance according to the up-to- (C/SCSC). Though, Earned Value has gained
date project costs and work progress. several names such as: performance
measurement tool, the Planned Value of Work
COST CONTROL METHODS Accomplished (PVWA), the Cost/Schedule
Generally, a few researches have been Planning Control Specification (C/SPCS) [2].
conducted on the construction cost control,
however, studies on cost control systems are US federal agencies implemented Earned
very rare. For simplification, the paper has Value Method. More organizations seem to be
classified the cost control systems into two more inclined to use EV Technique as the
main types: a separate cost-schedule methods market is becoming more competitive [3]. The
and the integrated cost-schedule control concept of earned value was illustrated by one
methods, as shown in Table 1. of researcher “The measurements of physical
performance against the planned, thus, predict
EARNED VALUE TECHNIQUE EVT the final cost and the schedule results.”
The concept of earned value has been around However, as a control tool, earned value is
for many years; however, 30 years have considered an integrated cost/schedule control
passed since it was part of what so-called: system [4].
cost/schedule control system criteria

Table 1: Cost Control Methods.


Cost Control Cost Control
Description of the Method
Classifications Method
- Based on the interim valuation
Cost Value
- Total value is compared with the actual cost
Reconciliation
- Adjustment has to be made in order to compare like-for-like
(C.V.R.)
figures,
- Work is divided into major headings
- The unit costs can be compared with the values of work which is
Unit Costing
paid by the client to identify the loss and profit per unit of
measurement.
Separate Cost / Schedule - Suitable for the projects which consist of typical portions
Control Methods - Budget estimated either by cost, work hours or quantities each
work package
Contract Variance
- The cumulative of both actual total cost and percent of completion
will be compared with the planned budget to define the cost
overrun

- Selected losing part of work is spotted to be controlled


Spot Cost Control - Unit cost control method is chosen to identify the reasons of the
losses.

- Highly depends on the project schedule network


- Conclusion can be drawn whether the work is carried out at a cost
PERT/Cost Method
higher or less than the estimated by comparing the values of the
items

- It considers the cost of activities at its earliest start and latest start
- Latest cost curve represents the minimum cost to the contractor
- The earliest cost curve represents the maximum cost
Integrated Cost/Schedule - The space between the two curves depends on the floats of the
Methods activities
- Cost-to date curve expresses the actual cost of the work completed
Cost Envelope - Value-to-date represents the value of work that is carried out in
accordance to the original estimate
- Critical activities must be sped up or slowed down according to
the difference
- The vertical intercept between the ends of value-to-date and cost-
to-date curves will determine whether the work is carried out
more or less than the estimated cost

JoCETM (2014) 31-45 © STM Journals 2014. All Rights Reserved Page 32
Journal of Construction Engineering, Technology and Management
Volume 4, Issue 3
ISSN: 2249-4723 (online), ISSN: 2347-7253 (print)

EVT was proven by U. S. federal agencies to FIELD SURVEY OF OVER RUN


be an effective tool. Yet, Fleming and PROJECTS
Koppelman concluded that Earned Value was The practical terms of this research include the
not universally employed due to the belief of principal survey methods used to achieve the
the concept opponents that applying this objectives of the research. These methods
technique is not justified with the expected include data collection techniques, sampling
outcome. Whilst, Potts (2008) added that there principles, data tabulation and statistical
is a disinclination to adopt EVT [5]. However, analysis and discussing the results.
Fleming and Koppelman attributed the
reluctance to use EVT to the complicated and Data Collection
bureaucratic process in earned value The research is aimed at identifying the most
implementation since it was mandated as part critical causes of project cost overrun as the
of C/SCSC criteria in its inflexible and formal research objectives. Therefore, the directions
model. of collecting data will serve the specific
purpose of the research in terms of meeting the
In his study titled “implementation of EVT”, objectives and answer the research question.
one researcher suggested a new model of EVT
inspired by his major findings in Sampling and Population
implementation these techniques which are The considered sampling frame has included
summarized in the following issues [6]: Bahraini and Saudi Building Companies
(i) EVT methodology is in a continuous according to the national contractor’s
change, but the existing literature is not classification as shown in Table 2. The
consistent with the actual development of comprehensive sampling frame involves the
EVT. companies that deal with projects values of
(ii) No changes found in applying EVT in more than 70 million Saudi Riyals (SAR)
different sizes of construction projects. according to the official classification system
for contractors, which takes in consideration
(iii) A suggested new model of EVT would the financial capacity as the volume of projects
contribute positively to the wide that were undertaken as shown in Table 3.
acceptance of this technique.

Table 2: Grades of Construction Companies.


Item Classification Grades Specialization
Saudi Construction Companies–Eastern Province Grade 1, 2, 3,4,5 Building
Bahraini Construction Companies Grade AA, A, B, C, D Building

Table 3: Classification of Saudi Arabia Construction Companies.


Grades I II III IV V
Maximum Project Value Million ( SAR ) More Than 280 280 70 21 7

In addition to the projects volume criteria, is based on other criteria Table 6 which is
Saudi Companies classification takes into developed from Ministry of Works’
consideration technical and financial factors as classification criteria. All the items listed in
per Saudi Arabian classification of the sampling frame are related to the research
contractor’s agency updated on 21/09/2011 by topic after excluding the irrelevant cases, so
The Ministry of Rural and Municipality Affair that the building contractors were chosen as
as shown in Table 4. Appendix C provides a representative of construction companies in
list of the contractors obtained from general due to the fact that the contractors
contractors’ classification agency of Saudi classification does not classify companies as a
Arabia. Ministry of Works classifies the general construction type, rather, the current
construction companies based on the classification considers the contractor
maximum project value as shown in Table 5. specialization in more detailed activities.
However, Bahraini contractors’ classification

JoCETM (2014) 31-45 © STM Journals 2014. All Rights Reserved Page 33
Causes of Inefficient Site Cost Management Systems Al-Rawi et al.

Table 4: Saudi Criteria of Classification.


Category Headings Budget
Assets
Budget
Capital
Total revenue
Profit and loses Working capital
Net profit
Financial Assessment
Rate of profit
Monetary ratios Cash rate
Debt ratio
Administration system
Head office auditing
Financial system
Directors
Staff Engineers
Technicians
Equipment
Projects cost
Technical Assessment
Financial maximum load
Projects
Average yearly load
Projects of high cost
Site assessment
Owner opinion

Table 5: Classification of Bahrain Companies.


Project Value (BD)
More than 6 million 6 million 1000000 500000 200000 100000
( x 6.5 USD)

Table 6: Bahraini Classification Criteria Developed from Ministry of Works.


Projects Maximum Value of Contracts Sought
General manager
Contractors manager
Senior engineers
Quantity surveyors
Total number of employees
Site engineers
Staff Safety officer
General foreman
Skilled laborer
Supervisory staff
Site staff on current projects Skilled labor
Unskilled labor
Specialist Services e.g., precast factory, asphalt plant.
Capacity
Plant and Equipment
Ownership
Total value of work completed over 3 years.
Principle contracts completed over last 3 years
Contract period
Experience and References
Consultant
Work in progress
Value
% Completion

JoCETM (2014) 31-45 © STM Journals 2014. All Rights Reserved Page 34
Journal of Construction Engineering, Technology and Management
Volume 4, Issue 3
ISSN: 2249-4723 (online), ISSN: 2347-7253 (print)

Table 7: Saudi and Bahrain Contractors Activity Classification.


Saudi Arabian Classification Bahraini Classification
Building Building
Roads Mechanical Works for Building
Sanitary Electrical Works for Building
Marine Works Roads
Dams Road Traffic Signals
Landscaping Asphalt Category
Bridges & Highways
Rehabilitation
Sanitary
Sewage

Table 7 shows the classification of Saudi and Bahrain and grade one and two in Saudi
Bahraini contractors into different construction Arabia where applying a cost control system
segments. The research is concerned with seem to be feasible.
building contractors in Bahrain and Saudi
Arabia (Eastern provinces and Riyadh). By using stratified sampling, (2 strata), two
Precisely, the research is also limited to samples have to be draw from the population,
contractors classified as grades AA and A in as shown in Table 8.

Table 8: Research Population.


Contractors Grade No.
Grade AA 22
Bahrain Companies
Grade A 16
Sample Frame(1) Total 38
Saudi Arabia Grade (1) 61
(Riyadh + Eastern provinces) Grade (2) 49
Sample Frame (2) Total 110
Total Population 148

By using the proportionate allocation to strata as per the ratio given bellow:
Fn n 62
R= = = =0.42
Nn N 148 (1)
Where Fn is the sampling fraction for stratum h, the calculation is shown in Table 9 below.

Table 9: Sampling Fraction for Stratum.


Nn Companies on Wn Proportion of Nn = Stratum Fn Stratum
Stratum
Frame Population Sample Size Sampling Fraction
Bahrain companies grade AA, A 38 0.25 0.42 16
Saudi Companies grade 1,2
110 0.75 0.42 46
(Riyadh, eastern Provinces)
Total 148 1 0.42 62

Questionnaire Design Three types of questions are developed in the


Due to thorough literature review conducted in questionnaire as follows:
this research, the close-ended questions are (i) List questions where more than one option
appropriate to achieve the research objectives. is offered as to achieve descriptive
questions.

JoCETM (2014) 31-45 © STM Journals 2014. All Rights Reserved Page 35
Causes of Inefficient Site Cost Management Systems Al-Rawi et al.

(ii) Category questions. (ii) Identify the question types and the
(iii) Scale or rating questions: Express the variables which are needed to be
respondent opinion in ranking order. measured.
In order to ensure that the designed questions (iii) Design the scale of measurement.
meet the objectives of the research, the
following steps have been followed: The above information has been compiled in a
(i) Break down each research question into data requirement table as shown in Table 10.
more detailed investigative questions.

Table 10: Data Requirement Table, Concept: Saunders (2003).


Data Requirement Table
Research question /objectives: 1-identify the cost overrun causes 1-identify the cost methods 2-Evaluate these method in
term of effectiveness 3-suggest earned value technique to avoid weaknesses in the current system 4-identify the required
modification in the current system to suit the earned value application.
Type of Research: Descriptive-Deductive: Testing Hypothesis
Variables Question Question Section
S/No Investigation question Sub-question
(s) type (NO) (NO)
1 Frequency of cost reports behavior category 1 C

General description of the


2 behavior list 2 C
method

3 Cost control base behavior list 3 C


What are the cost
4 control method Work break down structure behavior category 4,5 C
components?
5 Cost codes behavior List 6 C
How the comparison between
6 target cost and actual cost is behavior list 7 C
being measured
7 Manpower report behavior list 8-a C
8 Materials report behavior list 8-b C
9 What are the cost Equipment reports behavior list 8-c C
control method
10 components? Calculation of actual cost behavior list 9,10 C
Transferring man- hours to
11 behavior list 10. 2 C
monetary term
12 variances behavior list 12 C

13 Corrective action behavior List 14 C


Identify the
14 effectiveness of cost Effectiveness ranking opinion rating C
control system
Possibility of Earned value
15 opinion rating 2 E
Earned value method employment
evaluation Effectiveness of earned value
16 opinion rating 3 E
method

Characteristics of the Research Sample It is clear that 74.4% of the sample has
The research is applied to the building projects value above 50 million US dollars,
companies according to the official and the majority of them (51.2%) are building
classification of the contractors. Table 11 contractors, however, 67.4% of total sample
shows the construction type for each company are building companies carrying out projects
in the sample (Saudi Arabia) with its of different values.
associated average project value.

JoCETM (2014) 31-45 © STM Journals 2014. All Rights Reserved Page 36
Journal of Construction Engineering, Technology and Management
Volume 4, Issue 3
ISSN: 2249-4723 (online), ISSN: 2347-7253 (print)

Table 11: Construction Type * Projects Value Average Cross Tabulation (Saudi Arabia).
Project Value Average
Construction Type 1–10 20–30 30–40 40–50 Above 50 Total
Million Million Million Million Million
Count 2 1 1 3 22 29
Building
% of Total 4.7% 2.3% 2.3% 7.0% 51.2% 67.4%
Count 0 0 1 0 1 2
Industrial
% of Total .0% .0% 2.3% .0% 2.3% 4.7%
Count 0 0 0 1 1 2
Transportation
% of Total .0% .0% .0% 2.3% 2.3% 4.7%

General Count 0 1 0 1 7 9
construction % of Total .0% 2.3% .0% 2.3% 16.3% 20.9%
Count 0 0 0 0 1 1
Infrastructure
% of Total .0% .0% .0% .0% 2.3% 2.3%
Count 2 2 2 5 32 43
Total
% of Total 4.7% 4.7% 4.7% 11.6% 74.4% 100.0%

Table 12: Construction Type against Projects Value Average Cross Tabulation (Bahrain).
Project Value Average
Construction Type 1–10 10–20 20–30 30–40 Above 50 Total
Million Million Million Million Million
Count 2 3 1 2 5 13
Building
% of Total 12.5% 18.8% 6.3% 12.5% 31.3% 81.3%
Count 0 0 0 0 1 1
Industrial
% of Total .0% .0% .0% .0% 6.3% 6.3%

General Count 0 0 1 0 1 2
construction % of Total .0% .0% 6.3% .0% 6.3% 12.5%
Count 2 3 2 2 7 16
Total
% of Total 12.5% 18.8% 12.5% 12.5% 43.8% 100.0%

The majority of Bahraini construction For Saudi Arabia Construction Companies


companies in the sample are classified as (1) The analysis of the Saudi Arabia
building contractors, precisely (81.3%) of the construction companies’ responses has
sample are carrying out building construction, shown that 62.8% of the Saudi
while (12.5%) of contractors are a General Companies using Monthly Cost
Construction Firms. Forty three point eight Statement with 58% of them using
percent of the contractors have project value Tender Cost Estimates, and 37.2% of
that exceeds 50 million USD as shown in them using Work Break Down structure
Table 12. in itemizing the BoQ, and finally 46.5%
using Budgeted Cost versus Actual Cost
Data Analysis and Evaluation of work done as a cost variance
Having collected the questionnaire forms and calculation methods.
data analyzed to be evaluated according to the (2) The cost estimate is used as a control
responses of the participants, the analysis and base by 58.1% of contractors. Only 4.7%
evaluation has come out with the following depend on the cost standards developed
remarks: in their companies based on

JoCETM (2014) 31-45 © STM Journals 2014. All Rights Reserved Page 37
Causes of Inefficient Site Cost Management Systems Al-Rawi et al.

performance, while 16.3% ignore the (9) Although the profit/losses valuation (not
cost estimate in favor of work value considered as a real cost control method)
resulted from the periodical valuation. is still used by18.6% of the contractors.
Additionally, 2.2% of contractors do not Similarly, the cash flow method is used
have any kind of cost baseline. by 2.3% of the contractors.
(3) In breaking down the project into cost (10) Earned value method, which involves the
elements, 37.2% of the Saudi contractors comparison between actual costs of work
use WBS. However, the bill of quantities performed (ACWP), and budgeted cost
given by the client during bidding stage of work scheduled (BCWS) and budget
are being used in cost control by 34.9% cost of work performed (BCWP) is used
which further is broken down into its by only 9.3%.
constituents of material, manpower and (11) In addition to the main cost reports. The
plant. Eleven point six percent of the research survey shows the following cost
contractors are observed to depend on reports that are in use by the construction
breaking down the item into material, companies;
manpower and plants during planning, a) Thirty four point nine percent of the
however 7% of contractors do not contractors produce manpower reports
address detailed cost elements. showing budgeted man-hours against
(4) There are two methods of preparation actual man hours. Yet, 16.3% of
cost breakdown structure, the pre- contractors use the comparison of actual
defined item by the company or direct and indirect cost of labor force
international standards. This method is with the budgeted direct and indirect
used by the majority of the contractors cost. Eleven point six percent of the
(32.6%), while 30.2% use the method of contractors use the unit rate of labor
developing WBS for each project. force cost comparing with the standard
(5) Sixty two point eight percent of the unit cost or norms, while 20.9% of the
contractors produce the cost monitoring contractors do not have any manpower
reports on monthly basis, 16.3% produce cost reports.
a cost summary at project close out, b) Not very often, the contractors produce
4.7% of contracts produce both weekly material cost report: 39.5% of
and monthly cost reports, while the contractors who utilize material report
remaining 4.6% of contractors are cost of purchased item against actual
divided equally over yearly and quarterly cost of delivered item. 23.3% of
cost reports. contractors produce cost report taking
(6) Thirty nine point five percent of the into consideration the actual unit cost
contractors rely on a standard cost codes, versus budgeted unit cost measurement.
another 39.5% of contractors adopt On the other hand, 37.2% of contractors
project cost codes developed specifically don’t produce any material cost reports.
for a project. The rest of 20.9% remain c) Thirty two point six percent of the
without setting any cost codes system. contractors don’t have any equipment
(7) The contractors observe different reports, however, 46.5% of the
methods in this comparison. The most contractors record the total expenditures
common method (46.5%) is that the of equipment and compare it with the
budget is what do you mean? achieved planned expenditures. The remaining
quantity at the time of study is 20.9% deal with the unit cost and
calculated, and then the comparison is compare it against the planned unit cost
carried out between the actual costs and of a specific plant.
the budgeted cost of quantity achieved to (12) The results of the research field survey
date. of the actual used methods to calculate
(8) Sixteen point three percent of the actual costs have shown the following
contractors adopt the unit cost as a way indications:
of comparison. This method ignores the a) Forty four point two percent of the
actual performance against scheduled. contractors use time sheets to allocate
man-hours to specific cost codes, but

JoCETM (2014) 31-45 © STM Journals 2014. All Rights Reserved Page 38
Journal of Construction Engineering, Technology and Management
Volume 4, Issue 3
ISSN: 2249-4723 (online), ISSN: 2347-7253 (print)

23.3% utilize time sheets to allocate the define which part of work contributes to
man-hours to work item. However, cost overrun [7–11].
18.7% allocate cost inaccurately by
charging work hours cost to the whole For Bahraini Construction Companies
project either by an amount agreed by (1) The field survey of cost control methods
planning department or by in Bahraini contractors is summarized as
approximation. Eleven point six percent follows:
of the companies ignore charging a) Sixty two point five percent of the
manpower cost all together. When Bahraini companies produce cost reports
transferring man-hours into monetary on weekly, monthly basis, and yearly
terms, 62.8% of contractors calculate reports are less likely to be produced
basic wages based on the payroll, and 12.5% of contractors produce weekly
then adding the indirect cost like reports, 6.3% yearly reports. Some
travelling expenses and medical companies produce reports at two time
treatment cost. However, 18.6% of intervals either weekly or monthly (6.3%)
contractors have different methods or monthly and yearly (12.5%).
including multiplying the total man- b) Eighty one point three percent of the
hours charge by the general hourly rate respondents are depending on their cost
defined during estimation. The control systems on tender cost estimate.
remaining 4.7% of contract ignore this However, only 12.5% of them are
item. depending on cost standards which are
b) Forty eight point eight percent of the developed from past records, while 6.3%
contractors utilize time sheet for of them use cost indices in their
allocating equipment hours to a specific comparison process through their cost
cost center. In case the equipment’s are control systems
leased, the contractor charges monthly c) Break down structure (WBS) is a common
hours to the project on basis of lease way to break down the project works into
records. This method accounts for 27.9% the managerial elements in the estimation
of contractors. When transferring the stage. The researcher found that 37.5% of
plants hours into monetary terms, 39.5% the contractors are still depending on bill
of the companies charge the actual of quantities as cost control elements.
payment incurred by equipment usage, Some contractors had adopted work
only 20.9% consider the ownership and package and use them as elements of cost
depreciation, while 4.7% allocate fixed control. In addition to estimation and
amount decided by their planning procurement, 12.5% of the participants
department. concentrate on breaking down the project
c) In order to obtain the actual cost of items into equipment, materials and
material used in construction, 62.8% of manpower for preparing the breakdown
the construction firms utilize structure. Thirty seven point five percent
approximate methods by using the of them are depending on pre-defined
purchase orders and invoice values. standard item whilst 62.5% develop each
Field quantity report or material usage project breakdown structure tailored for a
against purchased value is another specific project.
method seems used by 25.6%. d) By a comparison between target cost and
(13) Despite of that 81.4% of contractors actual cost, we found out that 56.3% of the
stated that they can define the cost contractors use the dominant method
problems, or the operation causing cost which is comparing budgeted cost against
overrun, but in most cases there is no actual cost of work performed. For those
any systematic way in defining cost companies that prefer unit costing, the
overrun area. They are depending on the comparison between BOQ unit cost versus
experience. The other 18.6% of the actual unit cost is carried out when there is
companies reiterated that they could not no real cost control system. The only
financial control system they use which is

JoCETM (2014) 31-45 © STM Journals 2014. All Rights Reserved Page 39
Causes of Inefficient Site Cost Management Systems Al-Rawi et al.

comparing cumulative valuation to date a) Manpower Reports: These reports show


against cumulative actual cost. Six point different management styles. Forty three
three percent of the contractors compare point eight percent of the contractors use
actual to budgeted cost through the work these reports to show the budget man-
package. Table 18 shows the hours against actual man-hours. Eighteen
characteristics of cost control system in point eight percent use the reports to show
use method by the Bahrain Construction the budgeted direct and indirect against the
Contractors. actual cost. Eighteen point eight percent of
(2) The analysis of the participants’ answers the contractors use less accurate reports to
on the questionnaire has shown the compare the hour rate with the standard
followings remarks: rate. Finally 12.5% use the combination of
a) Fifty percent of the contractors use time above two methods in their reports.
sheets in allocating working hours to a b) Material Reports: 68.8% of contractors use
specific cost control code. Similarly, material reports to compare the budgeted
43.8% use time sheet to allocate man- cost of material against actual cost.
hours to a specific item as well. Only 6.3% However, 31.3% of the contractors use
of the contractors don’t use any method of unit measurement cost of materials for the
allocating man-hours accurately instead, comparison reports for material.
but they use approximation. c) Equipment Report: 68.8% of the
b) When transferring the man-hours into cash contractors utilize the method of
for comparison purpose, 87.5% of cumulative plant expenditure against
contractors calculate the hour cost from actual plant expenditure in the equipment
sum of basic wages and adding the indirect report. Six point three percent adopt the
cost. Only 12.5% use pre-defined hour- production rate against the actual one in
rate to be multiplied later with the the reports, while and the 6.3% utilize
registered man-hours. more than one method. Notably, 18.8%
c) When pieced equipment is leased 68.8% never produce any equipment report.
of the contractor uses the lease record to (4) The purpose of obtainment variances is
estimate working hours. Generally 31.3% to identify the status of the project in
of the contractors who own equipment use terms of cost and schedule. Sixty two
the time sheets to allocate the working point five percent of Bahraini contractors
hours to a specific cost account. The obtain cost variance, while 37.5% of the
working hours of owned equipment need contractors obtain both cost and schedule
to be transferred into monetary terms, 50% variances. Eighty seven point five percent
of contractors use the actual payment as of the respondents stated that the cost
operating cost of the equipment. However, control employed can detect the area of
25% of them using rather a simplified cost overrun; the other 12.5% have not
method consisting of multiplying the been able to define this area. In the event
actual hours with the hourly budgeted rate. of undesired cost variance, the corrective
The remaining 25% of the contractors use action differs. Fifty percent use site
accurate estimation of the actual cost by investigation through meeting the site
considering ownership cost and people. Thirty one point three percent of
depreciation. the contractors are investigating the
d) Ninety three point eight percent of the resources cost. While 12.5% use work
contractors use purchasing orders and study to improve the construction method
invoices to obtain the material costs used in order to be more efficient [12–14].
in construction. Yet, 6.3% of them use
field quantity report to define the value of The Efficiency of the Existed Cost
materials as a proportion of the total Management Systems
construction costs. The participants were asked to evaluate the
(3) In addition to the main cost control cost control system that is used by their firms.
reports, the Bahraini contractors are To simplify the analysis, the evaluation has
producing the following reports: been designed based on five criteria. The
ranking scale of 5 grades was used to evaluate

JoCETM (2014) 31-45 © STM Journals 2014. All Rights Reserved Page 40
Journal of Construction Engineering, Technology and Management
Volume 4, Issue 3
ISSN: 2249-4723 (online), ISSN: 2347-7253 (print)

each criterion. Tables 13 and 14 summarize standard deviation and variance. Similarly,
the five criteria, and the descriptive statistics Tables 15 and 16 show the same details for
of the respondents rating score for Saudi Bahrain Construction Companies.
construction companies. They show the mean,

Table 13: Saudi Companies Descriptive Statistics for Efficiency of Cost Control Methods.
Criteria N Minimum Maximum Mean Std. Deviation Variance
The cost control system should be able to
41 2.00 5.00 3.8250 .90263 .815
monitor the current cost level
Variance between actual cost, budgeted cost
41 2.00 5.00 3.6750 .91672 .840
and expected cost
The cost control system must be reliable 41 2.00 5.00 3.7073 .95509 .912
The ability to make spotting on the area of
41 1.00 5.00 3.8750 1.01748 1.035
cost overrun
The cost statement can be read in the light of
41 2.00 5.00 3.7250 1.03744 1.076
the project schedule

Table 14: Saudi Companies Severity Index of Effectiveness.


Criteria Ranking Frequency Percent Severity Index
Very poor 0 0
Poor 4 9.3
The cost control system should be able to monitor the
Fair 8 18.6 71.16
current cost level
Effective 19 44.2
Very effective 9 20.9
Very poor 0 0
Poor 5 11.6
Variance between actual cost, budgeted cost and expected
Fair 10 23.3 68.37
Cost
Effective 18 41.9
Very effective 7 16.3
Very poor 0 0
Poor 5 11.6
The cost control system must be reliable Fair 11 25.6 70.70
Effective 16 37.2
Very effective 9 20.9
Very poor 1 2.3
Poor 2 4.7
The ability to make spotting on the area of cost overrun Fair 11 25.6 72.09
Effective 13 30.2
Very effective 13 30.2
Very poor 0 0
Poor 6 14.0
The cost statement can be read in the light of the project
Fair 10 23.3 69.30
schedule
Effective 13 30.2
Very effective 11 25.6

JoCETM (2014) 31-45 © STM Journals 2014. All Rights Reserved Page 41
Causes of Inefficient Site Cost Management Systems Al-Rawi et al.

Table 15: Bahraini Companies Descriptive Statistics.


Criteria N Minimum Maximum Mean Std. Deviation Variance
The cost control system should be able to
16 3.00 5.00 3.7500 .57735 .333
monitor the current cost level
Variance between actual cost, budgeted cost
16 3.00 5.00 3.8125 .54391 .296
and expected cost
the cost control system must be reliable 16 2.00 5.00 3.6250 .71880 .517
The ability to make spotting on the area of cost
16 3.00 5.00 3.7500 .68313 .467
overrun
The cost statement can be read in the light of
16 3.00 5.00 4.0000 .51640 .267
the project schedule

Table 16: Bahrain Companies Severity Index of Efficiency.


Criteria Ranking Frequency Percent Severity Index
Very poor 0 0
Poor 0 0
The cost control system should be able
Fair 5 31.3 75.00
to monitor the current cost level
Effective 10 62.5
Very effective 1 6.3
Very poor 0 0
Poor 0 0
Variance between actual cost, budgeted
Fair 4 25.0 76.25
cost and expected cost
Effective 11 68.8
Very effective 1 6.3
Very poor 0 0
Poor 1 6.3
The cost control system must be
Fair 5 31.3 72.50
reliable
Effective 9 56.3
Very effective 1 6.3
Very poor 0 0
Poor 0 0
The ability to make spotting on the area
Fair 6 37.5 75.00
of cost overrun
Effective 8 50.0
Very effective 2 12.5
Very poor 0 0
Poor 0 0
The cost statement can be read in the
Fair 2 12.5 80.00
light of the project schedule
Effective 12 75.0
Very effective 2 12.5

CONCLUSIONS inclined to use systematic method despite


The field survey connecting with the that their average volume of work is less
efficiency of the existed cost management than the Saudi Contractors. The last
systems has concluded the following: conclusion is a surprising one as it
(1) The majority of cost control methods contradicts with the fact that the more
followed by the contractors can’t be complex the project is, the more
considered as systematic from an sophisticated the cost control methods
academic view. However, it is noticed are. It should be noted that the project's
that Bahraini contractors are more value handled by Saudi contractors are

JoCETM (2014) 31-45 © STM Journals 2014. All Rights Reserved Page 42
Journal of Construction Engineering, Technology and Management
Volume 4, Issue 3
ISSN: 2249-4723 (online), ISSN: 2347-7253 (print)

normally higher than the projects handled head office as a simple method followed
by Bahraini contractors of same by some companies. Whilst the Bahraini
classification grade. Although the contractors use a common method of
contractors showed a high diversity in recording the lease rates and hours for
using a cost control method to the extent leasing machines as more frequently
that, in some cases some, details are Bahraini contractors rely on hiring. The
adapted to match the special requirements important thing that can be seen when the
of contractors. equipment is owned by the contractor is
(2) Although, the most contractors are that rarely the ownership cost and
forming the WBS during the estimation depreciations are considered upon
phase. There is much depended on obtaining equipment cost especially by
B.O.Q. which is provided by the clients. Saudi contractors. In Bahrain, higher
It is evident that no sufficient details in percentages of contractors consider these
(WBS) are worked out to exert better factors.
control of the elements of the project. (7) The majority of contractors use invoices
Work package is also used by small to allocate materials cost. This method
numbers of contractors as a controlling has drawbacks as the entire purchased
element starting from planning stage, quantities are not necessarily used in
procurement and construction cost construction. However, very few
control. contractors use the field quantity report
(3) The general method of setting WBS is the which expresses the actual quantity of
standard one and pre-defined typically for materials consumed against each item.
similar projects. Yet, in Saudi contractors (8) In obtaining cost variance the most
where projects are expected to be more dominant method is to use a budgeted
complex, the minority is using the cost versus actual cost of work done. In
project–tailored break down structure “unit costing method,” the comparison is
WBS. carried out by the cumulative unit cost;
(4) Contractors don’t seem to be wildly this method is totally dependent on
familiar with the concept of cost codes. quantity achieved without proper linkage
This phenomenon can be clearly to project schedule.
highlighted among Saudi contractors. (9) The cost statements, including cost
Generally, using pre-defined standard variances, are produced in most cases on
cost codes are the common method. This a monthly basis. In certain cases, and
practice can be validated for simple according to senior management
building construction, but, for more requirement, cost statements are produced
complex projects it would suffer from weekly or quarterly in addition to the
serious shortcomings. yearly reports.
(5) Less than half of the contractors in Saudi (10) There is no evidence that the users of
Arabia use the site time sheet to allocate current cost control methods can deduct
work hours to cost codes. They usually the cost variance integrated with schedule
use approximate methods and personal variance as the majority of Saudi
judgment in recording site hours, for contractors stated, except for Earned
equipment and material in particular. Value and PERT/cost method. Thus, there
More frequent use of accurate method is no adequate explanation of how this
was found in Bahraini companies. could be achieved in practice. Bahraini
However, in transferring man-hours into respondents have consistent answers
monetary terms, the direct and indirect regarding the inability to integrate cost
costs are considered. and schedule variance when the method
(6) Comparing with man-hours recording, has limited applicability to achieve this
book keeping the equipment working combination.
hours is taking less attention by the (11) The main function of a successful cost
contractors. In this case, some contractors control is to highlight the cost overrun
charge the project a fixed amount by the zone. Yet, most contractors expressed that

JoCETM (2014) 31-45 © STM Journals 2014. All Rights Reserved Page 43
Causes of Inefficient Site Cost Management Systems Al-Rawi et al.

the cost control system is having the research results in such a way that the
application to detect cost overrun area details of the used cost control methods of
from cost variances obtained. There is no the majority of the contracts don’t seem
adequate explanation about how this to comply with the criteria of effective
could be achieved in reality. cost control method such as; integration
(12) Most of the contractors demonstrated that of cost and schedule, the possibility of
unless cost variance is read in estimation of the cost at completion, and
coordination with the schedule status, it in addition to the feedback and corrective
won’t give full sense. The fact is that actions. These results can be explained by
most of prevailing cost control methods the following:
do not integrate cost and schedule a) Poor level of knowledge of the cost
variances in a quantitative measure. control tools.
Instead contractors rely on visual b) Most companies don’t have a specialized
observation and approximation methods department for project control that can
to cover this function. Additionally, in adopt the most effective methods.
case of a negative cost variance, no (16) The concept of integrated cost and
evidence that they use a systematic schedule control is not widely recognized
analysis in finding causes of undesired by cost control participants in the
cost variances. No any document to prove research.
that has been there corrective action. (17) One important conclusion is that even the
(13) The lack of a cost management plan that concept of Earned Value that was
summarizes how variance should be emerged decades ago, yet, it is not widely
handled is a major problem. However, recognized among cost control
investigating the causes of cost growth practitioners in construction companies in
and making corrective action by most this region. Furthermore, the concept of
contractors is made through informal earning value is often understood as the
methods such as, site meetings, without “value of the work” which means “cash
having to go deeply into the causes of the in” as it might be implied by the name
problem. The lack of proper connection itself. This misunderstanding clearly
between costing department and site appeared through the inconsistency
management seems to be evident and between the method title and the details
reduces the cost control outcome of the method as indicated by some
expectation. participants. Even though the interviewer
(14) Hybrid cost control methods including did try to influence the participants'
different methods applied on resource answers, the interview questions have
categories: manpower, equipment and introduced further clarification on the
materials. These methods are more methods details through the questionnaire
noticeable among Bahraini contractors appendixes. Remarkably, nearly half of
than Saudi contractors. This would imply the sample declared that they don’t know
that more cost control in Bahraini projects any details of the earned value
is being exercised. Noticeably, the techniques.
limitation of financial resources in (18) Lack of knowledge in terms of cost
Bahrain can be the reason beyond control methods must be highlighted,
exerting tight cost monitoring and control especially that the contractors who
over resources. participated in the research belong to the
(15) The objective of this research is to higher grade of classification (Grade I, II)
evaluate the effectiveness of cost control where the magnitude of potential over-
methods that are in use. One of the budgeting can’t be overlooked, and where
evaluation is by the respondents who are the need for more sophisticated methods
directly involved in cost control. The is urgent.
results of the evaluation indicated that, for (19) The cost control concept is not
all criteria most respondents ranked the sufficiently addressed in construction
cost control methods used by them as companies and usually misinterpreted
effective. This result contradicts with the with the financial control terms.

JoCETM (2014) 31-45 © STM Journals 2014. All Rights Reserved Page 44
Journal of Construction Engineering, Technology and Management
Volume 4, Issue 3
ISSN: 2249-4723 (online), ISSN: 2347-7253 (print)

(20) The degree of cost-awareness among 3. Eldin NN. Cost Control System For
project management team needs to be PMT Use, American Association of
upgraded. Cost Engineers. viewed Jan 14, 2011
(21) Lack of correlation between estimation (http://www.ascelibrary.org).
standards and used cost control methods 4. Harris F, McCaffer R., Modern
used in reality. The lack of coordination Construction Management. 6th Edn.
between estimation and cost control is Blackwell Publishing: UK; 2006.
affecting the effectiveness of the project 5. Potts K. Construction Cost
performance. Management: Learning from Case
(22) There is no specialized Cost control Studied, USA & CANAD. Taylor &
department and to create it is not always a Francis e-Library. SAGE Publications,
main part of the construction company. In Inc.: USA; 2008.
some projects, one may take the role of 6. Halpin WD, Bolivar A, Senior.
cost controller reporting to project Financial Management and Accounting
manager, and no clear coordination is Fundamentals of Construction. John
established with site project team or with Willy & Sons Inc.: New Jersey, USA;
other projects. 2009.
(23) The employed control method is suffering 7. Hwang YS. Proactive Planning and
from lack of a performance measurement Control of Construction Productivity
tool that compares between the planned and Cost Using Time Series Data, PhD
and the actual performance. Thesis University of Illinios, USA;
(24) Generally, the applied control methods do 2007.
not integrate cost into the schedule in 8. Oberlender DG. Project Management
quantitative measurement. This makes the for Engineering and Construction. 2nd
cost variance meaningless. The budgeted Edn. Mc Graw Hill: Singapore; 2000.
cost of work performed to date is the 9. Pilcher R. Principals of Construction
main tool for comparison. Management, McGraw-Hill Book
(25) Calculation of the actual cost is not in all Company: UK; 1976.
cases accurate, especially in calculating 10. Pilcher R. Project Cost Control in
material and equipment costs. They Construction. Mac Kay of Chatham:
mostly depend on approximate methods. Kent, UK; 1985.
(26) In most cases the cost variance is not 11. Ritz JG. Total Construction Project
connected quantitatively to schedule. It Management, McGraw-Hill; 1994.
may depend on quantity achieved without 12. Saunders M, Lewis P, Thornhill A.
considering the project progress. Research Methods for Business
(27) Although the lack of knowledge of Students. 3rd Edn., Pearson Education
Earned Value Technique cannot be Limited: London, UK; 2003.
overshadowed, there is a tendency to 13. Sears KS, Sears AG, Clough HR.
apply this technique. Yet, there has been a Construction Project Management: A
lack of the practical steps to be followed Practical Guide to Field Construction
by interviewing construction experts. Management. 5th Edn. John Willy &
Sons, Inc.: New Jersey, USA; 2008.
REFERENCES 14. Zamel AS. Cost Control in Eastern
1. Corby C. GCC Powers of Construction. Province Of Saudi Arabia. M.Sc.
Deloitte Financial Advisory Service, Thesis, King Fahd University for
Dubai Financial Centre, viewed March Petroleum and Minerals, Saudi Arabia;
29, 2012 (http://www. deloitte. com). 1991.
2. Halpin WD. Construction Management.
3rd Edn. John Wiley & Sons, Inc.:
USA; 2006.

JoCETM (2014) 31-45 © STM Journals 2014. All Rights Reserved Page 45

View publication stats

You might also like