1.

RAW DATA
Risk Assessment
Economic (Cost in Constructability Sustainability (Life
Design (Probability of Failure in
Pesos) (Duration in days) Span in years)
Percentage)
Sheet Pile 13,351,800.00 171 25 4.64
Gabion Wall System 5,000,000.00 594 80 0.8
Concrete Retaining
10,709,984.70 570 100
Wall 2.1

2. Normalized data
Risk Assessment
Economic (Cost in Constructability Sustainability (Life
Design (Probability of Failure in
Pesos) (Duration in days) Span)
Percentage)
1.00
Sheet Pile 10.00 10.00 1.00
10.00
Gabion Wall System 1.00 3.40 10.00
Concrete Retaining 3.85
Wall 1.51 1.00 6.95

Table 3
Gabion Wall Concrete Retaining
Weight (%)
Project Constraints Sheet Pile System Wall
Economic (Cost in Pesos) 0.30 1.00 10.00 3.85

Constructability (Duration in days) 0.30 10.00 1.00 1.51

Sustainability (Life Span in years) 0.25 10.00 3.40 1.00


Risk Assessment (Probability of Failure in
0.15 1.00 10.00 6.95
Percentage)
Weighted Sum 5.95 5.65 2.90

Table 4
Gabion Wall Concrete Retaining
Weight (%)
Project Constraints Sheet Pile System Wall
Economic (Cost in Pesos) 0.38 1.00 5.50 10.00
Constructability (Duration in days) 0.28 10.00 5.50 1.00
Sustainability (Life Span in years) 0.22 5.50 10.00 1.00
Risk Assessment (Probability of Failure in
0.12
Percentage) 6.40 1.00 10.00
Weighted Sum 5.16 5.95 5.50

Table 5
Gabion Wall Concrete Retaining
Weight (%)
Project Constraints Sheet Pile System Wall
Economic (Cost in Pesos) 0.35 1.00 5.50 10.00
Constructability (Duration in days) 0.15 10.00 5.50 1.00
Sustainability (Life Span in years) 0.38 5.50 10.00 1.00
Risk Assessment (Probability of Failure in
0.12
Percentage) 6.40 1.00 10.00
Weighted Sum 4.71 6.67 5.23

5.272 6.09 4.54340527


1. RAW DATA
Risk
Constructability Assessment
Economic (Cost in Sustainability (Life
Design (Duration in (Probability of
Pesos) Span in years)
days) Failure in
Percentage)
Soil Nailing 2,557,800.00 222 45 1.5
Coco Nets 1,805,985.00 315 40 0.002
Vegetation 1,038,987.00 60 200 1.1

2. Normalized data
Risk
Constructability Assessment
Economic (Cost in Sustainability (Life
Design (Duration in (Probability of
Pesos) Span)
days) Failure in
Percentage)
Soil Nailing 1.00 4.28 10.00 1.00
Coco Nets 5.46 1.00 10.29 10.00
Vegetation 10.00 10.00 1.00 3.40

Table 3
Project Constraints Weight (%) Soil Nailing Coco Nets Vegetation
Economic (Cost in Pesos) 0.30 1.00 5.46 10.00
Constructability (Duration in days) 0.30 4.28 1.00 10.00
Sustainability (Life Span in years) 0.25 10.00 10.29 1.00
Risk Assessment (Probability of Failure in
0.15 1.00 10.00 3.40
Percentage)
Weighted Sum 4.23 6.01 6.76

Table 4
Project Constraints Weight (%) Soil Nailing Coco Nets Vegetation
Economic (Cost in Pesos) 0.38 1.00 5.50 10.00
Constructability (Duration in days) 0.28 10.00 5.50 1.00
Sustainability (Life Span in years) 0.22 5.50 10.00 1.00
Risk Assessment (Probability of Failure in
0.12
Percentage) 6.40 1.00 10.00
Weighted Sum 5.16 5.95 5.50

Table 5
Project Constraints Weight (%) Soil Nailing Coco Nets Coco Nets
Economic (Cost in Pesos) 0.35 1.00 5.50 10.00
Constructability (Duration in days) 0.15 10.00 5.50 1.00
Sustainability (Life Span in years) 0.38 5.50 10.00 1.00
Risk Assessment (Probability of Failure in
0.12
Percentage) 6.40 1.00 10.00
Weighted Sum 4.71 6.67 5.23

4.700235294 6.209695068 5.830160214