Name of Project :
Brief Description of the Project : All UG FOC Project
Classification: Regular Project
Contractor
Estimated number of Project per month
Proponent :
Contact Nos:

Supplies/Consumables/ot
No of Time Spent Per Total Tools/equipment required to complete the
No. Detailed activities Job Title Qty Amount hers required to Qty Amount REMARKS
Personnel site (In hours) Manhours activity
complete the activity

1 FOC Insertion via Fiber Blowing Fiber Blowing Operator 1 8 hours 8 hrs Fiber Blowing Machine 1 set Silicon Based lubricant 8 liters
Note: 1 set includes Air Compressor, Hydraulic
Power Pack, Cable Blowing Machine and
Accessories
2 assistant 10 8 hours 80 hrs Flat bed 10 wheeler truck 1 Compression Coupling 8 pcs
3 Closed Van 1 HDPE Pipe 16 meters
4 Pipe Slitter 1
5 Duct Cutter 1
6
7
8
9
10
11
12
13
14
15