Letter of instruction
Issue record
Issue Date Comments
4 Re-badge of RT/CE/S/011 into new numbering system
5 June 2006 Supersedes NR/L2/TRK/0011 Issue 4 with various
minor amendments.
6 June 2008 Updated to reflect Phase 2A reorganisation and
incorporate Letter of Instruction 46 (NR/BS/LI/046)
issued 4th April 2006. Renumbered NR/L2/TRK/3011
in line with Track documentation strategy
7 December 2012 Strikethrough version to indicate which sections of
Issue 6 are now included in other documents.
The new location of the requirement or guidance is
indicated at the end of each section struck through.
Compliance
This Network Rail standard is mandatory and shall be complied with by Network Rail
and its contractors if applicable from 01 December 2012.
When this standard is implemented, it is permissible for all projects, which have
formally completed GRIP Level 4, to continue to comply with the Issue of any
relevant Network Rail Standards current when GRIP Level 4 was reached and not to
comply with requirements contained herein unless the designated Standard Owner
has stipulated otherwise in the accompanying Briefing Note.
Reference documentation
See section 18.
Disclaimer
In issuing this document for its stated purpose, Network Rail makes no warranties,
express or implied, that compliance with all or any documents it issues is sufficient
on its own to ensure safe systems of work or operation. Users are reminded of their
own duties under health and safety legislation.
Supply
Copies of documents are available electronically, within Network Rail’s organisation.
Hard copies of this document may be available to Network Rail people on request to
the relevant controlled publication distributor. Other organisations may obtain copies
of this from an approved distributor.
Page 2 of 74
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
Contents
1 Purpose 7
2 Scope 7
3 Definitions 7
4 Design of new plain line CWR 10
5 Design of plain line CWR converted from jointed track 10
5.1 Approval by Network Rail 10
5.2 Rails for conversion by re-railing 10
5.3 Rails for conversion by welding in-situ 10
5.4 Welds and insulated joints 11
5.5 Sleepers, rail pads and longitudinal timbers 11
5.6 Rail fastenings 12
5.7 Ballast 12
6 Design of plain line CWR: Use of CWR on curves 13
6.1 Minimum radius of curvature at which CWR may be installed 13
6.2 Alignment and longitudinal level 13
7 Design of plain line CWR: Adjustment switches 13
7.1 Provision, siting and expansion gap 13
7.2 Removal of adjustment switches 13
8 Design of switches and crossings for use In CWR 13
8.1 General 13
8.2 Switches 14
8.3 CWR trap and catch points 15
8.4 Fixed crossings 15
8.5 Swing-nose crossings 16
8.6 Switch diamonds 16
8.7 Use of adjustment switches 16
8.8 Short lengths (less than 180m) of plain line between items of S&C 16
8.9 Minimum rail lengths and location of joints in S&C 17
Page 3 of 74
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
9.6 Anchors, tell tale points and pulling points 21
9.7 Cutting the rails 22
9.8 Rail supports during the stressing procedure 22
9.9 Movement of rails at the tell-tales 23
9.10 Measurement of rail temperature 23
9.11 Calculation of rail extension 24
9.12 Rail extension at reference points 24
9.13 Tensor stressing 25
9.14 Natural stressing 29
9.15 Thermal Stressing 30
9.16 Records 30
9.17 Review of SFT 31
9.18 Sites where no stressing records exist 31
9.19 Sites where the stress free temperature is known to have been
disturbed 31
10 Replacement of broken, cracked or defective rails, welds or insulated joints32
10.1. General 32
10.2. Replacement of a defective insulated joint or rail when the rail
temperature is below 21C 33
10.3. Replacement of a broken rail when rail temperature is below 21C 34
10.4. Replacement of a defective rail within tensor extension bars 34
11 Stressing of S&C within CWR 35
11.1 General 35
11.2 Anchor lengths and tell tales 36
11.3 Preliminary survey and considerations 36
Page 4 of 74
Page 5 of 74
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
Page 6 of 74
1 Purpose
This specification defines the requirements for the design, installation and
maintenance of continuous welded rail (CWR) track (for the purposes of this
specification “design” means “configuration”). It also specifies the methods to be
used when stressing CWR in plain line and switches and crossings.
2 Scope
3 Definitions
Adjustment switches
Joints with overlapping rail ends, allowing longitudinal rail movement and so
dissipating thermal forces when CWR abuts jointed track or other features not
designed to withstand thermal forces. Also used when thermal forces, additional to
those in CWR, may be encountered, such as at long underbridges which are
themselves subject to thermal movement.
Anchor (length)
The length of CWR track that is left clipped down during the stressing operation to
prevent any movement occurring at the fixed ends of the length being stressed.
Certificate of competence
Held by the Person in Charge of Stressing. There are three levels:
The Certificate of Competence is valid for five years (Note: the correct assembly,
operation and care of the tensor equipment is subject to separate training and
certification). For minimum competence requirements for stressing certification see
Appendix A
Page 7 of 74
Creep monitor
A device for monitoring creep of the heel of the switch blades on switches so fitted.
The type in normal use is known as “ball and claw”. These are not a stress transfer
devices.
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
Critical rail temperature (CRT)
The rail temperature to which CWR may be allowed to rise before measures to
protect traffic shall be taken. The CRT will depend on the stress-free temperature of
the rail and the quantity and degree of consolidation of the ballast.
Crossings
Suitable for incorporation in CWR are of two types:
1. Cast: are manufactured from cast steel either as a complete unit (i.e.
monobloc) or as a cast centre bloc crossing with welded-on leg ends.
2. Part-fabricated (or semi- or part-welded): have welded or cast vees, or
cast noses. An electro-slag welded vee is produced by machining rolled
rails and electro-slag welding them together. The wing rails are produced
from rolled rail and bolted or MGL-pinned to the vee.
Pull force
The force applied to a rail in order to extend it.
Pulling point
The location at which the rail is to be cut, tension applied and extension calculated.
Rail tensors
Hydraulic devices for extending CWR during stressing. In this specification a set of
tensors refers to sufficient equipment to tension both rails at the same time.
Reference points
Marks on each rail in line with a suitable reference mark on an adjacent unclipped
sleeper at equal intervals, e.g. 100m, in order to monitor and remeasure that the
calculated extension is obtained uniformly throughout the length of free rail being
stressed. They are numbered 1, 2, 3, etc. consecutively from the inner tell tale point
towards the pulling point (see diagram in para. 9.6).
Page 8 of 74
Rollers
Devices used to support CWR clear of the sleepers so as to allow its free
longitudinal movement during stressing.
Side rollers
(Support arms) are devices used to prevent lateral movement of CWR during
stressing. Their design varies to suit the sleeper and fastening type.
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
Spade ended steel sleepers
Steel sleepers where the whole sleeper end is forged down forming a broad “spade”
end that projects below the sleeper bottom. These are replacements for the now
obsolete crimp ended sleepers (which see).
Tensor stressing
The process of stretching CWR with hydraulic tensors so that the stress-free
temperature of the rails is at the upper permitted limit for SFT.
Stressing naturally
The clipping down of CWR, without tensors being used, when the rail temperature is
within the permitted limits for SFT.
Stress restoration
The process of stretching CWR so that the SFT of the rails is the same as it was
before the CWR was disturbed.
S&C
Switches and crossings, either individual built-up components or complete layouts.
Page 9 of 74
Tell-tales
Marks made on each rail in line with a suitable reference mark on an adjacent
unclipped sleeper, in order to monitor the effectiveness of the anchor length. A tell-
tale is required at each end of each anchor length: that adjoining the free rail is the
inner tell-tale, the other is the outer tell-tale (see diagram in para. 9.6).
Thermal stressing
Method of stressing where the rails are heated to the upper permitted limit for stress
free temperature and secured.
Watchman
A person appointed to monitor the track when the rail temperature exceeds the
CRT(W). He shall be equipped and competent to block the line in an emergency.
New CWR track shall comprise materials selected according to Track Category, in
accordance with NR/L2/TRK/2102 Track construction standards
All proposals to convert jointed track to CWR shall be subject to approval by the
Network Rail Principal Maintenance Support Engineer (Track) (PMSE(T).
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
Such approval will depend on adequate arrangements being made for anchor
lengths and lateral stability.
the rail depths are at least 2mm greater than the minimum shown in
NR/L2/TRK/001 Inspection and maintenance of permanent way and
there is no measurable gall, and
the rail has a residual life based upon sidewear considerations of at
least 5 years.
The history of rail defects within the length concerned shall be taken into
account prior to taking the decision to convert the length. Prior to
Page 10 of 74
Bond holes are not permitted within 30mm of the rail end.
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
Existing bolted joints shall be removed by cutting back beyond the bolt
holes. Minimum distances between bond holes or any other bolt holes,
and the weld, shall comply with NR/L2/TRK/130 and NR/L2/TRK/131.
CWR produced by in-situ welding may be formed initially from rails of any
length over 12m (Note: this allows for the cropping of existing 45-ft rails).
Page 11 of 74
The two sleepers each side of a weld (i.e. four in total) shall be of the same
material and depth.
The fastenings approved for the conversion of jointed track to CWR are shown
in Table 1.
5.7 Ballast
Prior to conversion, the ballast quality and depth shall be verified. If these do
not comply with NR/L2/TRK/2102 for the Track Category concerned, remedial
work may be required, e.g. ballast cleaning, excavation or track lifting.
Page 12 of 74
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
All ballast, including shoulder ballast, must be free of wet beds and able to
permit free drainage.
See NR/L2/TRK/2102.
See NR/L2/TRK/2102.
8.1 General
1. With stress transfer blocks and bolts connecting the switch to the stock
rail. Eight 25mm (1in) diameter High Tensile Steel (HTS) bolts,
tightened to a torque of 880 Nm (650 lb-ft), allow transfer of 70-tonne
thermal force. (Note: only those heel blocks with two bolts, or two
pairs of bolts, are deemed to be stress transfer blocks; they are
supplemented in DV-HV and EVS-HVS switches by single-bolt
distance blocks which do not transfer significant longitudinal force.)
This design is also found in some RT60 & NR60 C switches.
Page 13 of 74
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
S&C shall not be present within the stress transition length at the end of a
section of CWR. S&C not isolated from CWR by adjustment switches must be
fully stressed and any stress transition length must commence clear of the
S&C. All unstressed S&C must be isolated from CWR by adjustment switches.
S&C units not approved (see following paragraphs) for use in CWR, because
they have not been designed to withstand the longitudinal forces produced by
CWR, shall be isolated from adjacent CWR by adjustment switches positioned
not more than 40m distant, or replaced by CWR-compatible units.
8.2 Switches
Older inclined FB switch designs are not suitable for use in CWR, neither
are single and double slips nor any bull head designs.
Page 14 of 74
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
The lateral resistance of short (BV, CV and DV) full depth timbered
switches should be supplemented, e.g. either by fitting lateral resistance
end-plates to each end of each timber over the length of the stock rail
from the first heel block to two timbers beyond the stock rail front or by
the installation of castellated beams. This requirement is compulsory for
these switches when installed in lines with a speed of 100mph or higher.
When a crossing is replaced, any adjacent rails which are head-worn should be
replaced at the same time, since the use of lift-plates may induce bending in
the bearers.
Unless the crossing has welded-on legs, the joints between the casting
and the adjacent rails shall be formed by tight-joint fishplates with four
29mm (1 1/8") diameter HTS fishbolts torqued to 1020 Nm (750 lb-ft).
These joints shall not be lubricated.
Page 15 of 74
These types of common crossings shall have extended wings with each
wing rail being secured to the adjacent vee rail by at least eight 25.4mm
(1") diameter MGL pins or HTS bolts when used in CWR.
Mk Vl and VII types and all RT60 types are suitable for use in CWR.
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
the switch detection.)
Switch-diamond point rails shall be of the correct length so that the toes are
115mm from the knuckle when the rail temperature is 20C.
8.8 Short lengths (less than 180m) of plain line between items of S&C
Plain line between S&C may be welded or fitted with tight-joint or insulated
fishplates and as such shall be stressed. S&C suitable for use with CWR may
be used as part of an anchor length (but not within a stress transition length) for
stressing the length of plain line. If the recommended anchor lengths are not
available the length of track shall be stressed naturally (see para. 9.14 & 9.15).
Page 16 of 74
See NR/L2/TRK/2102.
Except for para. 9.1 and the requirements for cutting of CWR in 9.7, the
requirements of this section do not apply to the localised replacement of
defective or broken rails or insulated joints (not exceeding 36m in length),
where the provisions of section 10 shall apply.
Rollers shall be used in tunnels more than 180m long unless the rail has
time to acclimatise to the tunnel temperature in advance of the work. The
rail temperature at which the rail was clipped down shall be taken as the
SFT. CWR stressed to this temperature shall be confined to the length
between two points each of which is 40m inside the tunnel portals.
The SFTs of the two rails of the track shall be within the range given in
the definition of SFT. Where only one rail is being replaced but the other
rail has a history of disturbance or stress restoration then both rails shall
be re-stressed. If, however, the SFT of the other rail can be measured in
Page 17 of 74
advance of the work, and shown to be within the specified limits, then the
other rail need not be re-stressed.
When the SFT of a length of CWR is or has been disturbed then, in the
event of failure to achieve or restore a stress free temperature within the
permitted range, a CWR disturbance form shall be completed.
If there is evidence to suggest that the SFT is above 30C (or 32C for
crimp ended steel sleepers), then the section of track concerned should
be re-stressed before the onset of cold weather.
In summer, the rail temperature may rise fairly early in the day, and it is
desirable to complete stressing before 10.00 hours. If, however, the rail
temperature does rise above the upper limit given in 9.2.1 before
fastening down, the work should be completed in the usual way, the
temperature recorded and arrangements made for re-stressing when the
temperature has fallen sufficiently and before the onset of cold weather.
If any portion of CWR track has an SFT below 21C (whether because of
failure to stress, low temperature, or track curvature (see below)) it shall
be re-stressed before the onset of hot weather.
Stressing of rail on curves may induce a lateral shift of the track and for
this reason the maximum pull applied shall be limited as follows:
In cold weather these limits may preclude the achievement of the desired
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
Page 18 of 74
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
one curve or the other, not straddling the point of reversal (i.e.
when “pulling both ways” from a central pulling point, the
pulling point shall be located at the point of reversal). Side
rollers shall be used on both sides of the rail.
The term “stressing pull” applies to the stressing operation whether carried out
using hydraulic tensors or by other approved methods.
During the stressing pull, simple under rollers will displace by an amount equal
to half the extension effective at their position. In order to avoid those nearest
the pulling point rolling off the sleeper top, it may be necessary to limit the
maximum extension by limiting the length of pull.
If rail laid in an earlier shift is to be stressed, it is possible that the SFT of the
existing adjacent rail may have fallen in the vicinity of the join as a result of
movement at the join. Where the inner tell tale from stressing the adjacent rail
is available and can be returned to zero the multiple pull method in 9.13.4 may
be used. Where no tell tale is available the stressing length shall include at
least an anchor length of the adjacent rail.
For alternative methods the maximum length of free rail shall be limited
to that given for a single pull when stressing with tensors.
Page 19 of 74
The plain line within one anchor length of the toes of switches shall be
treated as S&C for the purposes of stressing.
When stressing plain line adjacent to switches the anchor length shall not
extend into the switches and at least one anchor length from the toes of
the switches shall remain fully clipped down.
Before the planned date for stressing the following shall be checked through
the length to be stressed and the anchor lengths (in some cases the items may
be attended to during the stressing operation, rather than beforehand):
The position of anchor lengths, lengths of rails to be pulled and the location of
closing welds shall be selected. Account should be taken of the influence
which cuttings, embankments, the period of the year and the time of day, may
have on rail temperatures during the stressing operation.
Page 20 of 74
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
Tell tale points shall be marked (on both rail and sleeper) at each end of each
anchor length in order to monitor the effectiveness of the anchor. The sleepers
used shall be freed from all rails.
The relationship between the pulling point, the length of free rail to be pulled
and the anchors is shown below.
OTT ITT RP1 RP2 X RP2 RP1 ITT OTT
anchor L1 unclip L1 unclip anchor
OTT = outer tell-tale ITT = inner tell-tale RP = reference point X = pulling point
L1 = 90m minimum, but 180m minimum if adjustment switches have been removed at X.
= 900m maximum on straight track (but less on curves - see para. 9.13.4)
Anchor: see table above.
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
The pulling point shall be at least 4.5m from another weld or joint, mid-way between
two sleepers and where possible should be the mid-point of the length of rail being
stressed.
Page 21 of 74
The first cut into CWR shall be by flame cutting. Subsequent cuts shall be
made by a method approved for the rail steel concerned.
When cutting the rails for the extension, the required total extension shall be
marked on the rail at the pulling point and allowance made for
If, on making the first cut into installed CWR, an unexpectedly large gap opens,
then the reason for this shall be thoroughly investigated and action taken
accordingly.
Fastenings shall be released commencing from the cut or free end and the rails
lifted clear of all obstructions and placed on solid rollers positioned at intervals
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
not exceeding 12 sleepers. Correct positioning of the rollers between the rail
foot and the rail seat is shown below:
Side rollers or support arms shall be used on the inside of curved track at the
intervals in Table 3. They should be staggered so that there is only one roller
per sleeper.
Page 22 of 74
When natural or thermal stressing, side rollers shall be used on alternate sides
of the rail throughout the length of pull.
When tensor stressing, consideration shall be given to the risk of tipping of the
rail. Where such a risk exists, side rollers shall be fitted on both sides
throughout.
Any movement of the rail at the tell-tales, when the fastenings are released,
shall be noted.
Movement at the outer tell-tale indicates that the anchor is not satisfactory and
a new anchor length shall be established.
Movement of the inner tell-tale may be towards or away from the pulling point,
depending upon the SFT of the anchor. Movement towards the pulling point
should be ignored; movement away shall be added to the calculated extension
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
(see Appendix B).
9.10.1 Thermometers
Thermometers shall be placed at the centre of the rail web on the shaded
side of each rail. At least three thermometers (3 reading locations for
digital thermometers) should be used on each rail, located
Page 23 of 74
When the readings of all thermometers are reasonably uniform, and after
not less than ten minutes (except for the digital contact type), an average
shall be taken. If any reading is obviously inconsistent with the
remainder a check should be made by changing the thermometer(s)
concerned. The readings used to calculate the extension shall be taken
at the last possible moment before marking the reference points.
The calculation of rail extension shall be based on the average rail temperature
over the length of the rail to be stressed or re-stressed. The rail extension
required, to produce a stress free condition at the rail temperature specified
below, shall be calculated by the formula e = 1000 LXt, where
e = extension in millimetres
L = the length of free rail in metres
X = coefficient of expansion of steel (0.0000115 per C for normal grade
rail)
t = difference between actual average rail temperature and required SFT.
Calculated extensions for various lengths of free rail for rail temperatures in the
range -8C to 27C, and examples showing how extensions are calculated, are
given in Appendix B.
Where rail temperatures are changing rapidly it will be necessary to repeat the
calculations unless they differ by no more than 2C from the previous reading.
The SFT shall be 27C except for crimp ended steel sleepers which shall be
stressed to 32C, and rail in tunnels more than 180m long where the SFT shall
fall within the ambient temperature range of the tunnel in question.
The full calculated extension shall be marked accurately at the free end (pulling
point) and the proportional movement marked at regularly-spaced (e.g. 100m
apart) intermediate reference points so that the rail movement may be
monitored during tensioning. The marking shall be carried out in such a way
that the movement can be measured to an accuracy of one millimetre. At the
reference points any sticking pads shall be freed in order to prevent movement
of the sleeper with the rail.
Page 24 of 74
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
9.13.1 General
60 tonnes;
10 tonnes less than the maximum capacity of the tensors.
When this maximum pull is insufficient to achieve the full rail extension,
an extension equivalent to the maximum pull shall be calculated and
applied. In such cases the required SFT will not be obtained and it may
be necessary for the CWR length to be re-stressed.
Page 25 of 74
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
Where rail temperatures are approaching the required SFT and the
closing welds have not been made, then the tensors must be removed
and the process completed as for natural stressing (allowable under
level(ii) competency in this case only). Where the closing welds have
been made then clipping down at rail temperatures above the required
SFT shall only continue provided that either:
If none of the above precautions has been carried out, then clipping
down shall cease, and all persons shall be kept clear of the unclipped rail
until rail temperatures drop back to the required SFT.
9.13.2 Method
Page 26 of 74
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
welding gap and complete the welds at the pulling point, with the
tensors in position (para. 9.13.6).
xiv. Remove all rollers. Replace all pads, insulators and clips.
xv. Remove tensors (para. 9.13.7). Remove welding debris. Fill cribs
with ballast. Pack all sleepers.
xvi. Fill out stressing certificate (para. 9.16).
Where the radius changes through the pulling length, the maximum
length to be pulled in one direction shall be determined by the minimum
radius.
Provided that the overall length to be stressed does not exceed double
the lengths in Table 4 and the tensor capability (load and extension) is
adequate, the required extension should be obtained over the whole
length by “pulling both ways” from a central pulling point: see diagram in
para. 9.6. When pulling both ways the lengths to be pulled should be as
nearly equal as possible.
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
Page 27 of 74
2. Final operation
Page 28 of 74
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
When the required total extension in each rail has been obtained, at
least 40m of rail on each side of the tensors shall be fastened down.
The welder shall check that the welding gap is correct for the type of
weld to be made, and re-cut the gap if necessary. Once a weld is
started there shall be no disturbance to that rail or the opposite rail of the
same line until the weld is completed and the cooling period has
elapsed.
The tensors shall remain in position for the minimum time specified in
NR/L2/TRK/032, after the weld has been made, in order to avoid hot
tears.
Natural stressing is achieved when, having had the rail free on rollers, it is
clipped down at a rail temperature between 24C and 30C (27C and 32C for
crimp ended steel sleepers).
Clipping down shall commence at the anchor and finish at the free end, care
being taken that the free end is not obstructed.
Method
i. Identify the positions and lengths of the anchors, lengths to be pulled,
and pulling points (from site survey para. 9.5).
ii. Mark the outer and inner tell tales, any reference points and the
pulling point (para. 9.6). Unclip tell tales and reference points.
iii. Cut the CWR at the pulling point (para. 9.7).
iv. Unclip the rails from the pulling point towards the inner tell tales.
v. Place unclipped rails on rollers and position side rollers (para. 9.8).
Splay the rail ends so that they can pass during the natural stressing
process
vi. Check any movement at the tell tales (para. 9.9).
vii. Measure and monitor rail temperature (para. 9.10).
viii. When rail temperature reaches the minimum specified temperature
confirm whether the rail is free and then commence removal of rollers
and clipping down, commencing from the anchor and working
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
Page 29 of 74
ix. Monitor rail temperature and continue to clip down until the pulling
point is reached.
x. Cut the rail(s) to produce the correct welding gap and complete the
welds at the pulling point.
xi. Remove welding debris. Fill cribs with ballast. Pack all sleepers.
xii. Fill out stressing certificate (para. 9.16).
During cold weather thermal stressing using rail warmers may be used as an
alternative to tensors, subject to Network Rail approval of the equipment and
process.
The rail warmers shall be used to obtain and maintain a rail temperature of 27C
(32C for crimp ended steel sleepers), with the rail free on rollers.
The process shall detail the sequence of events and the precautions necessary
to retain the correct stress free temperature within the rail as the process
proceeds.
9.16 Records
If the stress free temperature that has been achieved/obtained is not within the
specified range then the site shall be clearly marked as a stress required site.
Page 30 of 74
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
The person in charge of stressing shall produce the records at the same time
as the process is carried out with the exception of those derived from VERSE
tests. Stressing records derived from VERSE tests shall be produced from a
detailed analysis of the VERSE results on the next working day following the
test.
Details of the stress free temperature shall be passed to the person responsible
for hot weather precautions for the site within 24 hours
Consideration shall be given to re-measuring the SFT where the record is more
than 20 years old. Where there are reasons to expect that the original stress
condition has changed, e.g. where rail creep has occurred, the SFT should be
re-measured.
CWR sites for which no historical stressing records exist, but which are
reasonably believed to have been stressed and which have no history of stress
disturbance shall be classified as “stress unknown” sites.
Stress unknown sites shall be programmed for work to enable valid stressing
records to be obtained. The prioritisation shall be carried out using the method
detailed in Appendix F. Now NR/L2/TRK/001/mod03
9.19 Sites where the stress free temperature is known to have been
disturbed
CWR sites where the stress free temperature is known to have been disturbed
and where stress restoration or re-stressing has not been carried out, and all
sites where the SFT is known to be outside the permitted range shall be
classified as “stress required” sites.
Stress required sites shall be programmed for work to enable valid stressing
records to be obtained. The prioritisation of stress required sites shall be based
on the known SFT or on the likely SFT (dependant on the time of the year that
the track was disturbed). Sites having the lowest CRT shall have the highest
priority.
Obtaining valid stressing records for stress required sites shall normally take
priority over similar work on stress unknown sites.
Page 31 of 74
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`
10.1. General
The following paragraphs set out the requirements for “stress restoration” when
the replacement work is carried out. They apply principally to plain line.
However, in S&C, where for example a switch half-set is being replaced, the
stress shall be restored, and equalised as far as possible between the rails.
The minimum length of rail which may be inserted into CWR is 4.5m (or 3m in
cases of particular difficulty and subject to approval by the Principal
Maintenance Support Engineer (Track). In the event of a defect of a multiple
type, the whole 18m or 36m (60ft or 120ft) length of rail shall be replaced. The
stress restoration process shall not be applied to replacement rails exceeding
36m which shall be subject to full stressing as detailed in section 9.
For stress restoration in S&C the stressing plan shall be approved in advance
of the work by a holder of level (iii) stressing competency. The plan shall be
initialled to indicate approval of the proposals and the stress restoration
certificate reviewed and initialled to indicate that the correct procedure was
followed.
Any movement of the rail relative to the sleepers which occurred following the
break or when the rail was cut shall be measured and recorded and action
taken as in Table 5.
Note: Table 5 and paras 10.2 and 10.3 refer to other than crimp-ended steel
sleepers: in the case of crimp-ended sleepers the rail temperature values
quoted must be increased by 5C.
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
Page 32 of 74
Note – the actions for rails between 15C and 21C applies only to rails of
13716mm length or less. For longer rails use the action plan given for rail
temperatures below 15C
i. Mark on the existing rail both cutting points for the replacement
rail.
ii. Mark reference points on both the existing rail and
corresponding unfastened sleepers/housings (with any sticking
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
Page 33 of 74
welding between tensors, fit the tensors and pull the rails until
the reference marks on both the rails and the sleepers
correspond again.
v. Make the final cut for the welding gap and weld.
vi. Release and remove tensors. Replace pads, insulators and
fastenings. Fill all cribs with ballast and pack sleepers. Remove
weld debris from site.
vii. Fill out stressing certificate.
i. Measure the gap between the rail ends and take the appropriate
action (see para. 10.1).
ii. Mark on the existing rail both cutting points for the replacement
rail.
iii. Mark reference points on both the existing rail and
corresponding unfastened sleepers/housings (with any sticking
pads freed) clear of where the tensors will be located.
iv. Cut out the defective rail. Weld in the replacement rail at one
end.
v. Position the tensors and, after the first weld has cooled for the
period of time as specified in NR/L2/TRK/032 for welding
between tensors, pull the rails until the reference marks on the
rails have moved inward from the reference marks on the
sleepers by a combined amount equal to the original rail gap.
i. Mark on the existing rail both cutting points for the replacement
rail.
ii. Mark reference points on both the existing rail and
corresponding unfastened sleepers/housings (with any sticking
pads freed) clear of where the tensors will be located.
iii. Position the tensors with the extension bars spanning the portion
of rail to be removed and apply a pull force appropriate to the rail
temperature (see Appendix C).
iv. Flame cut the rail to be replaced.
v. Check the reference points and if necessary pull the rails until
the reference marks correspond with the reference marks on the
sleepers.
vi. Weld in the closure rail.
Then as vi and vii in para. 10.2.
Page 34 of 74
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
Notes:
The maximum length of rail that can be replaced using this method is
6m. This precludes replacement of a normal glued insulated rail joint
assembly but does permit the re-plating/re-bolting of a non-glued
joint where the rails are to remain.
This method may be used only when all rail cuts may be made using
oxy-fuel gas, since disc cutting of rail between tensors is prohibited.
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
11 Stressing of S&C within CWR
11.1 General
In stress-block layouts the closure rails (between the switch heel and the
crossing) shall be stressed to the extent practicable. This will depend upon the
practicability of installing tensors and upon the need to maintain adequate weld-
to-weld distances. (Note: although buckling in the closure area, where there
are four or more rails continuously fastened to bearers, is unlikely, the risk of
misalignment in the heel block area will be minimised if all rails in the S&C have
similar SFTs.)
Where cast common or obtuse crossings are being used as anchor points they
shall be welded or tight jointed to their adjacent closure rails and shall have all
pads and clips installed and be in good condition.
In layouts with creep monitors, thermal force is assumed to “ramp up” along the
closures from the heel towards the crossing, with the maximum tolerable force
occurring after approximately 40m. Closures longer than this should therefore
be stressed (see para. 11.7.3b).
All joints within the anchor length and the length to be pulled shall
be welded, or
be fitted with tight-joint fishplates and 29mm (1 1/8 in) dia. high-
tensile fishbolts, or
be insulated joints approved for use in CWR.
Intermediate closure rails between separate units of S&C shall be
stressed.
Page 35 of 74
S&C layouts may be used to form part of an anchor length provided that all
S&C units are of an approved design (see section 8). Movement of switch tips
and crossings shall be minimised by selecting appropriate pulling points.
Subsequent testing and adjustment of any switch detection shall be carried out.
The layout shall be to the design line and level and shall be packed and
correctly ballasted.
The positions of existing welds and insulated joints shall be checked to deliver
at least 4.5metres between welds/joints.
The distance between switches installed toe-to-toe may cause problems in the
fitting of tensors. For example, switches with short fronts of 1650 mm, and with
signalling equipment in the bed immediately in front of the switches towards the
stock rail end, provide a clearance for the tensors of just 2600mm. The site
shall be examined prior to stressing to affirm that appropriate tie bars are
supplied with the tensor equipment. The following arrangements of tensor
equipment are possible:
Short tie bar 380mm long gives overall length of tensor equipment of
1860mm and the tensors can be positioned with the weld at the
centre of the equipment;
Standard tie bar 1525mm long gives overall length of tensor
equipment of 3000mm and tensors can be positioned with the weld
at the centre of the equipment;
Page 36 of 74
11.5 General site procedure for stressing S&C with stress transfer
blocks
Where possible all lengths to be stressed should be done at the same time.
Where this is not possible the procedure below takes this into account.
Care shall be taken to preserve the correct crossing nose to toe dimensions.
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
Procedures for stressing common S&C units and layouts are given in paras
11.7 and 11.8 respectively.
Page 37 of 74
11.6 General site procedure for stressing S&C with creep monitors
The procedure in para. 11.5 applies, except that the stock rails shall be
stressed as if they were plain rails, with fastenings released (as shown in para.
11.7.2b). However, movement of the stock rails at the switch toes shall be
minimised.
The following instructions are additional to the general procedures for stressing
given above.
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
rails are directly joined by an insulated rail joint or tight joint
In all the examples the adjoining plain line CWR is assumed to be correctly
stressed. If it is not known to be correctly stressed then stressing of the plain
line should be carried out at the same time as the stressing of the S&C or,
failing that, before the onset of hot weather. The length of plain line stressed in
association with switch toes shall not exceed 180m.
Page 38 of 74
Anchor L2 L1 L3 Anchor
clip unclip unclip clip clip
Notes
(1) The ITT next to the switch toe shall be on the first plain sleeper, which shall be unclipped
(2) Switch toes must be maintained square, it may therefore be necessary to stress both half sets
Method:
i. Choose the position for the tensors, X1X2, approximately 18m (L1)
from the switch toes and mark the tell tale points for each anchor
length.
ii. Cut both rails at X1X2.
iii. Unclip both rails and place on rollers from the switch toes for a
distance of L1+L2.
iv. Mark both rails clear of the tensor positions and, when necessary,
provide reference points on unfastened sleepers/housings in the
plain line corresponding to the marks.
v. Calculate the extension required for L1+L2+L3 (see Appendix B),
and the pull force (see Appendix C).
vi. Cut again, allowing for the extension and the welding gap.
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
vii. Fit the tensors at X1X2 and apply tension to both rails until the
required extension or calculated pressure is achieved (see para.
11.5.vi).
viii. Check tell tale points to confirm whether the anchors have held and
check the switch toe dimensions.
ix. Complete the welds, remove all rollers and replace pads, insulators
and clips. Remove tensors, fill all cribs with ballast, pack sleepers /
bearers and remove welding debris.
x. Arrange for switch detection to be checked and, if necessary,
adjusted.
xi. Fill out stressing certificate.
Page 39 of 74
See para. 11.7.1a, but with L3 included within the anchor and excluded
from the calculation in part v of the method.
(through line shown, but method is the same for turnout line provided
that turnout radius exceeds minimum specified for CWR in
NR/L2/TRK/2102)
Diagram 11.7.2a - Stressing at crossing nose -switches with stress transfer bloc
(no adjustment switches removed)
X2
Anchor L1 L2 Anchor
clip unclip unclip clip
Notes
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
(1) Reference points required in L1 or L2 if the length excedes 90m
(2) ITT to be on the 3rd through bearer outside the crossing joint/weld, unclipped from all rails
(3) For anchor lengths see table 2
(4) Both rails to be stressed on each road on which CWR exists. Through road stressed first
Method:
i. Choose the position for the tensors, X1X2, approximately 18m (L1)
from the crossing joint/weld and mark tell tale points for each
anchor length.
ii. Cut both rails at X1X2.
iii. Unclip both rails and place on rollers from the third bearer from the
crossing joint/weld for a distance of L1+L2.
iv. Mark both rails clear of the tensors and, when necessary, provide
reference points on unfastened sleepers/housings corresponding to
the marks. Provide tell tale marks for each anchor length.
v. Calculate the extension required for L1+L2 (Appendix B), and the
pull force (Appendix C).
vi. Cut again, allowing for the extension and the welding gap.
vii. Fit the tensors at X1X2 and apply tension to both rails until the
required extension or calculated pressure is achieved (see para.
11.5.vi).
Page 40 of 74
viii. Check the tell tale marks to confirm whether the anchors have held.
ix. Complete the welds, remove all rollers and replace pads, insulators
and clips. Remove tensors, fill and compact all cribs with ballast,
pack sleepers and bearers and remove all welding debris.
x. Fill out stressing certificate.
Anchor L1 L2 Anchor
clip unclip unclip clip
Notes
(1) Reference points required in L1 or L2 if the length excedes 90m
(2) OTT nearest the switches to be on the switch heel bearer, bearer unclipped from all rails
(3) For anchor lengths see table 2
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
(4) If the crossing has been installed/replaced then both rails on both roads shall be stressed
Method:
i. Choose the position for the tensors, X1, and mark tell tale points for
each anchor length.
xi. Cut both rails at X1.
xii. Unclip both rails and place on rollers for a distance of L = L1 + L2.
xiii. Mark both rails clear of the tensors and, when necessary, provide
reference points on unfastened sleepers/housings corresponding to
the marks. Provide tell tale marks for each anchor length.
xiv. Calculate the extension required for L (Appendix B), and the pull
force (Appendix C).
xv. Cut again, allowing for the extension and the welding gap.
xvi. Fit the tensors at X1 and apply tension to both rails until the
required extension or calculated pressure is achieved (see para.
11.5.vi).
xvii. Check the tell tale marks to confirm whether that the anchors have
held.
xviii. Complete the welds, remove rollers, replace pads, insulators and
clips. Remove tensors, fill and compact all cribs with ballast, pack
sleepers and bearers and remove all welding debris.
Page 41 of 74
Anchor L1 L2 Anchor
clip unclip unclip clip
Notes
(1) The ITT at the back of the crossing should be the same as used for stressing at the crossing ve
(2) The ITT at the switch toes shall be on the first plain sleeper, sleeper unclipped from both rails
(3) For anchor lengths see table 2
(4) Through road shown, same method applies to turnout road
Stressing is mandatory between the last distance block from the switch
and the wing rail joint/weld of the crossing for EV switches and flatter.
However, stressing should be carried out also in shorter turnouts where
misalignment in the heel block area can result from excessive thermal
forces.
Page 42 of 74
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
Notes
(1) ITT on bearer next to wing rail joints/welds, bearer unclipped from all rails
(2) ITT on bearer next to last stress transfer block from toes, bearer unclipped from all rails
(3) For anchor lengths see table 2
(4) Through road shown, turnout road is the same method
The following method provides for all four rails to be stressed during the
same shift.
Method:
Page 43 of 74
xi. Remove tensors, fill and compact all cribs with ballast, pack
sleepers and bearers and remove all welding debris
xii. Arrange for switch detection to be checked and, if necessary,
adjusted.
xiii. Fill out stressing certificate.
OTT (see note 3) ITT (see note 2) X1 ITT (see note 1) OTT
Anchor L2 L1 Anchor
2 clip unclip unclip 1 clip
Notes
(1) ITT on bearer next to wing rail joints/welds, bearer unclipped from all rails
(2) ITT at an anchor length of 3 bearers per degree or 30m from OTT
(3) OTT on the first fastening at the switch heel
(3) For anchor lengths see table 2
(4) Through road shown, turnout road is the same method
After the stock rails have been stressed (paras 11.7.1b and 11.7.2b), the
switch rails shall be set to the correct position relative to the stock rails.
With a welding gap at a suitable position in each closure rail, and all
fastenings on the toe side of that gap released, the switch rails shall be
adjusted longitudinally so that the ball (assumed to be fitted to the switch
rail) of the anti-creep device is central within the claw at a rail
temperature of 27C, and is just contacting the “heel” side of the claw at
0C, and the “toe” side at 53C. Interpolation shall be made for
intermediate temperatures.
In layouts with creep monitors, thermal force “ramps up” along the
closures from the heel towards the crossing. The maximum tolerable
force occurs after approximately 40m, so closures longer than this should
be stressed (G switch turnouts and longer). If distance L1+L2 in the
diagram precludes the use of tensors, rollers, and suitable weld-to-weld
distances, warmers or natural stressing shall be used.
Page 44 of 74
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
Method:
Page 45 of 74
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
X2
Anchor L3 L1 L2 L4 Anchor
clip clip unclip unclip clip clip
Notes
(1) The ITTs next to the switch toes shall be on the first plain sleeper, which shall be unclipped
(2) Switch toes must be maintained square, it may therefore be necessary to stress both half sets
(3) Through road shown. Same method applies to turnout road
Method:
i. Choose the position for the tensors X1X2, ideally midway between
the switch toes.
ii. Cut both rails at X1X2.
iii. Unclip both rails and place on rollers between switch toes, L1.
iv. Mark both rails clear of the tensors and provide tell tale marks for
the anchor lengths including the switches.
v. For layouts with stress transfer blocks, calculate the extension
required for L1+L2+L3+L4 (see Appendix B), and the pull force (see
Appendix C). For layouts with creep monitors ignore L3 or L4 or
both as appropriate.
vi. Cut again, allowing for the extension and the welding gap.
vii. Fit the tensors at X1X2 and apply tension to both rails until the
required extension or calculated pressure is achieved (see para.
11.5.vi).
viii. Check the tell tale marks to confirm whether that the anchors have
held and check the switch toe dimensions.
ix. Complete the welds, remove all rollers and replace pads, clips and
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
insulators. Remove tensors, fill and compact all cribs with ballast,
pack sleepers and bearers and remove all welding debris.
x. Arrange for switch detection to be checked and, if necessary,
adjusted.
xi. Fill out stressing certificate.
Page 46 of 74
Diagram 11.7.5 Stressing between crossing vee and follow on switch toes
Lead 1 Lead 2
X2
OTT (see notes 3 - 5) ITT (see notes 3 - 5) X1 ITT (see note 7) OTT
Anchor L1 L2 L3 Anchor
clip unclip unclip clip clip
Notes
(1) Follow on applies where the distance between iTTs is less than 180m
(2) For anchor lengths see table 2
Lead 1
(3) OTT and ITT position shown for switches with stress transfer blocks
(4) For switches with stress transfer blocks see diagram 11.7.2a for OTT and ITT locations
(5) For switches with creep monitors see diagram 11.7.2b for OTT and ITT locations
Lead 2
(6) Lead 2 is shown for switches with stress transfer blocks, for creep monitors include L3 in ancho
(7) ITT located on first plain sleeper from switch toes, sleeper unclipped from both rails
If the distance precludes the use of tensors, stressing naturally will have to be used.
Method:
i. Choose the position for the tensors X1X2, ideally midway between
the switch toes and the crossing vee.
i. Cut both rails at X1X2.
ii. Unclip both rails and place on rollers between the switch toes and
the third bearer from the crossing joint/weld (L1).
iii. Mark both rails clear of the tensors and provide tell tale marks for
each anchor length.
iv. Calculate the extension required for L1+L2 +L3 (Appendix B), and
the pull force (Appendix C). For switches with creep monitors ignore
L3.
v. Cut again, allowing for the extension and the welding gap.
vi. Fit the tensors at X1X2 and apply tension to both rails until the
required extension or calculated pressure is achieved (see para.
11.5.vi).
vii. Check the tell tale marks to confirm whether that the anchors have
held and check the switch toe dimensions.
Page 47 of 74
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
viii. Complete the welds, remove all rollers and replace pads, clips and
insulators. Remove tensors, fill and compact all cribs with ballast,
pack sleepers and bearers and remove all welding debris.
ix. Arrange for switch detection to be checked and, if necessary,
adjusted.
x. Fill out stressing certificate.
Diagram 11.7.1 applies but with L2 equal to180m and reference points
provided within L2.
Method:
ix. Check the tell tale marks to confirm whether that the anchors have
held and check the switch toe dimensions.
x. Complete the welds, remove all rollers and replace pads, clips and
insulators. Remove tensors, fill and compact all cribs with ballast,
pack sleepers and bearers and remove all welding debris
xi. Arrange for switch detection to be checked and, if necessary,
adjusted.
xii. Fill out stressing certificate.
Page 48 of 74
Method:
The same method applies as for 11.7.6.a but with L3 included in the
anchor and excluded from the calculation in part vi of the method
Diagrams 11.7.2a and 11.7.2b apply depending on switch type but with L2
equal to180m and reference points provided within L2.
Method:
i. Remove adjustment switch and replace with plain line (Note: new
sleepers shall be of a type similar to those present on the adjacent
plain line).
ii. Choose the position for the tensors, X1X2, normally at one end of
the new closure rail.
iii. Unclip 180m from X1X2 into CWR, L2, and from X1X2 to the third
bearer from the crossing joint/weld, L1, and place rail on rollers.
iv. Weld up all joints except at X1X2.
v. Mark both rails clear of the tensors and provide reference points on
unfastened sleepers/housings corresponding to the marks. Also
provide tell tale marks for each anchor length.
vi. Calculate the extension required for L1+L2 (Appendix B), and the
pull force (Appendix C).
vii. Cut again, allowing for the extension and the welding gap.
viii. Fit the tensors at X1X2 and apply tension to both rails until the
required extension is achieved (see para. 11.5. vi).
ix. Check the tell tale marks to confirm whether the anchors have held.
x. Complete the welds, remove all rollers and replace pads, clips and
insulators. Remove tensors, fill and compact all cribs with ballast,
pack sleepers and bearers and remove all welding debris.
xi. Fill out stressing certificate.
Page 49 of 74
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
OTT ITT (see notes 3 - 5) X1 ITT (see notes 3 - 5) OTT
Anchor L1 L2 Anchor
clip unclip unclip clip
Notes
(1) Applies when L1 + L2 < 180m
(2) For anchor lengths see table 2
Lead 1 and Lead 2
(3) OTT and ITT position shown for switches with stress transfer blocks
(4) For switches with stress transfer blocks see diagram 11.7.2a for OTT and ITT locations
(5) For switches with creep monitors see diagram 11.7.2b for OTT and ITT locations
Method:
Page 50 of 74
11.7.9 Stressing between 'toe to toe' switches where stock rails are
directly joined by an insulated rail joint or tight joint
Method:
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
common joint is insulated it will also be necessary to change the
adjacent half-set if there is more than 2mm difference in headwear, since
there is currently no approved design of lift insulated joint.
The front of the switches shall be stressed first (see para. 11.7.1),
followed by the heel of the crossing on the through leg and then, if
appropriate, the heel of the crossing on the turnout leg (see para.
11.7.2). Finally, the closure rails shall be stressed (see para. 11.7.3).
Page 51 of 74
1 2
3 4
4 3
1 2
1 2
6
5
Crossover (for one set of tensors) Double junction (for one set of tensors)
12.1 General
The stability of CWR will be reduced if the SFT is reduced (para. 12.2) or the
lateral resistance is reduced (paras 12.3).
Page 52 of 74
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
Where the design line and level is not established by fixed references, or
an established design line and level is to be altered, re-stressing is
required as follows (slues, lifts etc are from the position at previous
stressing):
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
a) Alteration to line: sluing inward on horizontal curves
Curve radius 750m or less: re-stress when maximum slue is 30mm
or more.
Curve radius over 750m: re-stress when maximum slue in mm
exceeds 0.04 times radius in m.
b) Alteration to line: sluing outward on horizontal curves
Re-stress when maximum slue in mm exceeds 0.08 times curve
radius in m.
c) Alteration to level: lifting and/or increasing cant through
concave vertical curves or lowering and/or reducing cant over
convex vertical curves
Vertical curve radius 1875m or less: re-stress when maximum
lift/lower/re-cant is 75mm or more.
Vertical curve radius over 1875m: re-stress when maximum
lift/lower/re-cant in mm exceeds 0.04 times vertical curve radius in
m.
d) Alteration to level: lifting and/or increasing cant over convex
vertical curves, or lowering and/or reducing cant through
concave vertical curves
Page 53 of 74
Whenever CWR has been disturbed such that the SFT has been altered,
and/or any lifting/lining/recanting is outside the above limits, either
12.3.1 General
The lateral resistance of the track will be reduced by any work which
moves or removes sleepers, or removes or loosens the ballast, including
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
tamping/lining of undisturbed track. Now NR/L2/TRK/001/mod14
Work which may reduce the stability of track which is open to traffic
Page 54 of 74
Work which may reduce the stability of track shall not carried out when
the rail temperature is below –7C, except that in the following locations a
limit of 0C shall apply:
within 90m of adjustment switches;
on stressed curves having 90mm cant or more;
on stressed curves of radius below 600m;
on curves where cant deficiency exceeds 150mm
on curves where cant exceeds 150mm.
Now NR/L2/TRK/001/mod15
12.3.3 Temperature limits – lines under possession
Tamping/lining of undisturbed track (i.e. not associated with renewals
work or with any other work which has disturbed the track) shall not be
carried out when the rail temperature is above 32C. Otherwise, there is
no restriction but on re-opening of the line to traffic the CRT values from
section 14 and the precautions in paras 15.1 and 15.2 shall apply.
Now NR/L2/TRK/001/mod14
12.3.4 Opening out
If sleepers are to be packed manually, or require to be squared, not more
than six alternate half beds or two consecutive full beds may be opened
out at one time. Care shall be taken to retain the top and line, and to
restore the ballast profile before opening out adjacent sleepers.
Now NR/L2/TRK/001/mod03
12.3.5 Changing defective sleepers
Defective sleepers shall be changed singly and on completion the new
and adjoining sleepers shall be packed, the ballast between the sleepers
and on the ballast shoulders shall be replaced to the correct profile, and
the ballast consolidated or other appropriate precautions taken.
Now NR/L2/TRK/001/mod03
12.3.6 Slurried ballast
Where there are wet and slurried ballast conditions the foul ballast shall
be removed from around the sleepers and a graded slope created for
drainage purposes. Fresh ballast shall then be placed, packed and
compacted. Not more than six alternate half beds or two consecutive full
beds should be opened out at one time. Now NR/L2/TRK/001/mod03
Page 55 of 74
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
Use of the risk scoring system in Appendix F does not remove the
requirement to create a stressing record. Even if no stressing is
required, a record must be created: this may be by the use of an
approved direct SFT measurement method.
Page 56 of 74
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
Fastenings shall be examined periodically for rail pad movement and for
distortion or excessive wear on insulators or other components. If loss of
toe load (which can cause track instability if over several consecutive
sleepers) is suspected, the defective components shall be changed.
Badly-worn insulators and pads shall also be changed before excessive
wear results in track circuit failure. Worn or damaged rail pads shall be
replaced and displaced pads repositioned.
Individual pads may be replaced during traffic provided that not more
than three consecutive pairs of clips on one rail are released at once.
Now NR/L2/TRK/001/mod14
Page 57 of 74
A change in rail temperature of 15C will alter the length of the switch rail
and its clearance to the knuckle by 1mm for normal grade steels and
1.5mm for manganese steels. Where switch diamonds have a history of
detection failure and the clearance at the knuckle varies substantially
with changes in rail temperature, precautions (e.g. installation of
adjustment switches or painting the rails white) shall be taken to reduce
the thermal forces and limit switch rail movement relative to the knuckle.
Now NR/L2/TRK/001/mod14
14 Critical rail temperature
This section shall be read as referring to the switch areas of S&C, as well as to plain
line.
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
14.2.1 Methodology
Page 58 of 74
The original SFT value of CWR shall not be assumed as exceeding 21C
unless valid stressing records (para 9.16) are available to clearly indicate
otherwise.
Sites of unknown stress (see para 9.18), that have been entered into an
agreed compliant program for re-stressing or direct measurement of
stress free temperature (see page 2), may be assumed to have an
original stress free temperature of 21C. Those sites not so programmed
shall be assumed to have an SFT not exceeding 11C.
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
For stress required sites (see para 9.19) the selection of SFT value shall
take account of factors such as the time of year when the rail was
disturbed, and any buckling history. The SFT for stress required sites
shall not be assumed as exceeding 11C unless some record exists
clearly indicating otherwise.
Page 59 of 74
Page 60 of 74
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
Now NR/L2/TRK/001/mod14
14.2.5 Other considerations
Page 61 of 74
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
15.1 Watchmen
When the rail temperature is expected to exceed the CRT(W) (section 14),
watchmen shall be placed to monitor the length of track concerned. They shall
remain on site whether or not speed restrictions are imposed, to take rail
temperatures, monitor any known “trigger” points and observe for early
indications of movement. They shall continue to do so until the rail temperature
falls to, and can be expected to remain for that day, below the CRT(W).
Watchmen shall block the line or impose a speed restriction if a buckle occurs,
and shall be equipped and competent to do so.
Now NR/L2/TRK/001/mod14
Page 62 of 74
--`,,``,,`,,,``,,,,,````,,`,,,`,
Even if the above restrictions have not already been applied, differential speed
restrictions (as defined in the Rule Book Section U) shall be imposed as
follows:
Page 63 of 74
17 Track buckling
If a track buckle occurs the first requirement is to safeguard traffic and advise
the controlling signalbox or signalling centre. Before any traffic is allowed to
pass over the buckled length the track may first need to be slued, preferably
outwards on a curve or to an easy curvature on the straight, and a speed
restriction imposed. Structural clearances and the track position relative to any
OLE equipment shall be checked. An adjacent track may need to be
temporarily slued to provide satisfactory clearances and a speed restriction
imposed. Adjustment of the track to treat the cause of the buckle and to restore
the original alignment shall not be made until the rail temperature is less than
32C.
Now NR/L2/TRK/001/mod14
In addition to reporting via the Track Buckle Report Form, buckles shall be
reported under the national hazard reporting system, to the timescales required
for that system.
Now NR/L2/TRK/001/mod14
Page 64 of 74
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
18 Reference documentation
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
Page 65 of 74
Level i (Basic)
The person shall know and understand:
the reasons for stressing CWR
relevant terminology (including the definitions in this specification)
how to restore stress when removing defective or broken rails
how to install insulated rail joints
how to calculate pull force in relation to temperature difference
how to complete the stress restoration certificate
Level ii (Intermediate)
In addition to the requirements for Level i the person shall know and understand how to
stress existing and new plain line CWR using tensors, including
how to undertake a site survey, and collect relevant data
marking and monitoring of tell-tales and reference points
the relationships between rail extension, pull force, pressure reading and rail temperature
how to calculate rail extension, pull force, pressure reading and original SFT
pulling parameters
application to straight and curved track, tunnels and longitudinal timbers
Page 66 of 74
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
The extension (in mm) for various pulling lengths is as follows (for an SFT of 27C):
At lower temperatures the extensions for -8C shall be used (to avoid overstressing the
tensors). A lower SFT will be achieved. See also Appendix C.
Page 67 of 74
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
Examples
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
Page 68 of 74
This Appendix assumes the use of other than crimp-ended steel sleepers. In the case of
crimp-ended sleepers the SFT shall be 32C and the calculations shall be adjusted
accordingly.
Equation 1:
Tensor pull force (tonnes) = rail weight per yard (lbs) x (27 – T) x 0.01543
where T = rail temperature
Equation 2:
Pressure reading (lb/sq.in) = 110 x Tensor pull force (tonnes)
(for 70T Permaquip Tensors)
Examples
For numerical example No. 1 (see Appendix B); assume 109 lb FB rail
Tensor pull force = 109 x (27 - 11) x 0.01543 = 26.9 tonnes
Pressure reading = 110 x 26.9 = 2960 lb/sq.in.
For numerical example No. 2 (see Appendix B); assume 113 lb FB rail
Tensor pull force = 113 x (27 - 13) x 0.01543 = 24.4 tonnes
Pressure reading = 110 x 24.4 = 2685 lb/sq.in.
In both the above examples there will be adequate capacity in 70T Permaquip tensors.
Difference between T and 27C for a pull force of 60 tonnes = 35C, so tension rail to a SFT of (35 - 9)C
= 26C, which is within the allowed range of 21 to 27C (Note: Unless rail temperature is below –14C it
will be possible to tension to a SFT of at least 21C without exceeding the limit of pull force of 60
tonnes).
Values of pull force and pressure gauge reading for the more common rail sections, including
CEN60E1, are shown below (multiply the 113A value by 0.84 for 95lb bullhead rail, and by 0.87 for
98lb FB rail):
Page 69 of 74
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
For Stressing / Re-stressing Form see Track Engineering Form No. TEF/3010
For Stress Restoration Form see Track Engineering Form No. TEF/3011
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
Page 70 of 74
For Disturbance of CWR Form see Track Engineering Form No. TEF/3012
For Verse Test Results Form see Track Engineering Form No. TEF/3013
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
Page 71 of 74
This appendix describes how to conduct an assessment of track having no record of SFT,
i.e. where there is neither a stressing record nor a direct measurement. It takes account of
the three contributions to total risk, i.e. rail stress (A), lateral resistance (B) and
consequences of buckle (C).
A stressing priority assessment shall be made for each length of track without stressing
records. The maximum continuous length of track in one assessment shall be one mile, this
being shortened if conditions along the length vary significantly.
A1, Years since installation SFT tends to fall with time, particularly where there are
other contributory factors. One point is awarded for each year (maximum ten) since
installation.
A2, Curvature SFT is lost through pulling-in of curves in winter, particularly where smooth
lining is carried out without reference to datum pegs. A zero score may be awarded if the
track position is known to be as at installation.
A4, Rail creep Rail creep is a significant contributor to changes in SFT. Points shall be
awarded additively for
poor fastenings or pads (where lack of toe load is suspected);
situations at the bottom of an incline where traction or braking may cause bunching;
locations where repeated braking or acceleration occurs (stations, signals, junctions etc.).
A5, Maintenance history Points shall be awarded if rail defects have been repaired
without restoration of stress.
A6, Track subsidence This can significantly alter the SFT and such sites are normally
specially monitored. Unstable formation where large settlements occur, generally or locally,
shall also be taken into consideration.
The rail stress scores are summed to obtain the rail stress total A.
Now TEF3230
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
Page 72 of 74
B4, Track alignment This shall be based on the worst eighth mile of track geometry
recording data, excluding S&C.
B5, Sleeper type Points shall be awarded where timber sleepers exist in significant
consecutive numbers, excluding S&C.
B6, Exposure Assessment shall be made of the degree of exposure to the sun. Shaded
or windy sites shall score low. Sheltered sites in cuttings exposed to afternoon sun, and
other such hot spots, will score high.
The lateral resistance scores are summed to obtain the lateral resistance total B.
C1, Linespeed Linespeed will determine the derailment probability if a buckle occurs, and
the potential for injury. This is disproportionately higher at higher linespeeds.
C2, Traffic The derailment risk may be considered to be proportional to the total traffic.
C4, Number of tracks The consequences of a derailment will be related to the number of
adjacent tracks, which will determine the collision risk.
Track buckling probability is governed by the sum of the partial totals A and B.
Consequence of buckling is given by the consequence total C. Buckling risk is therefore
expressed as (A + B) x C. The resulting score can be used to prioritise sites for stressing.
A high score will indicate a high risk.
Assessment of the lateral resistance total B may be used also to indicate where other action
may be needed, e.g. the placing of extra ballast.
Now TEF3230
Page 73 of 74
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
If sections A3, A4 and A6 are not applicable then score the respective section zero.
Action to be taken
Completion of this risk assessment is for the purposes of prioritising stress unknown sites for
the work necessary to obtain valid stressing records. Completion of this risk assessment
does not constitute a stressing record. Regardless of the score a stressing record must be
created.
Now TEF3230
Page 74 of 74
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
The hot weather management aspects and maintenance requirements for CWR have been included in the revised NR/L2/TRK/001.
This issue of TRK/3011 identifies, by use of strike-through, which sections have been transferred to TRK/001.
Where text has been struck through, there will be a note included to indicate in which module of TRK/001 the detail is now included.
Note: The ultimate aim is for TRK/3011 to become a ‘How to Stress’ document. After this update there will still be some construction
details remaining which will be transferred to TRK/2102 at some point in the future.
Affected documents:
Reference Impact
NR/L2/TRK/3011 ISSUE 6 Superseded
Briefing requirements: Where Technical briefing (T) is required, the specific Post title is indicated. These posts have specific responsibilities
within this standard and receive briefing as part of the Implementation Programme. For Awareness briefing (A) the Post title is not mandatory.
Please see http://ccms2.hiav.networkrail.co.uk/webtop/drl/objectId/09013b5b804504da for guidance.
*NOTE: Contractors are responsible for arranging and undertaking their own Technical and Awareness Briefings in accordance with their own processes and procedure
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
The use of the equipment enables significant savings to be made, allowing replacement rails to be installed
and re-stressed more quickly using two sets of THR542 Stressing kits in tandem and two sets of proprietary
rail alignment devices.
2. Scope
This Letter of Instruction allows for the replacement of worn, defective and broken rails in (including welds
and IBJs) plain line and S&C using two sets of THR542 Stressing kits and two sets of proprietary approved
rail alignment devices on an individual rail. It excludes the replacement of rail lengths less than 9m or more
than 36m long.
This letter of instruction details the specified method that must be followed to allow stress restoration to be
carried out when two welds are undertaken at the same time. It will remain in place until reissued or included
in future standard changes to NR/L2/TRK/3011
3. Changes
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
NR/L2/TRK/3011 Position the tensors and, after the first weld has Insert and apply the
Clause 10.3 v) cooled for the period of time as specified in following procedure
NR/L2/TRK/032 for welding between tensors, pull the
rails until the reference marks on the rails have
moved inward from the reference marks on the
sleepers by a combined amount equal to the original
rail gap
4. Procedure
4.1. Preparation
Tools, equipment and plant items required but not limited to:
- Pencil/scribe
- Rail wax crayon/mark
- Rule (300mm with metric scale)
- Calculator
- Note book
- NR/L2/TRK/3011 Pull force and Pressure Reading table
- Flame cutting equipment
- Approved rail thermometers
- Fastening extractors, pad scrapers, hammers, bars, spanners
- Under rollers, side rollers
- Rail Jacks
- Fire extinguisher
- Welding Equipment
- 2no proprietary rail alignment devices
- Spacer (e.g. welder’s distance gauge)
- Rail drill
- Disc saw
- Grinder
- Generator
- 2no sets of Geismar THR542 stressing equipment
- Trolley
- Material as required
6. Procedure for the replacement of a defective insulated joint or rail, when the rail
temperature is below 21oC.
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
6.1. This process is for the stress restoration, of rail lengths between 9m and 36m,
when using two sets of THR542 Stressing kits and two sets of proprietary rail
alignment devices on an individual rail.
Note: An approved rail alignment device is available from Weld-A-Rail.
6.2. Mark on the existing rail both cutting points for the replacement rail.
6.3. Mark reference points (tell tales) on the outermost unfastened sleepers and rail
(after any sticking pads have been freed), which will be a minimum of 5 sleepers
beyond each weld position and clear of where the THR542 tensors will be located
(see Diagram 1).
6.4. The first cut into CWR shall be by flame cutting and trimmed by discutting. Check
any movement of the rail and take the appropriate action (see NR/L2/TRK/3011
paragraph 10.1). Make the second cut using a disc saw.
6.5. Measure & cut the replacement rail to length, minus the width of one welding gap,
and place into position.
6.6. One set of THR542 tensors (Tensor A) can then be fitted to the disc cut rail ends.
Place a suitable spacer (e.g. a welder’s distance gauge appropriate to the welding
process being used) between the rail ends at Tensor A and apply 5 tonnes of
force. This will hold the spacer in place.
Note: The rail ends that will form the gap at Tensor A MUST both have been prepared
using a disc saw.
6.7. Cut the other end of the rail allowing for the welding gap and tell tale movement.
Tensor B can now be fitted to this rail end.
6.8. Apply a pulling force of 5 tonnes to Tensor B whilst monitoring the welding gap
and the tell tales for movement.
6.9. If the required gap has not been achieved and there is more than 2mm more to
pull, a further force of 5 tonnes should be applied to Tensor A and the process is
repeated until correct welding gap is achieved.
6.10.At no point during the pull (unless there is 2mm or less to pull) should the gauge
on Tensor B read higher than on Tensor A.
6.11.It is essential that when both gaps have been achieved and the tell tales aligned,
that the gauge on Tensor B reads within 3 tonnes of Tensor A to allow for easy
removal of the spacer. If used correctly the gauge on Tensor A should read the
same or slightly above the gauge on Tensor B.
6.12.Record the pull force (Tonnes) at Tensor B on the TEF 3011 (note this can be
read directly from the THR542 tensor). After locking both THR542 Tensors the
stress is held mechanically and therefore, for the welders, there is no need to
record the stress after the welds are complete.
6.13.Clip up rail fastenings as required from the middle portion of the replacement rail,
leaving sufficient sleepers unfastened for the rail alignment devices to be used).
6.14.Align each rail joint using rail alignment devices and weld in accordance with the
requirements of NR/L2/TRK/0032. It is permissible for both welds to be aligned and
completed concurrently (if the required welding resource is available).
6.15.Tensors A & B and associated rail alignment devices shall be removed after the
welds have cooled for the period of time specified in the relevant process suppliers
manual. Note: each tensor can be removed independently of the remaining tensor.
6.16.Replace all pads, insulators and fastenings. Fill all cribs with ballast and pack
sleepers.
6.17.If stressing work is successful, complete Record of Stress Restoration form. If
stressing work is unsuccessful, complete disturbance of CWR form.
This process is for the stress restoration, of rail lengths between 9m and 36m, when
using two sets of THR542 Stressing kits and two sets of proprietary rail alignment
devices on an individual rail.
Note: An approved rail alignment device is available from Weld-A-Rail.
7.1. Measure the gap between the rail ends and take appropriate action (Ref.
NR/L2/TRK/3011). Cut out the defective rail (using a disc saw for the rail ends that
will form the joint at Tensor A).
7.2. Measure & cut the replacement rail to length, minus the width of one welding gap,
and place into position.
7.3. One set of THR542 tensors (Tensor A) can then be fitted to the disc cut rail ends.
Place a suitable spacer, (e.g. a welder’s distance gauge appropriate to the welding
process being used), between the rail ends at Tensor A. To this joint apply 5
tonnes of force. This will hold the spacer in place.
Note: The rail ends that will form the gap at Tensor A MUST both be cut using a disc
saw.
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
7.1. Cut the other end of the rail allowing for the tell tale movement. Tensor B can now
be fitted to this rail end.
7.2. Apply a pulling force of 5 tonnes to Tensor B whilst monitoring the welding gap
and tell tales for movement.
7.3. If the reference points on the rail have moved inward from the reference marks on
the sleeper by a combined amount equal to the original rail gap and there is more
than 2mm to pull, a further force of 5 tonnes should be applied to Tensor A and the
process is repeated until the reference points indicate that the required amount has
been achieved.
7.4. At no point during the pull (unless there is 2mm or less to pull) should the gauge
on Tensor B read higher than on Tensor A.
Tensor A Tensor B
--`,,``,,`,,,``,,,,,````,,`,,,`,-`-`,,`,,`,`,,`---
Not for Resale, 03/09/2019 02:59:12 MST
Licensee=Setec Ltd/5990765001, User=Parry, Richard
5 4 3 2 1 1 2 3 4 5
Spacer inserted in
this gap
Reference Reference
Point A Point B
Diagram 1 - Position of Reference Points
when using a Rail Alignment Device