You are on page 1of 2

ACTIVITIES NO. OF WORKERS NO.

OF DAYS

ACTIVITY A- SITE CLEARING 3 1

ACTIVITY B- EXCAVATION 3 1

ACTIVITY C- PRE-BORING 3 1

ACTIVITY D- ASSEMBLY OF REBAR CAGE 6 3

ACTIVITY E- PLACING OF REBAR CAGE 2 1

ACTIVITY F- BILLBOARD FRAME MANUFACTURING 2 3

ACTIVITY G- POURING OF CONCRETE 2 1

ACTIVITY H- OFFLOADING OF POLE 3 1

ACTIVITY I- PLACING ACHOR BOLTS 2 7

ACTIVITY J- ASSEMBLY OF POLE 2 1

ACTIVITY K- ERECTION OF POLE 2 1

ACTIVITY L- LOCKING UP OF POLE 3 1

ACTIVITY N- LIFTING UP OF BILLBOARD FRAME 2 1

ACTIVITY M- TIGHTENING UP BILLBOARD 2 1


NETWORK DIAGRAM

3 D

A B C E G I K L M
1 2 4 5 8 9 11 12 13 14

H J

10
F N
6 7