OUTSIDE PLANT PROJECT MANAGEMENT

FIELD/SITE INSTRUCTION No.

Date:
To:

This field/site instruction is for additional scope of


works and additional materials of the following work
activities:

Project Number: Exchange :


Project Description :

INSTRUCTION:
As Plan

Revision

The above activities of this field instruction will affect the contract in terms of :
Contract Time only Both Contract Price and Time
Contract Price only No Change in Contract Time and Price

Issued By :

OPPM-Site Engineer FxATOp-Site Engineer

Reviewed By :

OPPM-Division Head FxATOp-Division Head

Recommending Approval:

Head-OPPM Head-Reg'l FxATOp


Approved By:

Head-Build Head-TOC

Received By:
Contractor's Signature over printed Name and Date
( ) With Attachment/s ( ) Without Attachment Page 1 of 1