Note: Man hours includes excavation and loading onto truck/hauler. Soil Type Soil Manhours per one (1) cubic meters of Condition excavation First Lift 2nd Lift Third Lift Light Dry 1.4 1.84 1.84 Wet 2.1 1.97 1.97 Medium Dry 2.1 3.41 3.41 Wet 2.8 4.98 4.98 Heavy Dry 3.5 4.58 4.58 Wet 4.2 5.24 5.24 Hard Pan Dry 4.9 5.76 5.76 Wet 5.6 6.02 6.02