Customer Name Oman Gas Company (OGC) S.A.O.C. Project No
Project Title Sohar and Ibri GSS Project Requisition No
Requisition Title Requisition for Ultrasonic Flow meter (Inline type) Jobsite Location

INSPECTION REQUIREMENTS
Criticality Rating: 3
Inspection Required: Yes, As per Section IV
AVME Number: 32.621

SECTIONS (THE SECTIONS LISTED BELOW ARE CONTAINED IN THIS REVISION OF THE REQUISITION)
Section Section Title
I Deliverable Items List
II Technical Documents and Attachments
III Vendor Data Requirements
IV Vendor Quality Management Requirements

REVISION HISTORY
Revision Issue Date
0 Not issued -
A Not issued -
B Approved for Purchase 13/11/2017

The Requisition for Ultrasonic flow meter inline type was issued for enquiry under requisition no. R6-008-16-5-035-4-A
combined with Clamp-on type flow meters. However, Purchase requisition for Inline type flow meter and Clamp-on type flow
meter is segregated. Hence, this purchase requisition is pertaining only to Inline type flow meter and refer to R6-008-16-5-
035-4-B for Clamp-on type flow meter Purchase details.

AUTHORIZATIONS
Originator Checker Discipline Lead/EM
Name: Satheesh Name: Thilakavathy Sam Kumar Name: Sarang Joshi

Date: 13/11/2017 Date: 13/11/2017 Date: 13/11/2017

Quality Project Customer


Name: S. Thota Name: A. Brinkhuizen/ P. Sarin Name:

Date: 13/11/2017 Date: 13/11/2017 Date:

Project Internal
Engineering Requisition
Coversheet
Customer Name Oman Gas Company (OGC) S.A.O.C. Project No
Project Title Sohar and Ibri GSS Project Requisition No
Requisition Title Requisition for Ultrasonic Flow meter (Inline type) Jobsite Location
REVISION DESCRIPTION LIST

Par
Rev. Revision Description
a.
0 Not issued
A Not issued
B Approved for Purchase (incorporating Client comments on R6-008-16-5-035-4-A and Vendor details)

Hold Par Description of Hold


No. a.

Project Internal
Engineering Requisition
Section I – Deliverables Items List
(Scope of Supply)
Customer Name Oman Gas Company (OGC) S.A.O.C. Rev: B Project No 403060-00756
Project Title Sohar and Ibri GSS Project Date: 13/11/2017 Requisition No R6-008-16-5-032-4-B
Requisition Title Requisition for Ultrasonic Flow meter (Inline type) Jobsite Location Ibri/ Sohar, Oman

Item Commodity/ Size 1 Size 2 Description Prev Rev Total Unit Delivery
No. Tag (End Rating) Qty Qty Qty Designation

A IBRI
A1 116-FIQ-008 2” (Note-8) 600# Inline Ultrasonic flowmeter with accessories 1 -1 0 No.
A2 116-FIQA-004 14” (Note-8) 150# Inline Ultrasonic flowmeter with accessories 1 - 1 No.
B SOHAR
B1 91-FIC-247 14” (Note-8) 300# Clamp-on Ultrasonic flowmeter with accessories 1 -1 0 No.
B2 91-FIC-248 14” (Note-8) 300# Clamp-on Ultrasonic flowmeter with accessories 1 -1 0 No.
B3 91-FIC-249 10” (Note-8) 300# Clamp-on Ultrasonic flowmeter with accessories 1 -1 0 No.
B4 91-FIC-250 10” ((Note-8) 300# Clamp-on Ultrasonic flowmeter with accessories 1 -1 0 No.
B5 91-FIQA-291 2” (Note-8) 300# Inline Ultrasonic flowmeter with accessories 1 -1 0 No.
C COMMON
Pressure/temperature compensation software to upload in system shall
C1 035_SOFT_001 - - 1 - 1 Set -
be provided in CD with necessary license (if applicable)
C2 035_COM_SPR - - Installation and Commissioning Spare Parts 1 - 1 Lot -
C3 035_OPS_SPR - - 2 Years Operating Spare 1 - 1 Lot -
C4 035_COM-ASST - - Commissioning assistance (Day Rate) (Note-7) 1 - 1 Day -
C5 035_SP_TOOLS - - Special Tools (if any) 1 - 1 Set -
C6 035_REP_KIT - - Online Transducer Replacement Kit 1 - 1 Set -
C7 035_DOC - - Documentation as per Section-III 1 - 1 Set -
C8 035_TEST - - Tests as per Section-II and IV of MR 1 - 1 Lot -
C9 035_SITE_SUP - - Site Supervision (Note-9) 1 - 1 Lot -

Project Internal Page 1 of 2


Engineering Requisition
Section I – Deliverables Items List
(Scope of Supply)
Customer Name Oman Gas Company (OGC) S.A.O.C. Rev: B Project No 403060-00756
Project Title Sohar and Ibri GSS Project Date: 13/11/2017 Requisition No R6-008-16-5-032-4-B
Requisition Title Requisition for Ultrasonic Flow meter (Inline type) Jobsite Location Ibri/ Sohar, Oman

Notes :
Asbestos, whether combined with other materials or in free form, shall NOT be used in any installation, supplied equipment or packaging thereof. If asbestos is found to exist in an
1 installation, supplied equipment or packaging, the installation, equipment or packaging will be rejected and the supplier shall be responsible for the removal and clean-up of all
asbestos materials and all associated clean-up costs.
Hazardous Substances- The presence or use of any hazardous substances (substances which have the potential to cause harm to the health of people through their use of the
2
installation or supplied equipment) must be declared by the Supplier at Quotation and confirmed after Award of Purchase Order.
Errors and Omissions – the Supplier shall advise WorleyParsons in writing of any errors, omissions, inconsistencies, ambiguities or discrepancies identified in documentation
3
provided by Worley Parsons Oman Engineering LLC or Oman Gas Company (OGC) S.A.O.C.
4 All the items shall be from procure from Company approved vendor list.
Revised content shall be identified using “italic font & underlined” and the relevant paragraph where the content is modified (i.e. added / deleted to respond to OGC comments) is
5
marked with “vertical line on the right side”.
6 CR: Criticality Rating
The personnel deputed for the activities shall have minimum 10-12 yrs. experience in the project. Purchaser approval is required prior to deputation. Per diem shall include air
7
travel, transportation, accommodation, daily needs, etc. Working hours will be 10 hours per day.
8 Vendor to confirm the size of the flow meter to cover the complete flow range.
9 Site supervision during installation of meters (Specifically for Clamp on type) is required.