The study is based on questionnaire survey wherein the 5. Role of Entity: It was seen from the study that for
questionnaire prepared is used to collect data from traditional project the execution work was carried out by
various developers, contractors, project managers etc. more than one entity and that for fast-track project the
regarding the important aspects necessary for comparing entire execution was carried out by single entity.
design-build and design-bid-build projects relating to the
construction of residential projects. The questionnaire 6. Scheduled Compression: It was observed that
was prepared with the help of expert opinions and was compression for traditional project is only possible unless
survey was followed on two construction sites one all activities of construction are treated as critical and
Traditional site and one being fast-track project and fast-track project Compression can be done with the help
observations were noted. While comparing Design-build of advanced technologies.
and Design-bid-build project following points were given
utmost importance which are: 7. Mobilization: It was studied from both projects that
mobilization amount for traditional project is much less as
Time
compared to fast-track project.
Cost
Quality 8. Productivity and Maintenance: It was observed that
Type of Contract fast-track project yield higher productivity and lesser
Role of Entity maintenance cost as compared to traditional project.
Schedule Compression
Mobilization 9. Alterations: If there is some changes in the design after
Productivity and Maintenance starting the construction work those alterations cannot be
_______________________________________________________________________________________________
ISSN (Online): 2347 - 2812, Volume-4, Issue -4, 2016
79
International Journal of Recent Advances in Engineering & Technology (IJRAET)
_______________________________________________________________________________________________
easily dealt with in fast-track projects. In this study it was Terrace slab
observed that the work in fast-track project was delayed 3 Lift Machine Room 20 58
for 30 days because of certain changes in design. 4 O.H Tank 25 58
5 Finishing Works 350 301
10. Risk Associated: From the study undertaken it was including waterproofing
observed that fast –track project has inherent litigation 6 Compound Development 30 2
risk and for traditional project is due to cost overruns.
Table 2: Time and Cost for Fast-track Project
11. Unique Problems: From the study it was observed RESULTS
that fast-track project possess more unique problems due For traditional Project
to multiple contract conditions as compared to traditional X Values
project. PARAMETER VALUES
∑ 679
12. Technical Advisors: Since concept of fast-track is Mean 113.167
very new in Indian market hence the firms opting for ∑(X - Mx)2 98022.833
fast-track approach need to rope in technical advisors for Y Values
the proper implementation of work.
PARAMETER VALUES
∑ 1160
13. Safety: It was observed from study that no common
Mean 193
safety culture is practiced by contractors in case of
∑(Y - My)2 232085.333
traditional projects whereas fast-track projects are more
concerned to safety policies followed on their site. Combined X and Y
N=6
∑ (X-Mx) (Y-My) = 75782.657
14. Lack of Competition: From the study it was observed
that fast-track projects have very less bidders for work as
Hence by using Karl Pearson’s Coefficient of correlation
the fast-track approach is not used extensively in the
Indian market.
REFERENCES
CONSTRUCTION” 24th International [10] Prasanta Kumar Dey " Managing projects in fast
symposium on Automation and Robotics in track- A case of public sector organization in
Construction, 2007, Construction Automation India" The International Journal of Public Sector
group, I.I.T Madras. Management, Vol. 13 No. 7, 2000, pp. 588-609.
[9] P. FAZIO, MOSELHI, P. THEBERGE " [11] Vikas Pawar, P.M. Attarde, Abhishek C Ayachit,
Fast-tracking of construction projects: a case Swapnil Kulkarni " RISK IN FAST TRACK
study" Can. J. Civ. Eng. IS, 493-499 (1988) CONSTRUCTION" International Journal of
Advanced Engineering Research and Studies
E-ISSN2249–8974.
_______________________________________________________________________________________________
ISSN (Online): 2347 - 2812, Volume-4, Issue -4, 2016
82