Professional Documents
Culture Documents
(Phases) reduce the impact on the project if it doesoccur. This is also a good time to
Adrienne Watt identify all project stakeholders and establish acommunication plan describing
The project manager and project team have one shared goal: to carry out the the information needed and the delivery method tobe used to keep the
work ofthe project for the purpose of meeting the project’s objectives. Every stakeholders informed.
project has abeginning, a middle period during which activities move the project Finally, you will want to document a quality plan, providing quality targets,
towardcompletion, and an ending (either successful or unsuccessful). A standard assurance,and control measures, along with an acceptance plan, listing the
projecttypically has the following four major phases (each with its own agenda criteria to be met togain customer acceptance. At this point, the project would
of tasks andissues): initiation, planning, implementation, and closure. Taken have been planned in detailand is ready to be executed.
together, thesephases represent the path a project takes from the beginning to 3.3 Implementation (Execution) Phase
its end and aregenerally referred to as the project “life cycle.” During the third phase, the implementation phase, the project plan is put into
3.1 Initiation Phase motionand the work of the project is performed. It is important to maintain
During the first of these phases, the initiation phase, the project objective or control andcommunicate as needed during implementation. Progress is
need isidentified; this can be a business problem or opportunity. An appropriate continuously monitoredand appropriate adjustments are made and recorded as
response tothe need is documented in a business case with recommended variances from the originalplan. In any project, a project manager spends most
solution options. of the time in this step. Duringproject implementation, people are carrying out
Afeasibility study is conducted to investigate whether each option addresses the the tasks, and progress information isbeing reported through regular team
projectobjective and a final recommended solution is determined. Issues of meetings. The project manager uses thisinformation to maintain control over
feasibility (“canwe do the project?”) and justification (“should we do the the direction of the project by comparing theprogress reports with the project
project?”) are addressed. plan to measure the performance of the projectactivities and take corrective
Once the recommended solution is approved, a project is initiated to deliver the action as needed. The first course of action shouldalways be to bring the project
approved solution and a project manager is appointed. The major deliverables back on course (i.e., to return it to the original plan). Ifthat cannot happen, the
andthe participating work groups are identified, and the project team begins to team should record variations from the original plan andrecord and publish
takeshape. Approval is then sought by the project manager to move onto the modifications to the plan. Throughout this step, project sponsors
detailedplanning phase. and other key stakeholders should be kept informed of the project’s status
3.2 Planning Phase accordingto the agreed-on frequency and format of communication. The plan
The next phase, the planning phase, is where the project solution is further should beupdated and published on a regular basis.
developedin as much detail as possible and the steps necessary to meet the Status reports should always emphasize the anticipated end point in terms of
project’s objectiveare planned. In this step, the team identifies all of the work to cost,schedule, and quality of deliverables. Each project deliverable produced
be done. The project’stasks and resource requirements are identified, along should bereviewed for quality and measured against the acceptance criteria.
with the strategy for producingthem. This is also referred to as “scope Once all of thedeliverables have been produced and the customer has accepted
management.” A project plan is createdoutlining the activities, tasks, the final solution,the project is ready for closure.
dependencies, and time-frames. The project managercoordinates the
preparation of a project budget by providing cost estimates for thelabor, 3.4 Closing Phase
equipment, and materials costs. The budget is used to monitor and control cost During the final closure, or completion phase, the emphasis is on releasing the
expenditures during project implementation. finaldeliverables to the customer, handing over project documentation to the
Once the project team has identified the work, prepared the schedule, and business,terminating supplier contracts, releasing project resources, and
estimatedthe costs, the three fundamental components of the planning process communicating theclosure of the project to all stakeholders. The last remaining
are complete. step is to conductlessons-learned studies to examine what went well and what
This is an excellent time to identify and try to deal with anything that might pose didn’t. Through this typeof analysis, the wisdom of experience is transferred
athreat to the successful completion of the project. This is called risk back to the project organization,which will help future project teams.
management. Inrisk management, “high-threat” potential problems are
identified along with the actionthat is to be taken on each high-threat potential
Example: Project Phases on a Large the project documents, and the Chilean office was already working on
Multinational Project the next project. The accounting books were reconciled and closed,
A U.S. construction company won a contract to design and build the final reports written and distributed, and the project manager started
first copper mine in northern Argentina. There was no existing on a new project.
infrastructure for either the mining industry or large construction
projects in this part of South America. During the initiation phase of Activities
the project, the project manager focused on defining and finding a Chapter 3: The Project Life Cycle (Phases)
project leadership team with the knowledge, skills, and experience to
manage a large complex project in a remote area of the globe. The 1. Go online and search for project life cycle models. Identify at least two
project team set up three offices. One was in Chile, where large that are different from the PMI model, and compare and contrast the phases.
mining construction project infrastructure existed. The other two Be sure to cite your sources.
were in Argentina. One was in Buenos Aries to establish relationships 2. How does the application of a phased approach to project
and Argentinian expertise, and the second was in Catamarca—the management vary in different industries? Do you think that the phases work the
largest town close to the mine site. With offices in place, the project same in construction as they do in event management or software
start-up team began developing procedures for getting work done, development?
acquiring the appropriate permits, and developing relationships with
Chilean and Argentine partners. To be submitted on February 10,2020
During the planning phase, the project team developed an integrated 10:00am
project schedule that coordinated the activities of the design,
procurement, and construction teams. The project controls team also
developed a detailed budget that enabled the project team to track
project expenditures against the expected expenses. The project
design team built on the conceptual design and developed detailed
drawings for use by the procurement team. The procurement team
used the drawings to begin ordering equipment and materials for the
construction team; develop labor projections; refine the construction
schedule; and set up the construction site. Although planning is a
never-ending process on a project, the planning phase focused on
developing sufficient details to allow various parts of the project
team to coordinate their work and allow the project management
team to make priority decisions.
The implementation phase represents the work done to meet the
requirements of the scope of work and fulfill the charter. During the
implementation phase, the project team accomplished the work
defined in the plan and made adjustments when the project factors
changed. Equipment and materials were delivered to the work site,
labor was hired and trained, a construction site was built, and all the
construction activities, from the arrival of the first dozer to the
installation of the final light switch, were accomplished.
The closeout phase included turning over the newly constructed plant
to the operations team of the client. A punch list of a few remaining
construction items was developed and those items completed. The
office in Catamarca was closed, the office in Buenos Aries archived all
States, $122 million was wasted due to lacking project
The 4 Phases of the Project performance, according to Project Management Institute
Research.
Management Life Cycle Wasted money and resources can be prevented with
Posted By: Lucidchart Content Team effective project management, as 57% of unsuccessful
The 4 Phases of the Project Management Life projects fail due to communication breakdown. In the
Cycle phases of the project management life cycle, you come up
with the idea for a project, define its goals, plan for its
1. Initiation execution, and guide it to completion.
2. Planning
4 phases of the project management
3. Execution life cycle
4. Closure
The project management life cycle is usually broken down
Whether you’re working on a small project with modest into four phases: initiation, planning, execution, and
business goals or a large, multi-departmental initiative with closure. These phases make up the path that takes your
sweeping corporate implications, an understanding of the project from the beginning to the end.
project management life cycle is essential.
Note: Some methodologies also include a fifth phase—
Learn the four phases of the project management life cycle controlling or monitoring—but for our purposes, this
to keep your project organized and on track from initation phase is covered under the execution and closure phases.
to close.
You’ve received business approval, developed a plan, and Depending on the project management methodology you
built your team. Now it’s time to get to work. The follow, there are many visual tools that you can apply to
execution phase turns your plan into action. The project see which deliverables have been completed ensure that
manager’s job in this phase of the project management life your project remains on track. Click the Kanban board and
cycle is to keep work on track, organize team members, Gantt chart templates below to learn more.
manage timelines, and make sure the work is done
according to the original plan.
Scrum Board Example (Click on image to modify online)
Gantt Chart Example With Progress Bar (Click on image to
modify online)
4. Closure
Closing Phase
BSBA – III
PROJECT LIFE CYCLE MODEL:
Activities
Chapter 3: The Project Life Cycle (Phases)
1. Go online and search for project life cycle models. Identify at least two
that are different from the PMI model, and compare and contrast the phases.
Be sure to cite your sources.
2. How does the application of a phased approach to project
management vary in different industries? Do you think that the phases work the
same in construction as they do in event management or software
development?
ANSWERS:
1. * During the first of these phases, the initiation phase, the project
objective or need is identified; this can be a business problem or
opportunity. An appropriate response to the need is documented in
a business case with recommended solution options. A feasibility
study is conducted to investigate whether each option addresses the
project objective and a final recommended solution is determined.
Issues of feasibility (“can we do the project?”) and justification
(“should we do the project?”) are addressed.
1. Initiation
-to identify a business need, problem, or
opportunity and brainstorm ways that your team can
meet this need, solve this problem, or seize this
opportunity.
2. Planning
3. Execution
4. Closure
There are many visual tools that you can apply to see
which deliverables have been completed ensure that your
project remains on track.