Professional Documents
Culture Documents
net/publication/271523329
CITATIONS READS
17 376
2 authors:
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Kyuman Cho on 30 January 2015.
Abstract: The fast-track method is one of the most recognized methodologies for reducing construction project schedules. However, due to
the lack of definitive research to date pertaining to the effects of fast-track application in terms of time and cost, it has been difficult for project
Downloaded from ascelibrary.org by University Of Seoul on 01/13/13. Copyright ASCE. For personal use only; all rights reserved.
owners to determine its correct application. This paper presents the time and cost optimized decision support (TACTICS) model, and it was
developed based on the fast-track methodology and genetic algorithms (GAs). TACTICS was applied to two case studies, and the results
indicated that the fast-track method could be expected to deliver more efficient projects compared with using the traditional method. In
particular, (1) the average reduction in project duration by applying the fast-track method was 40.48% (Case I) and 18.59% (Case II) com-
pared with using the traditional method, and (2) the average project costs were reduced by as much as 0.39% (Case I) and 4.48% (Case II).
Consequently, TACTICS could be expected to help in making a decision regarding the fast-track application and further contribute to the
project scheduling expertise in the construction engineering and management body of knowledge. DOI: 10.1061/(ASCE)CO.1943-7862
.0000570. © 2013 American Society of Civil Engineers.
CE Database subject headings: Fast track construction; Decision support systems; Optimization; Algorithms.
Author keywords: Fast-track construction; Decision support system; Optimization algorithms.
Introduction and cost and (2) the function for optimizing the two results
(i.e., project duration and cost).
The construction industry is constantly looking for ways to reduce As shown in Fig. 1, TACTICS was developed in three phases.
the time schedules for projects. Various methods have been devel- In the first phase, a detailed literature review for research pertaining
oped over the years and the fast-track methodology is one of the to the fast-track methodology was conducted. In the second phase,
most common. When the fast-track method is applied, the entire the three modules of TACTICS were developed: (1) scheduling,
construction duration, in theory, could be reduced by overlapping (2) cost estimating, and (3) optimization. The scheduling and cost-
the design and construction activities (Fazio et al. 1988; Clough estimating module were developed based on the concept and
and Sears 1991; Williams 1995; Pena-Mora and Li 2001; Cho methodology of the fast-track construction method. Then, the op-
et al. 2010b). The fast-track method could result in an increase timization module, which aims to analyze the trade-off relationship
in construction cost due to the reduced duration, which can cause between project duration and cost (i.e., the results from the sched-
project owners to hesitate in applying it to their construction proj- uling and cost-estimating module), was developed using the genetic
ects (Jergeas 2004; Cho et al. 2010b). However, the fast-track algorithms (GAs) technique. Finally, the TACTICS was applied to
method could have an advantage over the traditional sequential two case studies for identifying its effectiveness measured by the
construction method in terms of life cycle costs due to earlier oc- optimized project duration and cost.
cupancy and a reduction in overhead costs (Russell and Ranasinghe
1991; Williams 1995; Lee et al. 2005).
Therefore, it is important to analyze the trade-off between the State of the Art
time and cost for fast-track projects, and a reliable decision-making
tool for determining the suitable application of the fast-track Much research has been done that addresses the successful appli-
method on a particular project would be helpful. This paper cation of the fast-track method. Based on case study of fast-track
presents the time and cost optimized decision support (TACTICS) construction projects, Fazio et al. (1988) analyzed the main prob-
model for fast-track projects, which is able to suggest the optimized lems and barriers for applying the fast-track method and the effects
project cost and time for potential fast-track construction projects of mistakes in the early design phase on the performance of fast-
while considering (1) the functions for predicting project duration track projects. Williams (1995) not only analyzed the differences
between the traditional method (i.e., the sequential construction
method) and the fast-track method in terms of planning, schedul-
1
Assistant Professor, Department of Architectural Engineering, Chosun ing, expenses, responsibility, procedures, and the design and
Univ., Gwangju, Korea (corresponding author). E-mail: cho129@chosun construction process, but also suggested the pros and cons of
.ac.kr the fast-track method based on the results of this analysis. Eldin
2
Professor and Head, Division of Construction Engineering and (1997) suggested lessons learned through the analysis of key suc-
Management, Purdue Univ., Lafayette, IN. E-mail: hastak@purdue.edu
cess factors that were delivered based on a case study with real
Note. This manuscript was submitted on August 8, 2011; approved on
April 5, 2012; published online on April 10, 2012. Discussion period open cases delivered by concurrent engineering. Various ways to im-
until June 1, 2013; separate discussions must be submitted for individual prove construction productivity in road pavement projects that
papers. This paper is part of the Journal of Construction Engineering and implemented the fast-track method were suggested by Lee et al.
Management, Vol. 139, No. 1, January 1, 2013. © ASCE, ISSN 0733- (2005). They conducted a case study on road pavement projects
9364/2013/1-90-101/$25.00. in terms of the design and construction operations in fast-track
projects. Cho et al. (2010b) analyzed the key success vehicles for fast-track projects (Cho et al. 2012). Therefore, the construction
applying the fast-track method to public design-build projects work packages of a fast-track project could be divided into more
and suggested a partnering process model for implementing the specific work packages by considering the space zoning concepts.
Downloaded from ascelibrary.org by University Of Seoul on 01/13/13. Copyright ASCE. For personal use only; all rights reserved.
fast-track method, which was found to be more effective. These In this context, if fast-track project A is determined to be divided
research efforts focused on developing the effective factors for into not only k design work packages (DWPs) and n construction
successful fast-track projects through the use of case studies and work packages (CWPs) but also m working spaces, DWP (k) and
literature reviews. CWP (n × m) are defined by Eq. (1). Fig. 2 illustrates an example
Meanwhile, there have been a number of studies regarding im- of a fast-track project divided into four DWPs and CWPs, respec-
plementation of the fast-track method. Russell and Ranasinghe tively, and three working spaces.
(1991) provided a conceptual decision framework for applying the 0 1
fast-track method based on a net present value analysis of expend- DWP1
B C
itures for fast-track projects compared with one for the traditional B . C
DWPk ¼ B .. C;
method. Pena-Mora and Li (2001) developed a planning and con- @ A
trol methodology for fast-track projects using the axiomatic design DWPk
method, graphical evaluation and review technique (GERT), and 0 1
the system dynamics technique. This research suggested not only CWP11 · · · CWP1m
B C
ways to separate work packages appropriately, but also a planning B .. .. .. C
CWPnm ¼ B . . . C ð1Þ
and control methodology based on simulation results from various @ A
scenarios. Bogus et al. (2005) suggested a useful methodology CWPn1 · · · CWPnm
for dividing design work for a fast-track project into a number
of design packages, which adopted a concept of concurrent engi- where DWPk = design work package k; and CWPnm = construction
neering methodology in order to reduce design time. In this re- work package n on work space m.
search, they determined a number of design packages based on the
sensitivity of the dependency of the design information in each
package. Maheswari et al. (2006) suggested a methodology, which Scheduling Module
was based on the dependency structure matrix (DSM), for deter-
The scheduling module was developed to determine the project
mining the sequence of activity on concurrent engineering projects.
duration of fast-track projects. This module requires three steps:
According to this research, the sequence of activities that are in-
(1) determining durations of each work package (i.e., DWPk
cluded for concurrent engineering projects could be determined
and CWPnm ), (2) positioning each work package, and (3) calculat-
on the basis of the dependency of the information available for each
ing project duration.
activity.
As shown, the existing research has mainly focused on how to
implement the fast-track method to a construction project, rather Step 1: Determine Durations of Each Work Package
than the decision-making process to choose to use it on a project. It is necessary to consider the uncertainty of construction projects
Therefore, there is a need for a decision-making model capable of when the duration of each work package is determined. Generally,
predicting the effects of applying the fast-track method in terms of there are three methods for considering the uncertainty: (1) interval
the change in project duration and costs. analysis, (2) probabilistic analysis, and (3) fuzzy set analysis
(Zimmermann 1987). Among them, probabilistic analysis, which
could predict the mean and standard deviation using statistical mea-
Development of TACTICS sures of input variables, has become widely used in the existing
research in terms of construction scheduling. There are, in general,
The decision making for fast-track projects could be achieved by two techniques to address uncertainty in construction scheduling on
first dividing the design and construction work of a project into the basis of the probabilistic analysis, namely, program evaluation
appropriate work packages. As mentioned previously, this division and review technique (PERT) and Monte Carlo simulation (MCS)
method was suggested in existing research (Pena-Mora and Li (Ock and Han 2010). For evaluating this uncertainty on fast-track
2001; Bogus et al. 2005; Maheswari et al. 2006). Meanwhile, space projects, therefore, determination of the duration for each DWP and
zoning or planning often results in effectively reducing construc- CWP is based on the three-point estimation (i.e., optimistic, most
tion duration through the iteration and overlapping of the related likely, and pessimistic duration) from the PERT technique. That is,
activities and also reducing the congestion and interference among the durations of each DWP [i.e., Di in Eq. (2)] and CWP [Dij in
the work tasks or resources in a project (Yeh 1995; Tommelein and Eq. (3)] could be defined by one of the three estimation values, as
Zouein 1993; Atinci et al. 2002). Because the space zoning concept shown in Eqs. (2) and (3).
is often applied to achieve reduction of the work time in repetitive
construction projects, this concept has become widely used in Di ¼ fðdpi ; dm
i ; di Þ;
o
for i ¼ 1 − k ð2Þ
edence relationship among them as well as their start and finish Meanwhile, the start time of the first CWPs (i.e., CWP11 ,
times. As shown in Fig. 2, once the fast-track methodology was
CWP21 , CWP31 , and CWP41 in Fig. 2) could be determined by
applied, basically each DWP overlaps with the CWP. For this over-
two conditions: (1) completion of precedence DWP (i.e., the con-
lapping, arranging each work package according to logic for estab-
dition from the relationship between the DWP and CWP), and
lishing precedence relationship is required. The logic for the
(2) availability of working space. For example, the initiation of
precedence relationship considers the relationship between DWP
CWP31 in Fig. 2 would be possible only after the later finish time
and CWP as well as the relationship among DWPs and CWPs,
of DWP3 (i.e., FT3 ) and CWP21 (i.e., FT21 ).
respectively.
Therefore, the start time of each work package could be defined
• The relationship between DWP and CWP: According to the
as Eqs. (4) and (5):
definition of fast track, the completion of precedence DWP
basically could be ensuring the start of equivalent CWP. For es- For DWPi ; STi ¼ FT; for i ¼ 1 − k; ST1 ¼ 0 ð4Þ
tablishing the relationship between them, therefore, it is required
to make a basic connection (i.e., which DWP is to be the pre-
For CWPij ; STij ¼ LargestðFTi ; FTi−1j ; FTij−1 Þ;
cedent package for each CWP). As shown in A in Fig. 2, if first
CWPs (i.e., CWP11 , CWP21 , CWP31 , and CWP41 in Fig. 2) are for i ¼ 1 − n; j ¼ 1 − m; FT0j ¼ 0; FTi0 ¼ 0 ð5Þ
determined as the following packages of DWP (i.e., DWP1 ,
DWP2 , DWP3 , and DWP4 ), the start time of the first CWPs where STi = start time of DWPi ; FTi−1 = finish time of DWPi−1 ;
could be determined by the finish time of the DWPs. STij = start time of CWPi on work space j; FTi = finish time
• The relationship among DWPs and CWPs: Based on the pre- of DWPi ; FTi−1j = finish time of CWPi−1 on work space j; and
vious basic relationship, as shown in B in Fig. 2, it is necessary FTij−1 = finish time of CWPi on work space j − 1.
to make the precedence relationship within the DWPs and In addition, as shown in C in Fig. 2, because there will be the
CWPs, and finally adjust the position of each work package. buffer times (or floats) between work packages, the start time of
Within DWPs, it is considered that precedence DWP is com- each DWP and CWP could be calculated as the sum of the finish
pleted in order to establish the relationship. That is, if there time of the precedence work package and buffer time [refer to
are k DWPs, DWPk−1 could be a precedence package of DWPk . Eqs. (6) and (7)].
where BTi−1 = buffer time of DWPi−1 ; and BTij−1 = buffer time of Cij ¼ EC00 × W ij ; for i ¼ 1 − n;
CWPi on work space j − 1.
j ¼ 1 − m; W 11 þ W 12 þ · · · þW nm ¼ 1 ð12Þ
As the final process in arranging each work package, the finish
time of each work package (i.e., FTi or FTij ) could be calculated by
the sum of the start time of each work package from Eqs. (6) and (7) X
n X
n X
m
and the duration of each work package from Eqs. (2) and (3) [refer DC0 ¼ EC0 þ EC00 ¼ Ci þ Cij ð13Þ
to Eqs. (8) and (9)]. i¼1 i¼1 j¼1
Downloaded from ascelibrary.org by University Of Seoul on 01/13/13. Copyright ASCE. For personal use only; all rights reserved.
For DWPi ; FTi ¼ STi þ Di ; for i ¼ 1 − k ð8Þ For the third step, the uncertainty lies in the unpredictable fac-
tors in construction projects. Because this uncertainty can not only
For CWPij ; FTij ¼ STij þ Dij ; cause changes in the duration of a project [i.e., Eqs. (2) and (3) in
for i ¼ 1 − n; j¼1−m ð9Þ the scheduling module], but can also affect the project cost, the
cost variance caused by uncertainty should be considered. As
mentioned in “Scheduling Module,” the three-point estimation
Step 3: Calculating Project Duration (i.e., most likely duration, optimistic duration, and pessimistic
duration) for the duration of each package was applied in this
Once the position of the work packages through the previous two study. In this context, the duration variances caused by uncertainty
steps has been established, as shown in Fig. 2, the finish time of the could be calculated on the basis of the difference between the
last work package (i.e., FT43 in Fig. 2) would represent the project most likely durations [i.e., Dm m
i and Dij in Eqs. (2) and (3)]
duration [refer to Eq. (10)]. and the selected durations [i.e., Di and Dij in Eqs. (2) and (3)]
Project Duration ¼ Finish Time of the Last CWP ð10Þ because Dm m
i and Dij are the most generally accepted durations
for each package, while Di and Dij are the selected durations
for consideration of uncertainty. As a result, those variations in
Cost-Estimating Module terms of duration for each package could be transferred into
the CV because generally there would be a trade-off relationship
The cost-estimating module is designed to estimate the project cost between time and cost in construction projects (Cho et al. 2010a).
for the fast-track delivered construction project with respect to two That is, the CVs per work package could be calculated as follows:
aspects: (1) the direct and indirect costs and (2) the operation and (1) calculating daily costs of each work package [i.e., Ci =day and
profit cost for the reduced duration due to fast tracking. Cij =day in Eqs. (14) and (15)], (2) analyzing the differences be-
tween the selected duration by model and the most likely dura-
tions [i.e., (Di − Dm i ) and (Dij − Dij ) in Eqs. (16) and (17)],
m
Calculating Direct Costs and (3) multiplying the results from (1) and (2) [refer to Eqs. (16)
There are four steps in estimating the direct costs (i.e., design cost and (17)]. In Eq. (18), CVTotal is defined as the sum of the CVs of
and construction cost) for the fast-track delivered project: (1) pre- each package.
diction of the total design cost and construction cost, (2) arrange-
Ci
ment of the design and construction cost into the cost of each For DWP; Ci =day ¼ ð14Þ
work package, (3) consideration of cost variance (CV) according Di
to uncertainty, and (4) calculation of the direct cost.
For the first step, which pursues the prediction of design and Cij
construction cost, a great deal of past research has tried to predict For CWP; Cij =day ¼ ð15Þ
Dij
those costs using various methodologies, so this paper will not
develop such a methodology. Instead, the estimated design
cost and construction cost are defined as EC0 (i.e., costs for all CVi ¼ ðDi − Dm
i Þ × Ci =day ð16Þ
design works) and EC00 (i.e., costs for all construction works),
respectively.
For the second step, the estimated design and construction costs CVij ¼ ðDij − Dm
ij Þ × Cij =day ð17Þ
should be split into the costs of each work package for fast tracking
[i.e., DWPi and CWPij in Eq. (1)]. For achieving this arrangement,
X
n X
n X
m
it is necessary to determine the weights for each package that will CVTotal ¼ CVi þ CVij ð18Þ
be considered as the work quantity on each package. For instance, i¼1 i¼1 j¼1
if there are n DWPs, the n weights per each DWP could be deter-
mined in terms of their work quantity. Then, the costs per each Finally, DCFinal , which means the final direct cost of the project
DWP could be determined by splitting the total cost of the design to which the fast-track method was applied, could be expressed by
work into them according to their weights. As shown in Eqs. (11) the sum of DC0 [in Eq. (13)] and CVTotal [in Eq. (18)], as shown
and (12), if the weights of DWPi and CWPij are defined as W i and in Eq. (19).
W ij , respectively, the allotted cost per each package (i.e., Ci and
Cij ) could be calculated by multiplying EC0 and W i , and EC00 DCFinal ¼ DC0 þ CVTotal ð19Þ
r = rate of indirect costs per 1 month, which would be determined ber of days in the month [refer to Eq. (23)].
according to project characteristics (e.g., size and complexity). Meanwhile, the number of days in the month is assumed to be
Meanwhile, MCn [i.e., monthly direct costs for the nth month in 30 days in this paper. Therefore, 30 × ðn − 1Þ and 30 × n in
Eq. (21)] could be defined by multiplying the number of working Eq. (22) represent the start day of the nth month and the finish
days for the nth month and the daily cost [i.e., Eqs. (14) and (15)]. day of the nth month, respectively. By considering the situations
As shown in D in Fig. 2, for example, if CWP13 , CWP22 , CWP31 , of each work package, finally, the MCn per each package
and CWP41 are proceeding on for the nth month, MCn could be [i.e., MCn ðDWPi Þ or MCn ðCWPij Þ in Eqs. (22) and (23)] can be
calculated as follows: (1) multiplying the working days per each calculated by Eqs. (22) and (23). Then MCn can be calculated by the
package for the nth month and daily costs per each package, sum of the monthly costs for each package, as shown in Eq. (24).
8( ! !) !
>
> FTi 30 × ðn − 1Þ Ci =day
! >
>
> − × ; if 30 × ðn − 1Þ < fðFTi ; FTij Þ ≤ 30 × n; : : : ðaÞ
MCn ðDWPi Þ < FTij 30 × ðn − 1Þ Cij =day
¼ ( ! !) ! ð22Þ
MCn ðCWPij Þ >
> 30 × n STi Ci =day
>
>
>
: − × if 30 × ðn − 1Þ < fðSTi STij Þ ≤ 30 × n; : : : ðbÞ
30 × n STij Cij =day
to find the optimal trade-offs, could be represented as the minimum the solutions that have the highest fitness values are screened
value of unit project cost (i.e., project cost divided by project (i.e., appropriate solutions in Fig. 4).
duration). 4. Based on the screened solutions, the new solutions (child gen-
eration) are created by generic operators (i.e., crossover and
PCi mutation).
Objective function ¼ min ; i¼1−x ð28Þ
PDi 5. Until the optimized solutions, which have the minimum values
of the objective function [i.e., Eq. (28)] in the reevaluation
where x = number of fast-track solutions; PCi = project cost for of the fitness values for the new solutions, are found, processes
solution i; and PDi = project duration for solution i. 1 to 5 are repeated.
for the sequential method could be used as they were in TACTICS. This research developed scenarios based on the changes in
The details for the sequential method are discussed in the next operation costs and profit in order to compare the results between
section with respect to a case study. the application of the sequential method and the fast-track method.
According to each scenario, which was developed based on the
monthly operation costs rate [i.e., OC0 in Eq. (25)] and the monthly
Case Study I profit rate [i.e., P0 in Eq. (26)], as shown in Table 2, the optimized
fast-track solution and sequential solution could be helpful in the
As shown on the right side of Table 1, an example project for the decision-making process of whether or not to apply the fast-track
first case study was designed with 4 DWPs and 16 CWPs (i.e., 4 method to the case project. In so doing, the two monthly rates per
CWPs x 4 work spaces) and the relationship among them (i.e., the scenario are defined as percentages (i.e., 0%, 1%, 3%, and 5%) of
Precedent column in Table 1) is determined by the logic for posi- the total direct costs (i.e., the last row in Table 1). Meanwhile,
tioning in fast tracking. For example, DWP1 , DWP2 , DWP3 , and the suggested scenario identifiers (i.e., profit rate and operation cost
DWP4 are the precedence work packages of CWP11 , CWP21 , rate) were selected because the effect of those factors on the re-
CWP31 , and CWP41 , respectively. According to the encoding duced duration by fast track was larger than the other factors.
values of the GA property in Fig. 3, the values of Di (duration All of the optimized solutions in Table 2 resulted from the op-
of DWP) and Dij (duration of CWP) are determined as shown timization process shown in Fig. 5. The optimized project duration
in Table 1, while each buffer time is defined as the percentage and cost results shown in this figure reflect the application of the
(i.e., 0%, 5%, 10%) of duration of each work package. In addition, fast-track method according to the number of populations (i.e., the
the direct costs for each work package are determined by consid- number of solutions in the child generation value in Fig. 4), wherein
ering the weights of each package, as shown in Table 1. The sum of the monthly operation cost rate and profit cost rate are assumed to
each weight of DWP and CWP is designed as one, as described in be 3%. In Fig. 5, the initial solution (i.e., project duration is
Eqs. (11) and (12). In order to compare these results to the results of 600 days and project cost is US$11,776,111) is a result that was
the fast-track application, on the other hand, the input variables for estimated by the scheduling module and the cost-estimating mod-
the sequential method (i.e., the left side of Table 1) consist of one ule based on the data in Table 1 (i.e., before applying the optimi-
design work variable and four construction work variables, and the zation module). According to the optimization process in Fig. 4,
duration and cost per each work are represented as the sum of the once the optimization module of the developed model was imple-
duration and cost per work package on the right side of Table 1. mented based on the initial solution, (1) the minimized objective
function value is convergent with 15,930.49 ($=days), and (2) the application makes the example project more effective because the
equivalent project duration and cost at the minimized value are differences in project duration between the fast-track method and
680 days and US$10,832,733, respectively. As shown in Fig. 5, sequential method are remarkable.
those values are convergent at one point, even though they are var-
iations of the population size.
Shown in Table 2 are the optimized fast-track solutions and se- Case Study II
quential method solutions according to each scenario, through the
previously mentioned process. Based on the results of Table 2, a In Case Study II, the developed TACTICS model is used to analyze
project owner or manager could make a decision as follows: If a real fast-track project, which is a grocery store construction
the project owner considers the project cost as a more important project, such as a Wal-Mart store in Korea. Its project duration
factor than project duration, application of the sequential method and total direct costs were 370 days (September 1, 2005, to
could be more helpful in scenarios 5, 9, 10, 13, 14, and 15 because September 6, 2006) and US$34,555,510, respectively. The case
these scenarios show that the project cost of the sequential method project was a steel superstructure system having seven floors with
is lower than the fast-track method project (refer to Table 2 a gross floor area of 6; 818 m2 . As shown in Table 3, there were five
and Fig. 6). With the exception of those scenarios, the fast-track DWPs (i.e., excavation design, file and foundation design, super-
application is more effective for such an example project in structure design, mechanical design, and interior design) and four
terms of project cost. Meanwhile, if the project owner makes a working space zones. The CWP41 (mechanical work) proceeded
decision based on consideration of project duration, the fast-track over the entire space (i.e., not a space zoning) after construction
of the superstructure. Based on the duration and cost data from the optimized sequential method were 533 days and US$31,673,073–
real case, the duration and cost per each work package were esti- US$31,870,603, resulting in a difference in project cost between
mated and optimistic and pessimistic durations also were designed the two methods of 4.31–4.74%. Based on this result, the project
in order to consider the uncertainty. On the other hand, the input owner was correct in making the decision to apply the fast-track
variables of the sequential method were determined with one de- method for the case project.
sign work and five construction works, utilizing the method used in
Case Study I.
Table 4 shows the results of the optimized fast-track solutions Discussion
and optimized sequential method solutions based on 16 scenarios
and the data set in Table 3. Based on the results shown in Table 4, it Given the results of the case studies, the project durations and costs
was concluded that the case project could apply the fast-track of the optimized fast-track solutions could be improved signifi-
method with respect to all scenarios. That is, the ranges of project cantly compared with ones using the sequential method. In particu-
durations and project costs for the optimized fast-track solutions lar, if the fast-track method is applied, (1) the average reduction in
were 430–440 days and US$30,171,127 (i.e., Scenario 4) to US project duration was 40.48% (on Case I) and 18.59% (on Case II)
$30,497,052 (i.e., Scenario 13), respectively. The results for the compared with using the traditional method, and (2) the average
project costs were reduced as much as 0.39% (on Case I) and US$11,550,000 in project costs (refer to Traditional Solution in
4.48% (on Case II) (please refer to Tables 2 and 4). In addition, Fig. 7). When TACTICS was applied, based on Table 1, the sched-
from the viewpoint of each scenario, the fast-track method would uling module (i.e., fast-track logic) and cost-estimating module of
be more acceptable if a project expects that a profit is higher than an TACTICS suggested the arrangement of each work package as well
operation cost. as the project duration (i.e., 600 days) and project costs (i.e.,
Fig. 7 illustrates the traditional method (i.e., sequential method) US$11,776,111) (refer to Nonoptimized Fast-Track Solution in
application results and the TACTICS results based on both the in- Fig. 7). Finally, the optimized project duration and cost was pro-
formation in Table 1 and the assumption of a 1% operation rate posed by the GA-based optimization module in TACTICS. The
and profit rate (i.e., Scenario 6 in Table 2). The application of optimized fast-track solution shows a project duration of 680 days
the traditional method resulted in a 970-day project duration and and total project costs of US$10,832,733 (refer to Optimized