PROJECT QUANTITY

DISTRIBUTION
M/s Dinesh Chandra R. Agrawal Infracon Pvt.Ltd.
Kalyani Expressway Project
North 24 Parganas

Bill of Quantity 14 Rainy Season 1 2 3 4 5


16 Dry Season 1 2 3 4
30 Total Month 1 2 3 4 5 6 7 8 9
Item Unit Qunatity Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20
Excavation cum 6,90,017.00 27,501.00 32,501.00 57,501.00 82,501.00
Excavation from Borrow cum 6,12,001.00 25,000.00 25,000.00 61,200.00 61,200.00
Earth work for RE Wall Use cum 66,341.00
Back Filling behind RE Wall cum 3,65,356.00
Sub Grade ( CBR 10%) cum 6,42,729.00 23,76,444.00 20,170.00 25,170.00 65,170.00 50,170.00
CT Sub Base cum 3,02,192.00 21,585.00 21,585.00
GSB cum 15,466.00 3,17,658.00 1,000.00 1,000.00 1,466.00
CT Base cum 1,22,534.00 9,425.00
WMM cum 1,801.00 1,24,335.00 150.00 150.00 150.00
Agg. Intermediate Layer cum 1,18,797.00 8,907.00
Prime Coat sqm 10,48,646.00 80,665.00
Tack Coat sqm 19,58,400.00
RAP Layer cum 16,299.00
DBM cum 41,724.00
BC cum 46,587.00 88,311.00
Concrete
M15 cum 27,681.00 1,000.00 2,129.00 2,129.00 2,129.00 1,129.00
M20 cum 15,732.00 1,210.00 1,210.00
M25 cum 80,037.00 1,334.00 3,334.00 3,334.00 3,334.00 3,334.00 650.00 684.00 3,334.00 3,334.00
M30 cum 2,473.00 103.00 103.00 103.00 103.00 103.00 103.00 103.00
M35 cum 68,199.00 435.00 2,435.00 3,717.00 3,717.00 3,717.00 3,717.00 3,217.00 3,217.00 3,217.00
M40 cum 50,576.00 2,44,698.00 156.00 1,806.00 1,806.00 2,218.00 2,218.00 1,806.00 1,806.00 1,806.00 1,806.00
RE Wall
Facia Panel sqm 86,111.00 17,222.20
R/F Steel MT 16,469.00 187.74 608.03 762.54 788.08 651.06 382.73 353.83 524.52 524.52
Kerb rmt 56000
PROJECT QUANTITY
DISTRIBUTION
M/s Dinesh Chandra R. Agrawal Infracon Pvt.Ltd.
Kalyani Expressway Project
North 24 Parganas

Bill of Quantity 6 7 8 9 10 11
5 6 7 8 9 10
10 11 12 13 14 15 16 17 18 19 20 21
Item Unit Nov 20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21 Jul-21 Aug-21 Sep-21 Oct-21
Excavation cum 67,501.00 77,501.00 77,501.00 77,501.00 77,501.00 77,501.00
Excavation from Borrow cum 61,200.00 61,200.00 97,400.00 97,400.00 61,200.00 61,200.00
Earth work for RE Wall Use cum 11,057.00 11,057.00 11,057.00 11,055.00 11,055.00 11,056.00
Back Filling behind RE Wall cum 30,446.00 30,446.00 30,446.00 30,446.00 30,446.00 30,446.00
Sub Grade ( CBR 10%) cum 25,170.00 32,170.00 40,170.00 65,170.00 48,170.00 40,170.00
CT Sub Base cum 21,585.00 21,585.00 21,585.00 21,585.00 21,585.00 21,585.00
GSB cum 1,000.00 1,000.00 1,000.00 2,000.00 2,000.00 2,000.00
CT Base cum 9,425.00 9,425.00 9,425.00 9,425.00 9,425.00 9,425.00
WMM cum 150.00 150.00 150.00 150.00 150.00 150.00
Agg. Intermediate Layer cum 8,907.00 8,907.00 8,907.00 8,907.00 8,907.00 8,907.00
Prime Coat sqm 80,665.00 80,665.00 80,665.00 80,665.00 80,665.00 80,665.00
Tack Coat sqm 1,63,200.00 1,63,200.00 1,63,200.00 1,63,200.00 1,63,200.00 1,63,200.00
RAP Layer cum 2,716.00 2,716.00 2,716.00 2,716.00 2,716.00 2,716.00
DBM cum 3,477.00 3,477.00 3,477.00 3,477.00 3,477.00 3,477.00
BC cum 5,176.00 5,176.00 5,176.00
Concrete
M15 cum 2,129.00 2,129.00 2,129.00 2,129.00 2,129.00 2,129.00
M20 cum 1,210.00 1,210.00 1,210.00 1,210.00 1,210.00 1,210.00
M25 cum 3,334.00 3,334.00 3,334.00 3,334.00 3,334.00 3,334.00 3,334.00 3,334.00 3,334.00 3,334.00
M30 cum 103.00 103.00 103.00 103.00 103.00 103.00 103.00 103.00 103.00 103.00
M35 cum 3,217.00 3,217.00 3,217.00 3,217.00 3,217.00 3,217.00 3,217.00 3,217.00 3,217.00 3,217.00 3,217.00 3,217.00
M40 cum 1,806.00 2,218.00 2,218.00 1,806.00 1,806.00 1,806.00 1,806.00 1,806.00 1,806.00 1,806.00 1,806.00 1,806.00
RE Wall
Facia Panel sqm 7,175.00 7,175.00 7,175.00 7,175.00 7,175.00 7,175.00
R/F Steel MT 524.52 757.08 757.08 731.54 731.54 731.54 731.54 524.52 311.43 311.43 524.52 524.52
Kerb rmt 6222 6222 6222 6222 6222 6222
PROJECT QUANTITY
DISTRIBUTION
M/s Dinesh Chandra R. Agrawal Infracon Pvt.Ltd.
Kalyani Expressway Project
North 24 Parganas

Bill of Quantity 12 13 14
11 12 13 14 15 16
22 23 24 25 26 27 28 29 30
Item Unit Nov-21 Dec-21 Jan-22 Feb-22 Mar-22 Apr-22 May-22 Jun-22 Jul-22
Excavation cum 17,503.00 17,503.00
Excavation from Borrow cum
Earth work for RE Wall Use cum
Back Filling behind RE Wall cum 30,446.00 30,446.00 30,446.00 30,446.00 30,446.00 30,446.00
Sub Grade ( CBR 10%) cum 20,170.00 40,170.00 45,170.00 45,170.00 40,170.00 40,170.00
CT Sub Base cum 21,585.00 21,585.00 21,585.00 21,585.00 21,585.00 21,585.00
GSB cum 1,000.00 1,000.00 1,000.00
CT Base cum 9,425.00 9,425.00 9,425.00 9,425.00 9,425.00 9,425.00
WMM cum 150.00 150.00 150.00
Agg. Intermediate Layer cum 8,907.00 8,907.00 9,907.00 9,907.00 9,907.00 8,907.00
Prime Coat sqm 80,665.00 80,665.00 80,665.00 80,665.00 80,665.00 80,665.00
Tack Coat sqm 1,63,200.00 1,63,200.00 1,63,200.00 1,63,200.00 1,63,200.00 1,63,200.00
RAP Layer cum
DBM cum 3,477.00 3,477.00 3,477.00 3,477.00 3,477.00 3,477.00
BC cum 5,176.00 5,176.00 5,176.00 5,176.00 5,176.00 5,176.00
Concrete
M15 cum 2,129.00 2,129.00 2,129.00
M20 cum 1,210.00 1,210.00 1,210.00 1,210.00 1,210.00
M25 cum 3,334.00 3,334.00 3,334.00 3,334.00 3,334.00 3,334.00 3,334.00
M30 cum 103.00 103.00 103.00 103.00 103.00 103.00 103.00
M35 cum 3,217.00 3,217.00 3,217.00 2,435.00 2,435.00 2,435.00 2,435.00
M40 cum 1,806.00 1,806.00 1,806.00 1,806.00 1,806.00 1,806.00 1,806.00
RE Wall
Facia Panel sqm 7,175.00 7,175.00 7,175.00 7,175.00 7,175.00 7,175.00
R/F Steel MT 524.52 731.54 731.54 683.05 551.06 551.06 476.04
Kerb rmt 6222 6222 6222 - - -