Bill of quantities

owner Hari Govinda Maharjan (Kamalesh) Date: 2076‐09‐

S.No. Description of work unit Quantity Rate(Rs) Amount (Rs)


1 Site Clearance/tahara LS 1 5000 5000.00
2 Earthwork 0.00
excavation cuft. 3821 15 57315.00
backfilling cuft. 2865.75 5 14328.75
backfilling in plinth cuft. 2448.168 8 19585.35
3 Sand Filling/ polythene sheet sqft. 699.4767 5 3497.38
4 Brickwork 0.00
flat brick soling sqft. 1557.787 8 12462.29
9" wall (substructure) sqft. 1648.175 45 74167.88
9" wall (ground floor) sqft. 899.76 45 40489.20
9" wall (first floor) sqft. 1017.04 45 45766.80
4" wall (ground floor) sqft. 453.17 45 20392.65
4" wall (first floor) sqft. 533.165 45 23992.43
0.00
5 Concrete work 0.00
PCC sqft. 1557.787 25 38944.67
RCC 0.00
Footing cuft. 582 75 43650.00
BTB sqft. 581.7625 90 52358.63
Footing column sqft. 360 75 27000.00
UTB sqft. 581.7625 90 52358.63
Column (Ground floor) sqft. 396 75 29700.00
Beam (Ground floor) sqft. 477 90 42930.00
Slab (Ground floor) sqft. 1100.62 90 99055.80
stair (ground floor) sqft. 151.5 90 13635.00
Column (first floor) sqft. 396 75 29700.00
Beam (first floor) sqft. 756 90 68040.00
Slab (first floor) sqft. 1030.05 90 92704.50
stair (first floor) sqft. 151.5 90 13635.00
septic tank cover sqft. 80.00 90 7200.00
total 927909.94

above bill is excluding plaster work
‐20