Professional Documents
Culture Documents
147324 May 25, 2004 Same; Same; Same; Requisites; The concurrence of the following
elements must be established.—In order that Globe may be exempt from
PHILIPPINE COMMUNICATIONS SATELLITE non-
CORPORATION, petitioner, _______________
vs.
GLOBE TELECOM, INC. (formerly Globe Mckay Cable and Radio *SECOND DIVISION.
Corporation), respondents. 154
154 SUPREME COURT REPORTS ANNOTATED
x-----------------------------x Philippine Communications Satellite Corporation vs. Globe
Telecom, Inc.
GLOBE TELECOM, INC., petitioner, compliance with its obligation to pay rentals under Section 8, the
vs. concurrence of the following elements must be established: (1) the event
PHILIPPINE COMMUNICATION SATELLITE must be independent of the human will; (2) the occurrence must render it
CORPORATION, respondent. impossible for the debtor to fulfill the obligation in a normal manner; and
(3) the obligor must be free of participation in, or aggravation of, the injury
Civil Law; Contracts; Force Majeure; Article 1174 exempts an obligor to the creditor.
from liability not only to events that are unforeseeable, but also to those Same; Same; Damages; Attorney’s Fees; In cases where both parties
which are foreseeable, but inevitable.—Article 1174, which exempts an have legitimate claims against each other, an award of attorney’s fees would
obligor from liability on account of fortuitous events or force majeure, refers not be warranted.—The award of attorney’s fees is the exception rather
not only to events that are unforeseeable, but also to those which are than the rule, and must be supported by factual, legal and equitable
foreseeable, but inevitable: Art. 1174. Except in cases specified by the law, justifications. In previously decided cases, the Court awarded attorney’s
or when it is otherwise declared by stipulation, or when the nature of the fees where a party acted in gross and evident bad faith in refusing to satisfy
obligation requires the assumption of risk, no person shall be responsible the other party’s claims and compelled the former to litigate to protect his
for those events which, could not be foreseen, or which, though foreseen rights; when the action filed is clearly unfounded, or where moral or
were inevitable. A fortuitous event under Article 1174 may either be an exemplary damages are awarded. However, in cases where both parties
“act of God,” or natural occurrences such as floods or typhoons, or an “act have legitimate claims against each other and no party actually prevailed,
of man,” such as riots, strikes or wars. such as in the present case where the claims of both parties were sustained
Same; Same; Same; Terms and Conditions; Parties may stipulate on in part, an award of attorney’s fees would not be warranted.
terms and conditions as they may see fit, and these have the force of law
between them.—Under Article 1306 of the Civil Code, parties to a contract PETITION for review on certiorari of a decision of the Court of Appeals.
may establish such stipulations, clauses, terms and conditions as they may
deem fit, as long as the same do not run counter to the law, morals, good The facts are stated in the opinion of the Court.
customs, public order or public policy. Article 1159 of the Civil Code also Rillorga, Africa, De Ocampo and Africa for Phil. Communications
provides that “[o]bligations arising from contracts have the force of law Satellite Corp.
between the contracting parties and should be complied with in good faith.” Salalima and Castelo for Globe Telecom, Inc.
Courts cannot stipulate for the parties nor amend their agreement where
the same does not contravene law, morals, good customs, public order or TINGA, J.:
public policy, for to do so would be to alter the real intent of the parties,
and would run contrary to the function of the courts to give force and effect Before the Court are two Petitions for Review assailing the Decision of the
thereto. Not being contrary to law, morals, good customs, public order, or Court of Appeals, dated 27 February 2001, in CA-G.R. CV No. 63619.1
public policy, Section 8 of the Agreement which Philcomsat and Globe
freely agreed upon has the force of law between them.
The facts of the case are undisputed.
For several years prior to 1991, Globe Mckay Cable and Radio FINDING that the Treaty constitutes a defective framework for
Corporation, now Globe Telecom, Inc. (Globe), had been engaged in the the continuing relationship between the two countries in the
coordination of the provision of various communication facilities for the spirit of friendship, cooperation and sovereign equality: Now,
military bases of the United States of America (US) in Clark Air Base, therefore, be it Resolved by the Senate, as it is hereby resolved,
Angeles, Pampanga and Subic Naval Base in Cubi Point, Zambales. The To express its decision not to concur in the ratification of the
said communication facilities were installed and configured for the Treaty of Friendship, Cooperation and Security and its
exclusive use of the US Defense Communications Agency (USDCA), and Supplementary Agreements, at the same time reaffirming its
for security reasons, were operated only by its personnel or those of desire to continue friendly relations with the government and
American companies contracted by it to operate said facilities. The people of the United States of America.6
USDCA contracted with said American companies, and the latter, in
turn, contracted with Globe for the use of the communication facilities. On 31 December 1991, the Philippine Government sent a Note Verbale to
Globe, on the other hand, contracted with local service providers such as the US Government through the US Embassy, notifying it of the
the Philippine Communications Satellite Corporation (Philcomsat) for the Philippines’ termination of the RP-US Military Bases Agreement.
provision of the communication facilities. The Note Verbalestated that since the RP-US Military Bases Agreement,
as amended, shall terminate on 31 December 1992, the withdrawal of all
On 07 May 1991, Philcomsat and Globe entered into an Agreement US military forces from Subic Naval Base should be completed by said
whereby Philcomsat obligated itself to establish, operate and provide an date.
IBS Standard B earth station (earth station) within Cubi Point for the
exclusive use of the USDCA.2 The term of the contract was for 60 months, In a letter dated 06 August 1992, Globe notified Philcomsat of its
or five (5) years.3 In turn, Globe promised to pay Philcomsat monthly intention to discontinue the use of the earth station effective 08
rentals for each leased circuit involved.4 November 1992 in view of the withdrawal of US military personnel from
Subic Naval Base after the termination of the RP-US Military Bases
At the time of the execution of the Agreement, both parties knew that the Agreement. Globe invoked as basis for the letter of termination Section 8
Military Bases Agreement between the Republic of the Philippines and (Default) of the Agreement, which provides:
the US (RP-US Military Bases Agreement), which was the basis for the
occupancy of the Clark Air Base and Subic Naval Base in Cubi Point, was Neither party shall be held liable or deemed to be in default for
to expire in 1991. Under Section 25, Article XVIII of the 1987 any failure to perform its obligation under this Agreement if such
Constitution, foreign military bases, troops or facilities, which include failure results directly or indirectly from force majeure or
those located at the US Naval Facility in Cubi Point, shall not be allowed fortuitous event. Either party is thus precluded from performing
in the Philippines unless a new treaty is duly concurred in by the Senate its obligation until such force majeure or fortuitous event shall
and ratified by a majority of the votes cast by the people in a national terminate. For the purpose of this paragraph, force majeure shall
referendum when the Congress so requires, and such new treaty is mean circumstances beyond the control of the party involved
recognized as such by the US Government. including, but not limited to, any law, order, regulation, direction
or request of the Government of the Philippines, strikes or other
Subsequently, Philcomsat installed and established the earth station at labor difficulties, insurrection riots, national emergencies, war,
Cubi Point and the USDCA made use of the same. acts of public enemies, fire, floods, typhoons or other
catastrophies or acts of God.
On 16 September 1991, the Senate passed and adopted Senate Resolution
No. 141, expressing its decision not to concur in the ratification of the Philcomsat sent a reply letter dated 10 August 1992 to Globe, stating that
Treaty of Friendship, Cooperation and Security and its Supplementary "we expect [Globe] to know its commitment to pay the stipulated rentals
Agreements that was supposed to extend the term of the use by the US of for the remaining terms of the Agreement even after [Globe] shall have
Subic Naval Base, among others.5 The last two paragraphs of the discontinue[d] the use of the earth station after November 08,
Resolution state: 1992."7 Philcomsat referred to Section 7 of the Agreement, stating as
follows:
7. DISCONTINUANCE OF SERVICE Dollars (US$92,238.00) or its equivalent in Philippine
Currency (computed at the exchange rate prevailing at
Should [Globe] decide to discontinue with the use of the earth the time of compliance or payment) representing rentals
station after it has been put into operation, a written notice shall for the month of December 1992 with interest thereon at
be served to PHILCOMSAT at least sixty (60) days prior to the the legal rate of twelve percent (12%) per annum starting
expected date of termination. Notwithstanding the non-use of the December 1992 until the amount is fully paid;
earth station, [Globe] shall continue to pay PHILCOMSAT for the
rental of the actual number of T1 circuits in use, but in no case 2. Ordering the defendant to pay the plaintiff the amount
shall be less than the first two (2) T1 circuits, for the remaining of Three Hundred Thousand (P300,000.00) Pesos as and
life of the agreement. However, should PHILCOMSAT make use for attorney’s fees;
or sell the earth station subject to this agreement, the obligation
of [Globe] to pay the rental for the remaining life of the 3. Ordering the DISMISSAL of defendant’s counterclaim
agreement shall be at such monthly rate as may be agreed upon for lack of merit; and
by the parties.8
4. With costs against the defendant.
After the US military forces left Subic Naval Base, Philcomsat sent Globe
a letter dated 24 November 1993 demanding payment of its outstanding SO ORDERED.9
obligations under the Agreement amounting to US$4,910,136.00 plus
interest and attorney’s fees. However, Globe refused to heed Philcomsat’s
Both parties appealed the trial court’s Decision to the Court of Appeals.
demand.
Philcomsat claimed that the trial court erred in ruling that: (1) the non-
On 27 January 1995, Philcomsat filed with the Regional Trial Court of
ratification by the Senate of the Treaty of Friendship, Cooperation and
Makati a Complaint against Globe, praying that the latter be ordered to
Security and its Supplementary Agreements constitutes force
pay liquidated damages under the Agreement, with legal interest,
majeure which exempts Globe from complying with its obligations under
exemplary damages, attorney’s fees and costs of suit. The case was raffled
the Agreement; (2) Globe is not liable to pay the rentals for the remainder
to Branch 59 of said court.
of the term of the Agreement; and (3) Globe is not liable to Philcomsat for
exemplary damages.
Globe filed an Answer to the Complaint, insisting that it was constrained
to end the Agreement due to the termination of the RP-US Military Bases
Globe, on the other hand, contended that the RTC erred in holding it
Agreement and the non-ratification by the Senate of the Treaty of
liable for payment of rent of the earth station for December 1992 and of
Friendship and Cooperation, which events constituted force
attorney’s fees. It explained that it terminated Philcomsat’s services on
majeure under the Agreement. Globe explained that the occurrence of
08 November 1992; hence, it had no reason to pay for rentals beyond that
said events exempted it from paying rentals for the remaining period of
date.
the Agreement.
1. Ordering the defendant to pay the plaintiff the amount The appellate court ruled that the non-ratification by the Senate of the
of Ninety Two Thousand Two Hundred Thirty Eight US Treaty of Friendship, Cooperation and Security, and its Supplementary
Agreements, and the termination by the Philippine Government of the D. THE HONORABLE COURT OF APPEALS ERRED IN
RP-US Military Bases Agreement effective 31 December 1991 as stated in RULING THAT GLOBE TELECOM IS NOT LIABLE TO
the Philippine Government’s Note Verbale to the US Government, are PHILCOMSAT FOR EXEMPLARY DAMAGES.12
acts, directions, or requests of the Government of the Philippines which
constitute force majeure. In addition, there were circumstances beyond Philcomsat argues that the termination of the RP-US Military Bases
the control of the parties, such as the issuance of a formal order by Cdr. Agreement cannot be considered a fortuitous event because the
Walter Corliss of the US Navy, the issuance of the letter notification from happening thereof was foreseeable. Although the Agreement was freely
ATT and the complete withdrawal of all US military forces and personnel entered into by both parties, Section 8 should be deemed ineffective
from Cubi Point, which prevented further use of the earth station under because it is contrary to Article 1174 of the Civil Code. Philcomsat posits
the Agreement. the view that the validity of the parties’ definition of force majeure in
Section 8 of the Agreement as "circumstances beyond the control of the
However, the Court of Appeals ruled that although Globe sought to party involved including, but not limited to, any law, order, regulation,
terminate Philcomsat’s services by 08 November 1992, it is still liable to direction or request of the Government of the Philippines, strikes or other
pay rentals for the December 1992, amounting to US$92,238.00 plus labor difficulties, insurrection riots, national emergencies, war, acts of
interest, considering that the US military forces and personnel public enemies, fire, floods, typhoons or other catastrophies or acts of
completely withdrew from Cubi Point only on 31 December 1992. 10 God," should be deemed subject to Article 1174 which defines fortuitous
events as events which could not be foreseen, or which, though foreseen,
Both parties filed their respective Petitions for Review assailing were inevitable.13
the Decision of the Court of Appeals.
Philcomsat further claims that the Court of Appeals erred in holding that
In G.R. No. 147324,11 petitioner Philcomsat raises the following Globe is not liable to pay for the rental of the earth station for the entire
assignments of error: term of the Agreement because it runs counter to what was plainly
stipulated by the parties in Section 7 thereof. Moreover, said ruling is
A. THE HONORABLE COURT OF APPEALS ERRED IN inconsistent with the appellate court’s pronouncement that Globe is liable
ADOPTING A DEFINITION OF FORCE to pay rentals for December 1992 even though it terminated Philcomsat’s
MAJEUREDIFFERENT FROM WHAT ITS LEGAL services effective 08 November 1992, because the US military and
DEFINITION FOUND IN ARTICLE 1174 OF THE CIVIL CODE, personnel completely withdrew from Cubi Point only in December 1992.
PROVIDES, SO AS TO EXEMPT GLOBE TELECOM FROM Philcomsat points out that it was Globe which proposed the five-year
COMPLYING WITH ITS OBLIGATIONS UNDER THE term of the Agreement, and that the other provisions of the Agreement,
SUBJECT AGREEMENT. such as Section 4.114 thereof, evince the intent of Globe to be bound to pay
rentals for the entire five-year term.15
B. THE HONORABLE COURT OF APPEALS ERRED IN
RULING THAT GLOBE TELECOM IS NOT LIABLE TO Philcomsat also maintains that contrary to the appellate court’s findings,
PHILCOMSAT FOR RENTALS FOR THE REMAINING TERM it is entitled to attorney’s fees and exemplary damages.16
OF THE AGREEMENT, DESPITE THE CLEAR TENOR OF
SECTION 7 OF THE AGREEMENT. In its Comment to Philcomsat’s Petition, Globe asserts that Section 8 of
the Agreement is not contrary to Article 1174 of the Civil Code because
C. THE HONORABLE OCURT OF APPEALS ERRED IN said provision does not prohibit parties to a contract from providing for
DELETING THE TRIAL COURT’S AWARD OF ATTORNEY’S other instances when they would be exempt from fulfilling their
FEES IN FAVOR OF PHILCOMSAT. contractual obligations. Globe also claims that the termination of the RP-
US Military Bases Agreement constitutes force majeure and exempts it
from complying with its obligations under the Agreement.17 On the issue
of the propriety of awarding attorney’s fees and exemplary damages to
Philcomsat, Globe maintains that Philcomsat is not entitled thereto
because in refusing to pay rentals for the remainder of the term of the In support of its position, Philcomsat contends that under Article 1174 of
Agreement, Globe only acted in accordance with its rights.18 the Civil Code, an event must be unforeseen in order to exempt a party to
a contract from complying with its obligations therein. It insists that
In G.R. No. 147334,19 Globe, the petitioner therein, contends that the since the expiration of the RP-US Military Bases Agreement, the non-
Court of Appeals erred in finding it liable for the amount of ratification of the Treaty of Friendship, Cooperation and Security and the
US$92,238.00, representing rentals for December 1992, since withdrawal of US military forces and personnel from Cubi Point were not
Philcomsat’s services were actually terminated on 08 November 1992.20 unforeseeable, but were possibilities known to it and Globe at the time
they entered into the Agreement, such events cannot exempt Globe from
In its Comment, Philcomsat claims that Globe’s petition should be performing its obligation of paying rentals for the entire five-year term
dismissed as it raises a factual issue which is not cognizable by the Court thereof.
in a petition for review on certiorari.21
However, Article 1174, which exempts an obligor from liability on account
On 15 August 2001, the Court issued a Resolution giving due course to of fortuitous events or force majeure, refers not only to events that are
Philcomsat’s Petition in G.R. No. unforeseeable, but also to those which are foreseeable, but inevitable:
147324 and required the parties to submit their respective memoranda.22 Art. 1174. Except in cases specified by the law, or when it is
otherwise declared by stipulation, or when the nature of the
obligation requires the assumption of risk, no person shall be
Similarly, on 20 August 2001, the Court issued a Resolution giving due
responsible for those events which, could not be foreseen, or
course to the Petition filed by Globe in G.R. No. 147334 and required both
which, though foreseen were inevitable.
parties to submit their memoranda.23
No reversible error was committed by the Court of Appeals in issuing the 4. Riots;
assailed Decision; hence the petitions are denied.
5. National emergencies;
There is no merit is Philcomsat’s argument that Section 8 of the
Agreement cannot be given effect because the enumeration of events 6. War;
constituting force majeure therein unduly expands the concept of a
fortuitous event under Article 1174 of the Civil Code and is therefore 7. Acts of public enemies;
invalid.
8. Fire, floods, typhoons or other catastrophies or acts of God; Obviously the non-ratification by the Senate of the RP-US
Military Bases Agreement (and its Supplemental Agreements)
9. Other circumstances beyond the control of the parties. under its Resolution No. 141. (Exhibit "2") on September 16, 1991
is beyond the control of the parties. This resolution was followed
Clearly, the foregoing are either unforeseeable, or foreseeable but beyond by the sending on December 31, 1991 o[f] a "Note
the control of the parties. There is nothing in the enumeration that runs Verbale" (Exhibit "3") by the Philippine Government to the US
contrary to, or expands, the concept of a fortuitous event under Article Government notifying the latter of the former’s termination of the
1174. RP-US Military Bases Agreement (as amended) on 31 December
1992 and that accordingly, the withdrawal of all U.S. military
forces from Subic Naval Base should be completed by said date.
Furthermore, under Article 130626 of the Civil Code, parties to a contract
Subsequently, defendant [Globe] received a formal order from
may establish such stipulations, clauses, terms and conditions as they
Cdr. Walter F. Corliss II Commander USN dated July 31, 1992
may deem fit, as long as the same do not run counter to the law, morals,
and a notification from ATT dated July 29, 1992 to terminate the
good customs, public order or public policy.27
provision of T1s services (via an IBS Standard B Earth Station)
effective November 08, 1992. Plaintiff [Philcomsat] was furnished
Article 1159 of the Civil Code also provides that "[o]bligations arising with copies of the said order and letter by the defendant on
from contracts have the force of law between the contracting parties and August 06, 1992.
should be complied with in good faith."28 Courts cannot stipulate for the
parties nor amend their agreement where the same does not contravene
Resolution No. 141 of the Philippine Senate and the Note Verbale
law, morals, good customs, public order or public policy, for to do so would
of the Philippine Government to the US Government are acts,
be to alter the real intent of the parties, and would run contrary to the
direction or request of the Government of the Philippines and
function of the courts to give force and effect thereto.29
circumstances beyond the control of the defendant. The formal
order from Cdr. Walter Corliss of the USN, the letter notification
Not being contrary to law, morals, good customs, public order, or public from ATT and the complete withdrawal of all the military forces
policy, Section 8 of the Agreement which Philcomsat and Globe freely and personnel from Cubi Point in the year-end 1992 are also acts
agreed upon has the force of law between them. 30 and circumstances beyond the control of the defendant.
In order that Globe may be exempt from non-compliance with its Considering the foregoing, the Court finds and so holds that the
obligation to pay rentals under Section 8, the concurrence of the following afore-narrated circumstances constitute "force majeure or
elements must be established: (1) the event must be independent of the fortuitous event(s) as defined under paragraph 8 of the
human will; (2) the occurrence must render it impossible for the debtor to Agreement.
fulfill the obligation in a normal manner; and (3) the obligor must be free
of participation in, or aggravation of, the injury to the creditor. 31
…
The Court agrees with the Court of Appeals and the trial court that the
From the foregoing, the Court finds that the defendant is
abovementioned requisites are present in the instant case. Philcomsat
exempted from paying the rentals for the facility for the
and Globe had no control over the non-renewal of the term of the RP-US
remaining term of the contract.
Military Bases Agreement when the same expired in 1991, because the
prerogative to ratify the treaty extending the life thereof belonged to the
Senate. Neither did the parties have control over the subsequent As a consequence of the termination of the RP-US Military Bases
withdrawal of the US military forces and personnel from Cubi Point in Agreement (as amended) the continued stay of all US Military
December 1992: forces and personnel from Subic Naval Base would no longer be
allowed, hence, plaintiff would no longer be in any position to
render the service it was obligated under the Agreement. To put
it blantly (sic), since the US military forces and personnel left or
withdrew from Cubi Point in the year end December 1992, there Court of Appeals did not err when it affirmed the trial court’s ruling that
was no longer any necessity for the plaintiff to continue Globe is liable for payment of rentals until December 1992.
maintaining the IBS facility…. 32 (Emphasis in the original.)
Neither did the appellate court commit any error in holding that
The aforementioned events made impossible the continuation of the Philcomsat is not entitled to attorney’s fees and exemplary damages.
Agreement until the end of its five-year term without fault on the part of
either party. The Court of Appeals was thus correct in ruling that the The award of attorney’s fees is the exception rather than the rule, and
happening of such fortuitous events rendered Globe exempt from must be supported by factual, legal and equitable justifications. 36 In
payment of rentals for the remainder of the term of the Agreement. previously decided cases, the Court awarded attorney’s fees where a party
acted in gross and evident bad faith in refusing to satisfy the other
Moreover, it would be unjust to require Globe to continue paying rentals party’s claims and compelled the former to litigate to protect his
even though Philcomsat cannot be compelled to perform its corresponding rights;37 when the action filed is clearly unfounded,38 or where moral or
obligation under the Agreement. As noted by the appellate court: exemplary damages are awarded.39 However, in cases where both parties
have legitimate claims against each other and no party actually
We also point out the sheer inequity of PHILCOMSAT’s position. prevailed, such as in the present case where the claims of both parties
PHILCOMSAT would like to charge GLOBE rentals for the were sustained in part, an award of attorney’s fees would not be
balance of the lease term without there being any corresponding warranted.40
telecommunications service subject of the lease. It will be grossly
unfair and iniquitous to hold GLOBE liable for lease charges for a Exemplary damages may be awarded in cases involving contracts or
service that was not and could not have been rendered due to an quasi-contracts, if the erring party acted in a wanton, fraudulent,
act of the government which was clearly beyond GLOBE’s control. reckless, oppressive or malevolent manner.41 In the present case, it was
The binding effect of a contract on both parties is based on the not shown that Globe acted wantonly or oppressively in not heeding
principle that the obligations arising from contracts have the Philcomsat’s demands for payment of rentals. It was established during
force of law between the contracting parties, and there must be the trial of the case before the trial court that Globe had valid grounds for
mutuality between them based essentially on their equality under refusing to comply with its contractual obligations after 1992.
which it is repugnant to have one party bound by the contract
while leaving the other party free therefrom (Allied Banking WHEREFORE, the Petitions are DENIED for lack of merit. The
Corporation v. Court of Appeals, 284 SCRA 357)….33 assailed Decision of the Court of Appeals in CA-G.R. CV No. 63619 is
AFFIRMED.
With respect to the issue of whether Globe is liable for payment of rentals
for the month of December 1992, the Court likewise affirms the appellate SO ORDERED.
court’s ruling that Globe should pay the same.
The RTC further ruled that petitioner corporation could not be held liable The CA concluded that both petitioners should be jointly and severally
for the loss of the pawned jewelry since it had not been rebutted by held liable to respondents for the loss of the pawned jewelry.
respondents that the loss of the pledged pieces of jewelry in the
possession of the corporation was occasioned by armed robbery; that Petitioners’ motion for reconsideration was denied in a Resolution dated
robbery is a fortuitous event which exempts the victim from liability for August 8, 2003.
the loss, citing the case of Austria v. Court of Appeals;7 and that the
parties’ transaction was that of a pledgor and pledgee and under Art. Hence, the instant petition for review with the following assignment of
1174 of the Civil Code, the pawnshop as a pledgee is not responsible for errors:
those events which could not be foreseen.
THE COURT OF APPEALS ERRED AND WHEN IT DID, IT
Respondents appealed the RTC Decision to the CA. In a Decision dated OPENED ITSELF TO REVERSAL, WHEN IT ADOPTED
March 31, 2003, the CA reversed the RTC, the dispositive portion of UNCRITICALLY (IN FACT IT REPRODUCED AS ITS OWN
which reads as follows: WITHOUT IN THE MEANTIME ACKNOWLEDGING IT) WHAT
THE RESPONDENTS ARGUED IN THEIR BRIEF, WHICH
WHEREFORE, premises considered, the instant Appeal is ARGUMENT WAS PALPABLY UNSUSTAINABLE.
GRANTED, and the Decision dated January 12, 1993,of the
Regional Trial Court of Makati, Branch 62, is hereby REVERSED THE COURT OF APPEALS ERRED, AND WHEN IT DID, IT
and SET ASIDE, ordering the appellees to pay appellants the OPENED ITSELF TO REVERSAL BY THIS HONORABLE
actual value of the lost jewelry amounting to P272,000.00, and COURT, WHEN IT AGAIN ADOPTED UNCRITICALLY (BUT
attorney' fees of P27,200.00.8 WITHOUT ACKNOWLEDGING IT) THE SUBMISSIONS OF
THE RESPONDENTS IN THEIR BRIEF WITHOUT ADDING
In finding petitioner Sicam liable together with petitioner corporation, ANYTHING MORE THERETO DESPITE THE FACT THAT
the CA applied the doctrine of piercing the veil of corporate entity THE SAID ARGUMENT OF THE RESPONDENTS COULD NOT
HAVE BEEN SUSTAINED IN VIEW OF UNREBUTTED (3) In Hernandez v. Chairman, Commission on Audit (179 SCRA
EVIDENCE ON RECORD.9 39, 45-46), the victim of robbery was exonerated from liability for
the sum of money belonging to others and lost by him to robbers.
Anent the first assigned error, petitioners point out that the CA’s finding
that petitioner Sicam is personally liable for the loss of the pawned Respondents filed their Comment and petitioners filed their Reply
jewelries is "a virtual and uncritical reproduction of the arguments set thereto. The parties subsequently submitted their respective
out on pp. 5-6 of the Appellants’ brief."10 Memoranda.
Petitioners argue that the reproduced arguments of respondents in their We find no merit in the petition.
Appellants’ Brief suffer from infirmities, as follows:
To begin with, although it is true that indeed the CA findings were exact
(1) Respondents conclusively asserted in paragraph 2 of their reproductions of the arguments raised in respondents’ (appellants’) brief
Amended Complaint that Agencia de R.C. Sicam, Inc. is the filed with the CA, we find the same to be not fatally infirmed. Upon
present owner of Agencia de R.C. Sicam Pawnshop, and therefore, examination of the Decision, we find that it expressed clearly and
the CA cannot rule against said conclusive assertion of distinctly the facts and the law on which it is based as required by
respondents; Section 8, Article VIII of the Constitution. The discretion to decide a case
one way or another is broad enough to justify the adoption of the
(2) The issue resolved against petitioner Sicam was not among arguments put forth by one of the parties, as long as these are legally
those raised and litigated in the trial court; and tenable and supported by law and the facts on records.11
(3) By reason of the above infirmities, it was error for the CA to Our jurisdiction under Rule 45 of the Rules of Court is limited to the
have pierced the corporate veil since a corporation has a review of errors of law committed by the appellate court. Generally, the
personality distinct and separate from its individual stockholders findings of fact of the appellate court are deemed conclusive and we are
or members. not duty-bound to analyze and calibrate all over again the evidence
adduced by the parties in the court a quo.12 This rule, however, is not
Anent the second error, petitioners point out that the CA finding on their without exceptions, such as where the factual findings of the Court of
negligence is likewise an unedited reproduction of respondents’ brief Appeals and the trial court are conflicting or contradictory 13 as is
which had the following defects: obtaining in the instant case.
(1) There were unrebutted evidence on record that petitioners had However, after a careful examination of the records, we find no
observed the diligence required of them, i.e, they wanted to open justification to absolve petitioner Sicam from liability.
a vault with a nearby bank for purposes of safekeeping the
pawned articles but was discouraged by the Central Bank (CB) The CA correctly pierced the veil of the corporate fiction and adjudged
since CB rules provide that they can only store the pawned petitioner Sicam liable together with petitioner corporation. The rule is
articles in a vault inside the pawnshop premises and no other that the veil of corporate fiction may be pierced when made as a shield to
place; perpetrate fraud and/or confuse legitimate issues. 14 The theory of
corporate entity was not meant to promote unfair objectives or otherwise
(2) Petitioners were adjudged negligent as they did not take to shield them.15
insurance against the loss of the pledged jelweries, but it is
judicial notice that due to high incidence of crimes, insurance Notably, the evidence on record shows that at the time respondent Lulu
companies refused to cover pawnshops and banks because of high pawned her jewelry, the pawnshop was owned by petitioner Sicam
probability of losses due to robberies; himself. As correctly observed by the CA, in all the pawnshop receipts
issued to respondent Lulu in September 1987, all bear the words
"Agencia de R. C. Sicam," notwithstanding that the pawnshop was That is the reason for the modifier "such" because if the rule
allegedly incorporated in April 1987. The receipts issued after such simply states that the admission may be contradicted by showing
alleged incorporation were still in the name of "Agencia de R. C. Sicam," that "no admission was made," the rule would not really be
thus inevitably misleading, or at the very least, creating the wrong providing for a contradiction of the admission but just a
impression to respondents and the public as well, that the pawnshop was denial.18 (Emphasis supplied).
owned solely by petitioner Sicam and not by a corporation.
While it is true that respondents alleged in their Amended Complaint
Even petitioners’ counsel, Atty. Marcial T. Balgos, in his letter 16 dated that petitioner corporation is the present owner of the pawnshop, they did
October 15, 1987 addressed to the Central Bank, expressly referred to so only because petitioner Sicam alleged in his Answer to the original
petitioner Sicam as the proprietor of the pawnshop notwithstanding the complaint filed against him that he was not the real party-in-interest as
alleged incorporation in April 1987. the pawnshop was incorporated in April 1987. Moreover, a reading of the
Amended Complaint in its entirety shows that respondents referred to
We also find no merit in petitioners' argument that since respondents had both petitioner Sicam and petitioner corporation where they
alleged in their Amended Complaint that petitioner corporation is the (respondents) pawned their assorted pieces of jewelry and ascribed to
present owner of the pawnshop, the CA is bound to decide the case on both the failure to observe due diligence commensurate with the business
that basis. which resulted in the loss of their pawned jewelry.
Section 4 Rule 129 of the Rules of Court provides that an admission, Markedly, respondents, in their Opposition to petitioners’ Motion to
verbal or written, made by a party in the course of the proceedings in the Dismiss Amended Complaint, insofar as petitioner Sicam is concerned,
same case, does not require proof. The admission may be contradicted averred as follows:
only by showing that it was made through palpable mistake or that no
such admission was made. Roberto C. Sicam was named the defendant in the original
complaint because the pawnshop tickets involved in this case did
Thus, the general rule that a judicial admission is conclusive upon the not show that the R.C. Sicam Pawnshop was a corporation. In
party making it and does not require proof, admits of two exceptions, to paragraph 1 of his Answer, he admitted the allegations in
wit: (1) when it is shown that such admission was made through palpable paragraph 1 and 2 of the Complaint. He merely added "that
mistake, and (2) when it is shown that no such admission was in fact defendant is not now the real party in interest in this case."
made. The latter exception allows one to contradict an admission by
denying that he made such an admission.17 It was defendant Sicam's omission to correct the pawnshop tickets
used in the subject transactions in this case which was the cause
The Committee on the Revision of the Rules of Court explained the of the instant action. He cannot now ask for the dismissal of the
second exception in this wise: complaint against him simply on the mere allegation that his
pawnshop business is now incorporated. It is a matter of defense,
x x x if a party invokes an "admission" by an adverse party, but the merit of which can only be reached after consideration of the
cites the admission "out of context," then the one making the evidence to be presented in due course.19
"admission" may show that he made no "such" admission, or that
his admission was taken out of context. Unmistakably, the alleged admission made in respondents' Amended
Complaint was taken "out of context" by petitioner Sicam to suit his own
x x x that the party can also show that he made no "such purpose. Ineluctably, the fact that petitioner Sicam continued to issue
admission", i.e., not in the sense in which the admission is made pawnshop receipts under his name and not under the corporation's name
to appear. militates for the piercing of the corporate veil.
We likewise find no merit in petitioners' contention that the CA erred in Art. 1174. Except in cases expressly specified by the law, or when
piercing the veil of corporate fiction of petitioner corporation, as it was it is otherwise declared by stipulation, or when the nature of the
not an issue raised and litigated before the RTC. obligation requires the assumption of risk, no person shall be
responsible for those events which could not be foreseen or which,
Petitioner Sicam had alleged in his Answer filed with the trial court that though foreseen, were inevitable.
he was not the real party-in-interest because since April 20, 1987, the
pawnshop business initiated by him was incorporated and known Fortuitous events by definition are extraordinary events not foreseeable
as Agencia de R.C. Sicam. In the pre-trial brief filed by petitioner Sicam, or avoidable. It is therefore, not enough that the event should not have
he submitted that as far as he was concerned, the basic issue was been foreseen or anticipated, as is commonly believed but it must be one
whether he is the real party in interest against whom the complaint impossible to foresee or to avoid. The mere difficulty to foresee the
should be directed.20 In fact, he subsequently moved for the dismissal of happening is not impossibility to foresee the same. 22
the complaint as to him but was not favorably acted upon by the trial
court. Moreover, the issue was squarely passed upon, although To constitute a fortuitous event, the following elements must concur: (a)
erroneously, by the trial court in its Decision in this manner: the cause of the unforeseen and unexpected occurrence or of the failure of
the debtor to comply with obligations must be independent of human will;
x x x The defendant Roberto Sicam, Jr likewise denies liability as (b) it must be impossible to foresee the event that constitutes
far as he is concerned for the reason that he cannot be made the caso fortuito or, if it can be foreseen, it must be impossible to avoid; (c)
personally liable for a claim arising from a corporate transaction. the occurrence must be such as to render it impossible for the debtor to
fulfill obligations in a normal manner; and, (d) the obligor must be free
This Court sustains the contention of the defendant Roberto C. from any participation in the aggravation of the injury or loss. 23
Sicam, Jr. The amended complaint itself asserts that "plaintiff
pawned assorted jewelries in defendant's pawnshop." It has been The burden of proving that the loss was due to a fortuitous event rests on
held that " as a consequence of the separate juridical personality him who invokes it.24 And, in order for a fortuitous event to exempt one
of a corporation, the corporate debt or credit is not the debt or from liability, it is necessary that one has committed no negligence or
credit of the stockholder, nor is the stockholder's debt or credit misconduct that may have occasioned the loss. 25
that of a corporation.21
It has been held that an act of God cannot be invoked to protect a person
Clearly, in view of the alleged incorporation of the pawnshop, the issue of who has failed to take steps to forestall the possible adverse consequences
whether petitioner Sicam is personally liable is inextricably connected of such a loss. One's negligence may have concurred with an act of God in
with the determination of the question whether the doctrine of piercing producing damage and injury to another; nonetheless, showing that the
the corporate veil should or should not apply to the case. immediate or proximate cause of the damage or injury was a fortuitous
event would not exempt one from liability. When the effect is found to be
The next question is whether petitioners are liable for the loss of the partly the result of a person's participation -- whether by active
pawned articles in their possession. intervention, neglect or failure to act -- the whole occurrence is
humanized and removed from the rules applicable to acts of God. 26
Petitioners insist that they are not liable since robbery is a fortuitous
event and they are not negligent at all. Petitioner Sicam had testified that there was a security guard in their
pawnshop at the time of the robbery. He likewise testified that when he
We are not persuaded. started the pawnshop business in 1983, he thought of opening a vault
with the nearby bank for the purpose of safekeeping the valuables but
was discouraged by the Central Bank since pawned articles should only
Article 1174 of the Civil Code provides:
be stored in a vault inside the pawnshop. The very measures which
petitioners had allegedly adopted show that to them the possibility of
robbery was not only foreseeable, but actually foreseen and anticipated.
Petitioner Sicam’s testimony, in effect, contradicts petitioners’ defense of Art. 1170. Those who in the performance of their obligations are
fortuitous event. guilty of fraud, negligence, or delay, and those who in any manner
contravene the tenor thereof, are liable for damages.29
Moreover, petitioners failed to show that they were free from any
negligence by which the loss of the pawned jewelry may have been Article 2123 of the Civil Code provides that with regard to pawnshops
occasioned. and other establishments which are engaged in making loans secured by
pledges, the special laws and regulations concerning them shall be
Robbery per se, just like carnapping, is not a fortuitous event. It does not observed, and subsidiarily, the provisions on pledge, mortgage and
foreclose the possibility of negligence on the part of herein petitioners. antichresis.
In Co v. Court of Appeals,27 the Court held:
The provision on pledge, particularly Article 2099 of the Civil Code,
It is not a defense for a repair shop of motor vehicles to escape provides that the creditor shall take care of the thing pledged with the
liability simply because the damage or loss of a thing lawfully diligence of a good father of a family. This means that petitioners must
placed in its possession was due to carnapping. Carnapping per se take care of the pawns the way a prudent person would as to his own
cannot be considered as a fortuitous event. The fact that a thing property.
was unlawfully and forcefully taken from another's rightful
possession, as in cases of carnapping, does not automatically give In this connection, Article 1173 of the Civil Code further provides:
rise to a fortuitous event. To be considered as such, carnapping
entails more than the mere forceful taking of another's property. Art. 1173. The fault or negligence of the obligor consists in the
It must be proved and established that the event was an act of omission of that diligence which is required by the nature of the
God or was done solely by third parties and that neither the obligation and corresponds with the circumstances of the persons,
claimant nor the person alleged to be negligent has any of time and of the place. When negligence shows bad faith, the
participation. In accordance with the Rules of Evidence, the provisions of Articles 1171 and 2201, paragraph 2 shall apply.
burden of proving that the loss was due to a fortuitous event rests
on him who invokes it — which in this case is the private If the law or contract does not state the diligence which is to be
respondent. However, other than the police report of the alleged observed in the performance, that which is expected of a good
carnapping incident, no other evidence was presented by private father of a family shall be required.
respondent to the effect that the incident was not due to its fault.
A police report of an alleged crime, to which only private
We expounded in Cruz v. Gangan30 that negligence is the omission to do
respondent is privy, does not suffice to establish the carnapping.
something which a reasonable man, guided by those considerations which
Neither does it prove that there was no fault on the part of
ordinarily regulate the conduct of human affairs, would do; or the doing of
private respondent notwithstanding the parties' agreement at the
something which a prudent and reasonable man would not do. 31 It is want
pre-trial that the car was carnapped. Carnapping does not
of care required by the circumstances.
foreclose the possibility of fault or negligence on the part of
private respondent.28
A review of the records clearly shows that petitioners failed to exercise
reasonable care and caution that an ordinarily prudent person would
Just like in Co, petitioners merely presented the police report of the
have used in the same situation. Petitioners were guilty of negligence in
Parañaque Police Station on the robbery committed based on the report of
the operation of their pawnshop business. Petitioner Sicam testified,
petitioners' employees which is not sufficient to establish robbery. Such
thus:
report also does not prove that petitioners were not at fault.
Court:
On the contrary, by the very evidence of petitioners, the CA did not err in
finding that petitioners are guilty of concurrent or contributory
negligence as provided in Article 1170 of the Civil Code, to wit: Q. Do you have security guards in your pawnshop?
A. Yes, your honor. robbers were armed with caliber .45 pistols each, which were allegedly
poked at the employees.33 Significantly, the alleged security guard was
Q. Then how come that the robbers were able to enter the not presented at all to corroborate petitioner Sicam's claim; not one of
premises when according to you there was a security guard? petitioners' employees who were present during the robbery incident
testified in court.
A. Sir, if these robbers can rob a bank, how much more a
pawnshop. Furthermore, petitioner Sicam's admission that the vault was open at the
time of robbery is clearly a proof of petitioners' failure to observe the care,
Q. I am asking you how were the robbers able to enter despite the precaution and vigilance that the circumstances justly demanded.
fact that there was a security guard? Petitioner Sicam testified that once the pawnshop was open, the
combination was already off. Considering petitioner Sicam's testimony
that the robbery took place on a Saturday afternoon and the area in BF
A. At the time of the incident which happened about 1:00 and
Homes Parañaque at that time was quiet, there was more reason for
2:00 o'clock in the afternoon and it happened on a Saturday and
petitioners to have exercised reasonable foresight and diligence in
everything was quiet in the area BF Homes Parañaque they
protecting the pawned jewelries. Instead of taking the precaution to
pretended to pawn an article in the pawnshop, so one of my
protect them, they let open the vault, providing no difficulty for the
employees allowed him to come in and it was only when it was
robbers to cart away the pawned articles.
announced that it was a hold up.
Unlike in the Cruz case, the robbery in this case happened in petitioners'
pawnshop and they were negligent in not exercising the precautions
justly demanded of a pawnshop.
G.R. No. L-47379 May 16, 1988 God. (1 Corpus Juris, pp. 1174–1175). Thus, it has been held that when the
negligence of a person concur s with an act of God in producing a loss, such
NATIONAL POWER CORPORATION, petitioner, person is not exempt from liability by showing that the immediate cause of
vs. the damage was the act of God. To be exempt from liability for loss because
HONORABLE COURT OF APPEALS and ENGINEERING of an act of God, he must be free from any previous negligence or
CONSTRUCTION, INC., respondents. misconduct by which the loss
_______________
G.R. No. L-47481 May 16, 1988
*THIRD DIVISION.
335
ENGINEERING CONSTRUCTION, INC., petitioner,
vs. VOL. 161, MAY 16, 1988 335
COUTRT OF APPEALS and NATIONAL POWER National Power Corporation vs. Court of Appeals
CORPORATION, respondents. or damage may have been occasioned. (Fish & Elective Co. v. Phil.
Motors, 55 Phil. 129; Tucker v. Milan, 49 O.G. 4379; Limpangco &Sons v.
Raymundo A. Armovit for private respondent in L-47379. Yangco Steamship Co., 34 Phil. 594, 604; Lasam v. Smith, 45 Phil. 657)."
Same; Same; Same; Same; The question of whether or not there was
The Solicitor General for petitioner. negligence on the part of NPC is a question of fact which falls within the
jurisdiction of the CA.—Furthermore, the question of whether or not there
was negligence on the part of NPC is a question of fact which properly falls
within the jurisdiction of the Court of Appeals and will not be disturbed by
Civil Law; Torts and Damages; Negligence; NPC cannot escape
this Court unless the same is clearly unfounded, Thus, in Tolentino v.
liability because its negligence was the proximate cause of the loss and
Court of Appeals,(150 SCRA 26, 36) we ruled: “Moreover, the findings of
damage even though the typhoon was an act of God.—It is clear from the
fact of the Court of Appeals are generally final and conclusive upon the
appellate court’s decision that based on its findings of fact and that of the
Supreme Court (Leonardo v. Court of Appeals, 120 SCRA 890 [1983]. In
trial court’s, petitioner NPC was undoubtedly negligent because it opened
fact it is settled that the Supreme Court is not supposed to weigh evidence
the spillway gates of the Angat Dam only at the height of typhoon
but only to determine its substantially (Nunez v. Sandiganbayan, 100
“Welming” when it knew very well that it was safer to have opened the
SCRA 433 [1982] and will generally not disturb said findings of fact when
same gradually and earlier, as it was also undeniable that NPC knew of
supported by substantial evidence (Aytona v. Court of appeals, 113 SCRA
the coming typhoon at least four days before it actually struck. And even
575 [1985]; Collector of Customs of Manila v. Intermediate Appellate
though the typhoon was an act of God or what we may call force majeure,
Court, 137 SCRA 3 [1985]. On the other hand substantial evidence is
NPC cannot escape liability because its negligence was the proximate
defined as such relevant evidence as a reasonable mind might accept as
cause of the loss and damage. As we have ruled in Juan F. Nakpil & Sons
adequate to support a conclusion (Philippine Metal Products, Inc. v. Court
v. Court of Appeals (144 SCRA 596, 606–607): Thus, if upon the happening
of Industrial Relations, 90 SCRA 135 [1979]; Police Commission v. Lood,
of a fortuitous event or an act of God, there concurs a corresponding fraud,
127 SCRA 757 [1984]; Canete v. WCC, 136 SCRA 302 [1985])."
negligence, delay or violation or contravention in any manner of the tenor
Same; Same; Same; Same; Consequential damages; Court of Ap-peals
of the obligation as provided for in Article 1170 of the Civil Code, which
did not err in reducing the consequential damages from P333,200.00 to
results in loss or damage, the obligor cannot escape liability. The principle
P19,000.00; Reasons.—Likewise, it did not err in re-ducing the
embodied in the act of God doctrine strictly requires that the act must be
consequential damages from P333,200.00 to P19,000.00. As shown by the
one occasioned exclusively by the violence of nature and human agencies
records, while there was no categorical statement or admission on the part
are to be excluded from creating or entering into the cause of the mischief.
of ECI that it bought a new crane to replace the damaged one, a sales
When the effect, the cause of which is to be considered, is found to be in
contract was presented to the effect that the new crane would be delivered
part the result of the participation of man, whether it be from active
to it by Asian Enterprises within 60 days from the opening of the letter of
intervention or neglect, or failure to act, the whole occurrence is thereby
credit at the cost of P1 06,336.75. The offer was made by Asian Enterprises
humanized, as it was, and removed from the rules applicable to the acts of
a few days after the flood. As compared to the amount of P106,336.75 for a
brand new crane and paying the alleged amount of P4,000.00 a day as National Power Corporation (NPC) in G.R. No. 47379, questioning the
rental for the use of a temporary crane, which use petitioner ECI alleged decision of the Court of Appeals for holding it liable for damages and the
to have lasted for a period of one year, thus, totalling P1 20,000.00, plus Engineering Construction, Inc. (ECI) in G.R. No. 47481, questioning the
the fact that there was already a sales contract between it and Asian same decision for reducing the consequential damages and attorney's fees
Enterprises, there is no reason why ECI should opt to rent a temporary and for eliminating the exemplary damages.
crane for a period of one year. The appellate court also found that the
damaged crane was subsequently repaired and re-activated and the cost of The facts are succinctly summarized by the respondent Court of Appeals,
repair was as follows:
336
336 SUPREME COURT REPORTS ANNOTATED On August 4, 1964, plaintiff Engineering Construction,
National Power Corporation us. Court of Appeals Inc., being a successful bidder, executed a contract in
P77,000.00. Therefore, it included the said amount in the award of Manila with the National Waterworks and Sewerage
compensatory damages, but not the value of the new crane. We do not find Authority (NAWASA), whereby the former undertook to
anything erroneous in the decision of the appellate court that the furnish all tools, labor, equipment, and materials (not
consequential damages should represent only the service of the temporary furnished by Owner), and to construct the proposed 2nd
crane for one month. A contrary ruling would result in the unjust lpo-Bicti Tunnel, Intake and Outlet Structures, and
enrichment of ECI. Appurtenant Structures, and Appurtenant Features, at
Same; Same; Same; Same; Exemplary Damages; Appellate court is Norzagaray, Bulacan, and to complete said works within
correct in eliminating exemplary damages since there was no bad faith and eight hundred (800) calendar days from the date the
gross negligence on the part of NPC.—As to the question of exemplary Contractor receives the formal notice to proceed (Exh. A).
damages, we sustain the appellate court in eliminating the same since it
found that there was no bad faith on the part of NPC and that neither can The project involved two (2) major phases: the first phase
the latter’s negligence be considered gross. In Dee Hua Liong Electrical comprising, the tunnel work covering a distance of seven
Equipment Corp. v. Reyes, (145 SCRA 713, 719) we ruled: “Neither may (7) kilometers, passing through the mountain, from the
private respondent recover exemplary damages since he is not entitled to Ipo river, a part of Norzagaray, Bulacan, where the Ipo
moral or compensatory damages, and again because the petitioner is not Dam of the defendant National Power Corporation is
shown to have acted in a wanton, fraudulent, reckless or oppressive located, to Bicti; the other phase consisting of the
manner (Art. 2234, Civil Code; Yutuk v. Manila Electric Co., 2 SCRA 377; outworks at both ends of the tunnel.
Francisco v. Government Service Insurance System, 7 SCRA 577;
Gutierrez v. Villegas, 8 SCRA 527; Air France v. Carrascoso, 18 SCRA 155; By September 1967, the plaintiff corporation already had
Pan Pacific (Phil.) v. Phil. Advertising Corp., 23 SCRA 977; Marchan v. completed the first major phase of the work, namely, the
Mendoza, 24 SCRA 888)." tunnel excavation work. Some portions of the outworks at
PETITIONS to review the decision of the Court of Appeals. the Bicti site were still under construction. As soon as the
The facts are stated in the opinion of the Court. plaintiff corporation had finished the tunnel excavation
Raymundo A. Armovit for private respondent in L-47379. work at the Bicti site, all the equipment no longer needed
The Solicitor General for petitioner. there were transferred to the Ipo site where some projects
were yet to be completed.
GUTIERREZ, JR., J.:
The record shows that on November 4,1967, typhoon
These consolidated petitions seek to set aside the decision of the 'Welming' hit Central Luzon, passing through defendant's
respondent Court of Appeals which adjudged the National Power Angat Hydro-electric Project and Dam at lpo, Norzagaray,
Corporation liable for damages against Engineering Construction, Inc. Bulacan. Strong winds struck the project area, and heavy
The appellate court, however, reduced the amount of damages awarded rains intermittently fell. Due to the heavy downpour, the
by the trial court. Hence, both parties filed their respective petitions: the water in the reservoir of the Angat Dam was rising
perilously at the rate of sixty (60) centimeters per hour. which were all submitted as Exhibits K to M-38 a, N to O,
To prevent an overflow of water from the dam, since the P to U-2 and V to X- 60-a (Vide: Folders Nos. 1 to 4). The
water level had reached the danger height of 212 meters appellant did not submit proofs to traverse the
above sea level, the defendant corporation caused the aforementioned documentary evidence. We hold that the
opening of the spillway gates." (pp. 45-46, L-47379, Rollo) lower court did not commit any error in awarding P
675,785.31 as actual or compensatory damages.
The appellate court sustained the findings of the trial court that the
evidence preponlderantly established the fact that due to the negligent However, We cannot sustain the award of P333,200.00 as
manner with which the spillway gates of the Angat Dam were opened, an consequential damages. This amount is broken down as
extraordinary large volume of water rushed out of the gates, and hit the follows: P213,200.00 as and for the rentals of a crane to
installations and construction works of ECI at the lpo site with terrific temporarily replace the one "destroyed beyond repair,"
impact, as a result of which the latter's stockpile of materials and and P120,000.00 as one month bonus which the appellee
supplies, camp facilities and permanent structures and accessories either failed to realize in accordance with the contract which the
washed away, lost or destroyed. appellee had with NAWASA. Said rental of the crane
allegedly covered the period of one year at the rate of
The appellate court further found that: P40.00 an hour for 16 hours a day. The evidence, however,
shows that the appellee bought a crane also a crawler
It cannot be pretended that there was no negligence or type, on November 10, 1967, six (6) days after the incident
that the appellant exercised extraordinary care in the in question (Exh N) And according to the lower court,
opening of the spillway gates of the Angat Dam. which finding was never assailed, the appellee resumed
Maintainers of the dam knew very well that it was far its normal construction work on the Ipo- Bicti Project
more safe to open them gradually. But the spillway gates after a stoppage of only one month. There is no evidence
were opened only when typhoon Welming was already at when the appellee received the crane from the seller,
its height, in a vain effort to race against time and Asian Enterprise Limited. But there was an agreement
prevent the overflow of water from the dam as it 'was that the shipment of the goods would be effected within 60
rising dangerously at the rate of sixty centimeters per days from the opening of the letter of credit (Exh.
hour. 'Action could have been taken as early as November N).<äre||anº•1àw> It appearing that the contract of sale
3, 1967, when the water in the reservoir was still low. At was consummated, We must conclude or at least assume
that time, the gates of the dam could have been opened in that the crane was delivered to the appellee within 60
a regulated manner. Let it be stressed that the appellant days as stipulated. The appellee then could have availed
knew of the coming of the typhoon four days before it of the services of another crane for a period of only one
actually hit the project area. (p. 53, L-47379, Rollo) month (after a work stoppage of one month) at the rate of
P 40.00 an hour for 16 hours a day or a total of P
19,200.00 as rental.
As to the award of damages, the appellate court held:
On the other hand, ECI assails the reduction of the consequential Thus, it has been held that when the negligence of a
damages from P333,200.00 to P19,000.00 on the grounds that the person concurs with an act of God in producing a loss,
appellate court had no basis in concluding that ECI acquired a new such person is not exempt from liability by showing that
Crawler-type crane and therefore, it only can claim rentals for the the immediate cause of the damage was the act of God. To
temporary use of the leased crane for a period of one month; and that the be exempt from liability for loss because of an act of God,
award of P4,000.00 a day or P120,000.00 a month bonus is justified since he must be free from any previous negligence or
the period limitation on ECI's contract with NAWASA had dual effects, misconduct by which the loss or damage may have been
i.e., bonus for earlier completion and liquidated damages for delayed occasioned. (Fish & Elective Co. v. Phil. Motors, 55 Phil.
performance; and in either case at the rate of P4,000.00 daily. Thus, since 129; Tucker v. Milan 49 O.G. 4379; Limpangco & Sons v.
NPC's negligence compelled work stoppage for a period of one month, the Yangco Steamship Co., 34 Phil. 594, 604; Lasam v. Smith,
said award of P120,000.00 is justified. ECI further assailes the reduction 45 Phil. 657).
of attorney's fees and the total elimination of exemplary damages.
Furthermore, the question of whether or not there was negligence on the
Both petitions are without merit. part of NPC is a question of fact which properly falls within the
jurisdiction of the Court of Appeals and will not be disturbed by this
It is clear from the appellate court's decision that based on its findings of Court unless the same is clearly unfounded. Thus, in Tolentino v. Court of
fact and that of the trial court's, petitioner NPC was undoubtedly appeals, (150 SCRA 26, 36) we ruled:
negligent because it opened the spillway gates of the Angat Dam only at
the height of typhoon "Welming" when it knew very well that it was safer Moreover, the findings of fact of the Court of Appeals are
to have opened the same gradually and earlier, as it was also undeniable generally final and conclusive upon the Supreme Court
that NPC knew of the coming typhoon at least four days before it actually (Leonardo v. Court of Appeals, 120 SCRA 890 [1983]. In
struck. And even though the typhoon was an act of God or what we may fact it is settled that the Supreme Court is not supposed
call force majeure, NPC cannot escape liability because its negligence was to weigh evidence but only to determine its substantially
the proximate cause of the loss and damage. As we have ruled in Juan F. (Nuñez v. Sandiganbayan, 100 SCRA 433 [1982] and will
Nakpil & Sons v. Court of Appeals, (144 SCRA 596, 606-607): generally not disturb said findings of fact when supported
by substantial evidence (Aytona v. Court of Appeals, 113 presented in the records of these petitions. It is not shown that NAWASA
SCRA 575 [1985]; Collector of Customs of Manila v. imposed them.
Intermediate Appellate Court, 137 SCRA 3 [1985]. On the
other hand substantial evidence is defined as such As to the question of exemplary damages, we sustain the appellate court
relevant evidence as a reasonable mind might accept as in eliminating the same since it found that there was no bad faith on the
adequate to support a conclusion (Philippine Metal part of NPC and that neither can the latter's negligence be considered
Products, Inc. v. Court of Industrial Relations, 90 SCRA gross. In Dee Hua Liong Electrical Equipment Corp. v. Reyes, (145 SCRA
135 [1979]; Police Commission v. Lood, 127 SCRA 757 713, 719) we ruled:
[1984]; Canete v. WCC, 136 SCRA 302 [1985])
Neither may private respondent recover exemplary
Therefore, the respondent Court of Appeals did not err in holding the damages since he is not entitled to moral or compensatory
NPC liable for damages. damages, and again because the petitioner is not shown to
have acted in a wanton, fraudulent, reckless or oppressive
Likewise, it did not err in reducing the consequential damages from manner (Art. 2234, Civil Code; Yutuk v. Manila Electric
P333,200.00 to P19,000.00. As shown by the records, while there was no Co., 2 SCRA 377; Francisco v. Government Service
categorical statement or admission on the part of ECI that it bought a Insurance System, 7 SCRA 577; Gutierrez v. Villegas, 8
new crane to replace the damaged one, a sales contract was presented to SCRA 527; Air France v. Carrascoso, 18 SCRA 155; Pan
the effect that the new crane would be delivered to it by Asian Pacific (Phil.) v. Phil. Advertising Corp., 23 SCRA 977;
Enterprises within 60 days from the opening of the letter of credit at the Marchan v. Mendoza, 24 SCRA 888).
cost of P106,336.75. The offer was made by Asian Enterprises a few days
after the flood. As compared to the amount of P106,336.75 for a brand We also affirm the reduction of attorney's fees from P50,000.00 to
new crane and paying the alleged amount of P4,000.00 a day as rental for P30,000.00. There are no compelling reasons why we should set aside the
the use of a temporary crane, which use petitioner ECI alleged to have appellate court's finding that the latter amount suffices for the services
lasted for a period of one year, thus, totalling P120,000.00, plus the fact rendered by ECI's counsel.
that there was already a sales contract between it and Asian Enterprises,
there is no reason why ECI should opt to rent a temporary crane for a WHEREFORE, the petitions in G.R. No. 47379 and G.R. No. 47481 are
period of one year. The appellate court also found that the damaged crane both DISMISSED for LACK OF MERIT. The decision appealed from is
was subsequently repaired and reactivated and the cost of repair was AFFIRMED.
P77,000.00. Therefore, it included the said amount in the award of of
compensatory damages, but not the value of the new crane. We do not
SO ORDERED.
find anything erroneous in the decision of the appellate court that the
consequential damages should represent only the service of the
temporary crane for one month. A contrary ruling would result in the
unjust enrichment of ECI.
The P120,000.00 bonus was also properly eliminated as the same was
granted by the trial court on the premise that it represented ECI's lost
opportunity "to earn the one month bonus from NAWASA ... ." As stated
earlier, the loss or damage to ECI's equipment and facilities occurred long
after the stipulated deadline to finish the construction. No bonus,
therefore, could have been possibly earned by ECI at that point in time.
The supposed liquidated damages for failure to finish the project within
the stipulated period or the opposite of the claim for bonus is not clearly
No. L-44748. August 29, 1986 LOQUITUR (the thing speaks for itself), by considering the presence of
RADIO COMMUNICATIONS OF THE PHILS., INC. (RCPI), facts or circumstances surrounding the injury.
petitioner, vs. COURT OF APPEALS and LORETO DIONELA,
respondents. PETITION for review by certiorari of the decision of the Court of Appeals.
Civil Law; Damages; Breach of contract; Inclusion of extraneous and
libelous matter in telegraphic message constitutes breach of contract.— The facts are stated in the opinion of the Court.
Petitioner is a domestic corporation engaged in the business of receiving O. Pythogoras Oliver for respondents.
and transmitting messages. Everytime a person transmits a message
through the facilities of the petitioner, a contract is entered into. Upon PARAS, J.:
receipt of the rate or fee fixed, the petitioner undertakes to transmit the
message accurately. There is no question that in the case at bar, libelous Before Us, is a Petition for Review by certiorari of the decision of the
matters were included in the message transmitted, without the consent or Court of Appeals, modifying the decision of the trial court in a civil case
knowledge of the for recovery of damages against petitioner corporation by reducing the
_________________ award to private respondent Loreto Dionela of moral damages from
P40,000 to Pl5,000, and attorney's fees from P3,000 to P2,000.
*SECOND DIVISION.
658
The basis of the complaint against the defendant corporation is a
658 SUPREME COURT REPORTS ANNOTATED telegram sent through its Manila Office to the offended party, Loreto
Radio Communications of the Philippines, Inc. vs. Court of Dionela, reading as follows:
Appeals
sender. There is a clear case of breach of contract by the petitioner in 176 AS JR 1215PM 9 PAID MANDALUYONG JUL 22-66
adding extraneous and libelous matters in the message sent to the private LORETO DIONELA CABANGAN LEGASPI CITY
respondent.
Same; Same; Same; Same; Telegraph corporation, as employer is WIRE ARRIVAL OF CHECK FER
liable directly for the acts of its employees; Action based on Arts. 19 and 20
of the Civil Code, not on subsidiary liability of corporation under Article LORETO DIONELA-CABANGAN-WIRE ARRIVAL OF
1161, New Civil Code.—As a corporation, the petitioner can act only CHECK-PER
through its employees. Hence the acts of its employees in receiving and
transmitting messages are the acts of the petitioner. To hold that the
115 PM
petitioner is not liable directly for the acts of its employees in the pursuit
of petitioner’s business is to deprive the general public availing of the
services of the petitioner of an effective and adequate remedy. The action SA IYO WALANG PAKINABANG DUMATING KA
for damages was filed in the lower court directly against respondent DIYAN-WALA-KANG PADALA DITO KAHIT BULBUL
MO
corporation not as an employer subsidiarily liable under the provisions of
Article 1161 of the New Civil Code in relation to Art. 103 of the Revised
Penal Code. The cause of action of the private respondent is based on Arts. (p. 19, Annex "A")
19 and 20 of the New Civil Code (supra). As well as on respondent’s breach
of contract thru the negligence of its own employees. Plaintiff-respondent Loreto Dionela alleges that the defamatory words on
Same; Same; Same; Same; Res ipsa loquitur; Since negligence may be the telegram sent to him not only wounded his feelings but also caused
hard to substantiate in some cases, the application of the doctrine of res ipsa him undue embarrassment and affected adversely his business as well
loquitur is proper; Case at bar.—In most cases, negligence must be proved because other people have come to know of said defamatory words.
in order that plaintiff may recover. However, since negligence may be hard Defendant corporation as a defense, alleges that the additional words in
to substantiate in some cases, we may apply the doctrine of RES IPSA Tagalog was a private joke between the sending and receiving operators
and that they were not addressed to or intended for plaintiff and
therefore did not form part of the telegram and that the Tagalog words metal fastener. Moreover, they are open to view and
are not defamatory. The telegram sent through its facilities was received inspection by third parties.
in its station at Legaspi City. Nobody other than the operator manned the
teletype machine which automatically receives telegrams being It follows that the plaintiff is entitled to damages and
transmitted. The said telegram was detached from the machine and attorney's fees. The plaintiff is a businessman. The
placed inside a sealed envelope and delivered to plaintiff, obviously as is. libelous Tagalog words must have affected his business
The additional words in Tagalog were never noticed and were included in and social standing in the community. The Court fixes the
the telegram when delivered. amount of P40,000.00 as the reasonable amount of moral
damages and the amount of P3,000.00 as attorney's fee
The trial court in finding for the plaintiff ruled as follows: which the defendant should pay the plaintiff. (pp. 15-16,
Record on Appeal)
There is no question that the additional words in Tagalog
are libelous. They clearly impute a vice or defect of the The respondent appellate court in its assailed decision confirming the
plaintiff. Whether or not they were intended for the aforegoing findings of the lower court stated:
plaintiff, the effect on the plaintiff is the same. Any
person reading the additional words in Tagalog will The proximate cause, therefore, resulting in injury to
naturally think that they refer to the addressee, the appellee, was the failure of the appellant to take the
plaintiff. There is no indication from the face of the necessary or precautionary steps to avoid the occurrence
telegram that the additional words in Tagalog were sent of the humiliating incident now complained of. The
as a private joke between the operators of the defendant. company had not imposed any safeguard against such
eventualities and this void in its operating procedure does
The defendant is sued directly not as an employer. The not speak well of its concern for their clientele's interests.
business of the defendant is to transmit telegrams. It will Negligence here is very patent. This negligence is
open the door to frauds and allow the defendant to act imputable to appellant and not to its employees.
with impunity if it can escape liability by the simple
expedient of showing that its employees acted beyond the The claim that there was no publication of the libelous
scope of their assigned tasks. words in Tagalog is also without merit. The fact that a
carbon copy of the telegram was filed among other
The liability of the defendant is predicated not only on telegrams and left to hang for the public to see, open for
Article 33 of the Civil Code of the Philippines but on the inspection by a third party is sufficient publication. It
following articles of said Code: would have been otherwise perhaps had the telegram
been placed and kept in a secured place where no one may
ART. 19.- Every person must, in the exercise of his rights have had a chance to read it without appellee's
and in the performance of his duties, act with justice, give permission.
everyone his due, and observe honesty and good faith.
The additional Tagalog words at the bottom of the
ART. 20.-Every person who, contrary to law, wilfully or telegram are, as correctly found by the lower court,
negligently causes damage to another, shall indemnify the libelous per se, and from which malice may be presumed
latter for the same. in the absence of any showing of good intention and
justifiable motive on the part of the appellant. The law
There is sufficient publication of the libelous Tagalog implies damages in this instance (Quemel vs. Court of
words. The office file of the defendant containing copies of Appeals, L-22794, January 16, 1968; 22 SCRA 44). The
telegrams received are open and held together only by a award of P40,000.00 as moral damages is hereby reduced
to P15,000.00 and for attorney's fees the amount of Petitioner is a domestic corporation engaged in the business of receiving
P2,000.00 is awarded. (pp. 22-23, record) and transmitting messages. Everytime a person transmits a message
through the facilities of the petitioner, a contract is entered into. Upon
After a motion for reconsideration was denied by the appellate court, receipt of the rate or fee fixed, the petitioner undertakes to transmit the
petitioner came to Us with the following: message accurately. There is no question that in the case at bar, libelous
matters were included in the message transmitted, without the consent
ASSIGNMENT OF ERRORS or knowledge of the sender. There is a clear case of breach of contract by
the petitioner in adding extraneous and libelous matters in the message
sent to the private respondent. As a corporation, the petitioner can act
I
only through its employees. Hence the acts of its employees in receiving
and transmitting messages are the acts of the petitioner. To hold that the
The Honorable Court of Appeals erred in holding that petitioner is not liable directly for the acts of its employees in the pursuit
Petitioner-employer should answer directly and primarily of petitioner's business is to deprive the general public availing of the
for the civil liability arising from the criminal act of its services of the petitioner of an effective and adequate remedy. In most
employee. cases, negligence must be proved in order that plaintiff may recover.
However, since negligence may be hard to substantiate in some cases, we
II may apply the doctrine of RES IPSA LOQUITUR (the thing speaks for
itself), by considering the presence of facts or circumstances surrounding
The Honorable Court of Appeals erred in holding that the injury.
there was sufficient publication of the alleged libelous
telegram in question, as contemplated by law on libel. WHEREFORE, premises considered, the judgment of the appellate court
is hereby AFFIRMED.
III
SO ORDERED.
The Honorable Court of Appeals erred in holding that the
liability of petitioner-company-employer is predicated on
Articles 19 and 20 of the Civil Code, Articles on Human
Relations.
IV
7. That the plaintiff received notice of the fact that the 11. That it being normal business practice in case of
defendant accepted plaintiff's offer to sell to the defendant foreign importation that the buyer opens a letter of credit
the items specified in Annex 'A', as well as the terms and in favor of the foreign supplier before delivery of the goods
conditions of said offer, as shown by the signed conformity sold, the plaintiff herein awaited the opening of such a
of the defendant appearing on Annex 'A' which was duly letter of credit by the defendant;
delivered by the defendant's agent to the plaintiff herein,
whereupon all that the plaintiff had to do in the 12. That the defendant and his agent have repeatedly
meantime was to await advice from the defendant as to assured plaintiff herein of the defendant's financial
the radio frequency to be assigned by the proper capabilities to pay for the goods ordered by him and in
authorities to the defendant; fact he accomplished the necessary application for a letter
of credit with his banker, but he subsequently instructed
8. That believing that the defendant would faithfully his banker not to give due course to his application for a
fulfill his contract with the plaintiff herein, considering letter of credit and that for reasons only known to the
his signed conformity appearing in Annex 'A' hereof as defendant, he fails and refuses to open the necessary
letter of credit to cover payment of the goods ordered by transceivers were purposely made or
him; manufactured solely for the use of the
defendant herein and cannot possibly be
13. That it has come to the knowledge of the plaintiff marketed by the plaintiff herein to the
herein that the defendant has been operating his taxicabs general public;
without the required radio transceivers and when the
U.S. Navy Authorities of Subic Bay, Philippines, were [b] The amount of P 52,393.89 or 10% of
pressing defendant for compliance with his commitments the purchase price by way of loss of
with respect to the installations of radio transceivers on expected profits from the transaction or
his taxicabs, he impliedly laid the blame for the delay contract between plaintiff and the
upon the plaintiff herein, thus destroying the reputation defendant;
of the plaintiff herein with the said Naval Authorities of
Subic Bay, Philippines, with whom plaintiff herein [c] Loss of confidence in him and goodwill
transacts business; of the plaintiff which will result in the
impairment of his business dealings with
14. That on March 27, 1973, plaintiff wrote a letter thru Japanese firms, thereby resulting also in
his counsel, copy attached marked as Annex 'E', to loss of possible profits in the future which
ascertain from the defendant as to whether it is his plaintiff assess at no less than
intention to fulfill his part of the agreement with the P200,000.00;
plaintiff herein or whether he desired to have the contract
between them definitely cancelled, but defendant did not [d] That in view of the defendant's bad
even have the courtesy to answer plaintiff's demand; faith in inducing plaintiff to enter into the
contract with him as set forth
15. That the defendant herein entered into a contract with hereinabove, defendant should be assessed
the plaintiff herein as set forth in Annex 'A' without the by his Honorable Court in favor of the
least intention of faithfully complying with his obligation plaintiff the sum of P200,000.00 as moral
is thereunder, but he did so only in order to obtain the and exemplary damages;
concession from the U.S. Navy Exchange, Subic Bay,
Philippines, of operating a fleet of taxicabs inside the U.S. [e] That in view of the defendant's fault
Naval Base to his financial benefit and at the expense and and to protect his interests, plaintiff
prejudice of third parties such as the plaintiff herein; herein is constrained to retain the services
of counsel with whom he agreed to pay by
16. That in view of the defendant's failure to fulfill his way of attorney's fees the sum of
contractual obligations with the plaintiff herein, the P50,000.00".
plaintiff will suffer the following damages:
Respondent Guerrero filed a motion to dismiss said complaint for lack of
[a] As the radio transceivers ordered by cause of action, which ground is propounded by respondent's counsel
the defendant are now in the hands of the thus: 2
plaintiff's Japanese representative, the
plaintiff will have to pay for them, thus he ... it is clear that plaintiff was merely anticipating his loss
will have to suffer as total loss to him the or damage which might result from the alleged failure of
amount of P523,938.98 (converting the defendant to comply with the terms of the alleged
amount of $77,620.59 to pesos at the rate contract. Hence, plaintiff's right of recovery under his
of P6.75 to the dollar) as said radio
cause of action is premised not on any loss or damage allegations, the essential elements of a cause of action are present, to wit:
actually suffered by him but on a non-existing loss or [1] the existence of a legal right to the plaintiff; [2] a correlative duty of
damage which he is expecting to incur in the near future. the defendant and [3] an act or omission of the defendant in violation of
Plaintiff's right therefore under his cause of action is not the plaintiff's right, with consequent injury or damage to the latter for
yet fixed or vested. which he may maintain an action for recovery of damages or other
appropriate relief. 7
Inasmuch as there is no other allegation in the present
Complaint wherein the same could be maintained against Indisputably, the parties, both businessmen, entered into the aforesaid
defendant, the present Complaint should be dismissed for contract with the evident intention of deriving some profits therefrom.
its failure to state a cause of action against defendant. Upon breach of the contract by either of them, the other would
necessarily suffer loss of his expected profits. Since the loss comes into
The respondent judge, over petitioner's opposition, issued a minute order being at the very moment of breach, such loss is real, "fixed and vested"
dismissing the complaint as follows:3 and, therefore, recoverable under the law.
Acting upon the 'Motion to Dismiss' filed by the Article 1170 of the Civil Code provides:
defendant, through counsel, dated June 7, 1973, as well as
the opposition thereto filed by the plaintiff, through Those who in the performance of their obligation are
counsel, dated June 14, 1973, for the reasons therein guilty of fraud, negligence, or delay, and those who in any
alleged, this Court hereby grants said motion and, as manner contravene the tenor thereof are liable for
prayed for, the complaint in the above-entitled case is damages.
dismissed.
The phrase "in any manner contravene the tenor" of the obligation
SO ORDERED. includes any ilicit act or omission which impairs the strict and faithful
fulfillment of the obligation and every kind of defective performance. 8
Both parties are in accord with the view that when a motion to dismiss is
based on the ground of lack of cause of action, the sufficiency of the case The damages which the obligor is liable for includes not only the value of
of action can only be determined on the basis of the facts alleged in the the loss suffered by the obligee [daño emergente] but also the profits
complaint 4 ; that the facts alleged are deemed hypothetically admitted, which the latter failed to obtain [lucro cesante] 9. If the obligor acted in
including those which are fairly deducible therefrom 5 ; and that, good faith, he shall be liable for those damages that are the natural and
admitting the facts as alleged, whether or not the Court can render a probable consequences of the breach of the obligation and which the
valid judgment against the defendant upon said facts in accordance with parties have foreseen or could have reasonably foreseen at the time the
the prayer in the complaint 6. obligation was constituted; and in case of fraud, bad faith, malice or
wanton attitude, he shall be liable for all damages which may be
After a thorough examination of the complaint at bar, We find the test of reasonably attributed to the non-performance of the obligation 10.
legal sufficiency of the cause of action adequately satisfied. In a
methodical and logical sequence, the complaints recites the circumstances The same is true with respect to moral and exemplary damages. The
that led to the perfection of the contract entered into by the parties. It applicable legal provisions on the matter, Articles 2220 and 2232 of the
further avers that while petitioner had fulfilled his part of the bargain Civil Code, allow the award of such damages in breaches of contract
[paragraph 8 of the Complaint], private respondent failed to comply with where the defendant acted in bad faith. To Our mind, the complaint
his correlative obligation by refusing to open a letter of credit to cover sufficiently alleges bad faith on the part of the defendant.
payment of the goods ordered by him [paragraphs 11 & 12 of the
Complaint], and that consequently, petitioner suffered not only loss of his
expected profits, but moral and exemplary damages as well. From these
In fine, We hold that on the basis of the facts alleged in the complaint, the construction, and the architect made plans that contain defects and
court could render a valid judgment in accordance with the prayer inadequacies, both contractor and architect cannot escape liability for
thereof. damages sustained by the building that collapsed in the wake of an
earthquake on Aug. 2, 1968.—The negligence of the defendant and the
ACCORDINGLY, the questioned order of dismissal is hereby set aside third-party defendants petitioners was established beyond dispute both in
and the case ordered remanded to the court of origin for further the lower court and in the Intermediate Appellate Court. Defendant United
proceedings. No costs. Construction Co., Inc. was found to have made substantial deviations from
the plans and specifications, and to have failed to observe the requisite
SO ORDERED. workmanship in the construction as well as to exercise the requisite degree
of supervision; while the
_______________
*SECOND DIVISION.
G.R. No. L-47851 October 3, 1986 597
VOL. 144, OCTOBER 3, 1986 597
JUAN F. NAKPIL & SONS, and JUAN F. NAKPIL, petitioners,
vs. Juan F. Nakpil & Sons vs. Court of Appeals
THE COURT OF APPEALS, UNITED CONSTRUCTION third-party defendants were found to have inadequacies or defects in
COMPANY, INC., JUAN J. CARLOS, and the PHILIPPINE BAR the plans and specifications prepared by them. As correctly assessed by
ASSOCIATION, respondents. both courts, the defects in the construction and in the plans and
specifications were the proximate causes that rendered the PBA building
unable to withstand the earthquake of August 2, 1968. For this reason the
G.R. No. L-47863 October 3, 1986
defendant and third-party defendants cannot claim exemption from
liability.
THE UNITED CONSTRUCTION CO., INC., petitioner, Same; Same; Fact that all other buildings withstood the earthquake,
vs. except the one at bar, cannot be ignored.—In any event, the relevant and
COURT OF APPEALS, ET AL., respondents. logical observations of the trial court as affirmed by the Court of Appeals
that “while it is not possible to state with certainty that the building would
G.R. No. L-47896 October 3, 1986 not have collapsed were those defects not present, the fact remains that
several buildings in the same area withstood the earthquake to which the
PHILIPPINE BAR ASSOCIATION, ET AL., petitioners, building of the plaintiff was similarly subjected,” cannot be ignored.
vs. Same; Same; The lower courts found, among others, that spirals in
COURT OF APPEALS, ET AL., respondents. column A5, ground floor were cut.—The cutting of the spirals in column A5,
ground floor is the subject of great contention between the parties and
Obligations and Contracts; Damages; Requisites for exemption from deserves special consideration. The proper placing of the main
liability due to an “act of God.”—To exempt the obligor from liability under reinforcements and spirals in column A5, ground floor, is the responsibility
Article 1174 of the Civil Code, for a breach of an obligation due to an “act of the general contractor which is the UCCI. The burden of proof, therefore,
of God,’ the following must concur: (a) the cause of the breach of the that this cutting was done by others is upon the defendants. Other than a
obligation must be independent of the will of the debtor; (b) the event must strong allegation and assertion that it is the plumber or his men who may
be either unforseeable or unavoidable; (c) the event must be such as to have done the cutting (and this was flatly denied by the plumber) no
render it impossible for the debtor to fulfill his obligation in a normal conclusive proof was presented. The engineering experts for the defendants
manner; and (d) the debtor must be free from any participation in, or asserted that they could have no motivation for cutting the bar because
aggravation of the injury to the creditor. they can simply replace the spirals by wrapping around a new set of spirals.
Same; Same; Having made substantial deviations from plans and This is not quite correct. There is evidence to show that the pouring of
specifications, having failed to observe requisite workmanship in concrete for columns was sometimes done through the beam and girder
reinforcements which were already in place as in the case of column A4 mentioned amounts from finality until paid. Solidary costs against the
second floor. If the reinforcement for the girder and column is to defendant and third-party defendants (except Roman Ozaeta).
subsequently wrap around the spirals, this would not do for the elasticity
of steel would prevent the making of tight column spirals and loose or PETITIONS for certiorari to review the decision of the Court of Appeals.
improper spirals would result. The proper way is to produce correct spirals
down from the top of the main column bars, a procedure which can not be The facts are stated in the opinion of the Court.
done if either the beam or girder reinforcement is already in place. The
engineering experts for the defendants strongly assert and apparently PARAS, J.:
believe that the cutting of the spirals did not materially diminish the
strength of the column. This belief together with the difficulty of slipping These are petitions for review on certiorari of the November 28, 1977
the spirals on the decision of the Court of Appeals in CA-G.R. No. 51771-R modifying the
598 decision of the Court of First Instance of Manila, Branch V, in Civil Case
598 SUPREME COURT REPORTS ANNOTATED No. 74958 dated September 21, 1971 as modified by the Order of the
Juan F. Nakpil & Sons vs. Court of Appeals lower court dated December 8, 1971. The Court of Appeals in modifying
top of the column once the beam reinforcement is in place may be a the decision of the lower court included an award of an additional amount
sufficient motivation for the cutting of the spirals themselves. The of P200,000.00 to the Philippine Bar Association to be paid jointly and
defendants, therefore, should be held responsible for the consequences severally by the defendant United Construction Co. and by the third-
arising from the loss of strength or ductility in column A5 which may have party defendants Juan F. Nakpil and Sons and Juan F. Nakpil.
contributed to the damages sustained by the building.
Same; Same; One who creates a dangerous condition cannot escape The dispositive portion of the modified decision of the lower court reads:
liability although an act of God may have intervened.—Relative thereto,
the ruling of the Supreme Court in Tucker v. Milan (49 O.G. 4379, 4380) WHEREFORE, judgment is hereby rendered:
which may be in point in this case, reads: “One who negligently creates a
dangerous condition cannot escape liability for the natural and probable (a) Ordering defendant United Construction Co., Inc. and
consequences thereof, although the act of a third person, or an act of God third-party defendants (except Roman Ozaeta) to pay the
for which he is not responsible, intervenes to precipitate the loss.” As plaintiff, jointly and severally, the sum of P989,335.68
already discussed, the destruction was not purely an act of God. Truth to with interest at the legal rate from November 29, 1968,
tell hundreds of ancient buildings in the vicinity were hardly affected by the date of the filing of the complaint until full payment;
the earthquake. Only one thing spells out the fatal difference; gross
negligence and evident bad faith, without which the damage would not
(b) Dismissing the complaint with respect to defendant
have occurred.
Juan J. Carlos;
Same: Same; Liability of architect and contractor for collapse of
building is solidary.—WHEREFORE, the decision appealed from is hereby
MODIFIED and considering the special and environmental circumstances (c) Dismissing the third-party complaint;
of this case, We deem it reasonable to render a decision imposing, as We do
hereby impose, upon the defendant and the third-party defendants (with (d) Dismissing the defendant's and third-party
the exception of Roman Ozaeta) a solidary (Art. 1723, Civil Code, Supra, p. defendants' counterclaims for lack of merit;
10) indemnity in favor of the Philippine Bar Association of FIVE MILLION
(P5,000,000.00) Pesos to cover all damages (with the exception of attorney’s (e) Ordering defendant United Construction Co., Inc. and
fees) occasioned by the loss of the building (including interest charges and third-party defendants (except Roman Ozaeta) to pay the
lost rentals) and an additional ONE HUNDRED THOUSAND costs in equal shares.
(P100,000.00) Pesos as and for attorney’s fees, the total sum being payable
upon the finality of this decision. Upon failure to pay on such finality, SO ORDERED. (Record on Appeal p. 521; Rollo, L- 47851,
twelve (12%) per cent interest per annum shall be imposed upon afore- p. 169).
The dispositive portion of the decision of the Court of Appeals reads: the other third-party defendants Juan F. Nakpil & Sons. The building
was completed in June, 1966.
WHEREFORE, the judgment appealed from is modified to
include an award of P200,000.00 in favor of plaintiff- In the early morning of August 2, 1968 an unusually strong earthquake
appellant Philippine Bar Association, with interest at the hit Manila and its environs and the building in question sustained major
legal rate from November 29, 1968 until full payment to damage. The front columns of the building buckled, causing the building
be paid jointly and severally by defendant United to tilt forward dangerously. The tenants vacated the building in view of
Construction Co., Inc. and third party defendants (except its precarious condition. As a temporary remedial measure, the building
Roman Ozaeta). In all other respects, the judgment dated was shored up by United Construction, Inc. at the cost of P13,661.28.
September 21, 1971 as modified in the December 8, 1971
Order of the lower court is hereby affirmed with COSTS On November 29, 1968, the plaintiff commenced this action for the
to be paid by the defendant and third party defendant recovery of damages arising from the partial collapse of the building
(except Roman Ozaeta) in equal shares. against United Construction, Inc. and its President and General Manager
Juan J. Carlos as defendants. Plaintiff alleges that the collapse of the
SO ORDERED. building was accused by defects in the construction, the failure of the
contractors to follow plans and specifications and violations by the
Petitioners Juan F. Nakpil & Sons in L-47851 and United Construction defendants of the terms of the contract.
Co., Inc. and Juan J. Carlos in L-47863 seek the reversal of the decision of
the Court of Appeals, among other things, for exoneration from liability Defendants in turn filed a third-party complaint against the architects
while petitioner Philippine Bar Association in L-47896 seeks the who prepared the plans and specifications, alleging in essence that the
modification of aforesaid decision to obtain an award of P1,830,000.00 for collapse of the building was due to the defects in the said plans and
the loss of the PBA building plus four (4) times such amount as damages specifications. Roman Ozaeta, the then president of the plaintiff Bar
resulting in increased cost of the building, P100,000.00 as exemplary Association was included as a third-party defendant for damages for
damages; and P100,000.00 as attorney's fees. having included Juan J. Carlos, President of the United Construction Co.,
Inc. as party defendant.
These petitions arising from the same case filed in the Court of First
Instance of Manila were consolidated by this Court in the resolution of On March 3, 1969, the plaintiff and third-party defendants Juan F.
May 10, 1978 requiring the respective respondents to comment. (Rollo, L- Nakpil & Sons and Juan F. Nakpil presented a written stipulation which
47851, p. 172). reads:
The facts as found by the lower court (Decision, C.C. No. 74958; Record on 1. That in relation to defendants' answer with
Appeal, pp. 269-348; pp. 520-521; Rollo, L-47851, p. 169) and affirmed by counterclaims and third- party complaints and the third-
the Court of Appeals are as follows: party defendants Nakpil & Sons' answer thereto, the
plaintiff need not amend its complaint by including the
The plaintiff, Philippine Bar Association, a civic-non-profit association, said Juan F. Nakpil & Sons and Juan F. Nakpil
incorporated under the Corporation Law, decided to construct an office personally as parties defendant.
building on its 840 square meters lot located at the comer of Aduana and
Arzobispo Streets, Intramuros, Manila. The construction was undertaken 2. That in the event (unexpected by the undersigned) that
by the United Construction, Inc. on an "administration" basis, on the the Court should find after the trial that the above-named
suggestion of Juan J. Carlos, the president and general manager of said defendants Juan J. Carlos and United Construction Co.,
corporation. The proposal was approved by plaintiff's board of directors Inc. are free from any blame and liability for the collapse
and signed by its president Roman Ozaeta, a third-party defendant in of the PBA Building, and should further find that the
this case. The plans and specifications for the building were prepared by collapse of said building was due to defects and/or
inadequacy of the plans, designs, and specifications p by (d) The alleged failure to exercise the requisite degree of
the third-party defendants, or in the event that the Court supervision expected of the architect, the contractor
may find Juan F. Nakpil and Sons and/or Juan F. Nakpil and/or the owner of the building;
contributorily negligent or in any way jointly and
solidarily liable with the defendants, judgment may be (e) An act of God or a fortuitous event; and
rendered in whole or in part. as the case may be, against
Juan F. Nakpil & Sons and/or Juan F. Nakpil in favor of (f) Any other cause not herein above specified.
the plaintiff to all intents and purposes as if plaintiff's
complaint has been duly amended by including the said
2. If the cause of the damage suffered by the building
Juan F. Nakpil & Sons and Juan F. Nakpil as parties
arose from a combination of the above-enumerated
defendant and by alleging causes of action against them
factors, the degree or proportion in which each individual
including, among others, the defects or inadequacy of the
factor contributed to the damage sustained;
plans, designs, and specifications prepared by them
and/or failure in the performance of their contract with
plaintiff. 3. Whether the building is now a total loss and should be
completely demolished or whether it may still be repaired
and restored to a tenantable condition. In the latter case,
3. Both parties hereby jointly petition this Honorable
the determination of the cost of such restoration or repair,
Court to approve this stipulation. (Record on Appeal, pp.
and the value of any remaining construction, such as the
274-275; Rollo, L-47851,p.169).
foundation, which may still be utilized or availed of
(Record on Appeal, pp. 275-276; Rollo, L-47851, p. 169).
Upon the issues being joined, a pre-trial was conducted on March 7, 1969,
during which among others, the parties agreed to refer the technical
Thus, the issues of this case were divided into technical issues and non-
issues involved in the case to a Commissioner. Mr. Andres O. Hizon, who
technical issues. As aforestated the technical issues were referred to the
was ultimately appointed by the trial court, assumed his office as
Commissioner. The non-technical issues were tried by the Court.
Commissioner, charged with the duty to try the following issues:
Meanwhile, plaintiff moved twice for the demolition of the building on the
1. Whether the damage sustained by the PBA building
ground that it may topple down in case of a strong earthquake. The
during the August 2, 1968 earthquake had been caused,
motions were opposed by the defendants and the matter was referred to
directly or indirectly, by:
the Commissioner. Finally, on April 30, 1979 the building was authorized
to be demolished at the expense of the plaintiff, but not another
(a) The inadequacies or defects in the plans and earthquake of high intensity on April 7, 1970 followed by other strong
specifications prepared by third-party defendants; earthquakes on April 9, and 12, 1970, caused further damage to the
property. The actual demolition was undertaken by the buyer of the
(b) The deviations, if any, made by the defendants from damaged building. (Record on Appeal, pp. 278-280; Ibid.)
said plans and specifications and how said deviations
contributed to the damage sustained; After the protracted hearings, the Commissioner eventually submitted
his report on September 25, 1970 with the findings that while the damage
(c) The alleged failure of defendants to observe the sustained by the PBA building was caused directly by the August 2, 1968
requisite quality of materials and workmanship in the earthquake whose magnitude was estimated at 7.3 they were also caused
construction of the building; by the defects in the plans and specifications prepared by the third-party
defendants' architects, deviations from said plans and specifications by
the defendant contractors and failure of the latter to observe the requisite
workmanship in the construction of the building and of the contractors,
architects and even the owners to exercise the requisite degree of damage to the building, still the deficiency in the original design and jack
supervision in the construction of subject building. of specific provisions against torsion in the original plans and the
overload on the ground floor columns (found by an the experts including
All the parties registered their objections to aforesaid findings which in the original designer) certainly contributed to the damage which
turn were answered by the Commissioner. occurred. (Ibid, p. 174).
The trial court agreed with the findings of the Commissioner except as to In their respective briefs petitioners, among others, raised the following
the holding that the owner is charged with full nine supervision of the assignments of errors: Philippine Bar Association claimed that the
construction. The Court sees no legal or contractual basis for such measure of damages should not be limited to P1,100,000.00 as estimated
conclusion. (Record on Appeal, pp. 309-328; Ibid). cost of repairs or to the period of six (6) months for loss of rentals while
United Construction Co., Inc. and the Nakpils claimed that it was an act
Thus, on September 21, 1971, the lower court rendered the assailed of God that caused the failure of the building which should exempt them
decision which was modified by the Intermediate Appellate Court on from responsibility and not the defective construction, poor workmanship,
November 28, 1977. deviations from plans and specifications and other imperfections in the
case of United Construction Co., Inc. or the deficiencies in the design,
plans and specifications prepared by petitioners in the case of the
All the parties herein appealed from the decision of the Intermediate
Nakpils. Both UCCI and the Nakpils object to the payment of the
Appellate Court. Hence, these petitions.
additional amount of P200,000.00 imposed by the Court of Appeals. UCCI
also claimed that it should be reimbursed the expenses of shoring the
On May 11, 1978, the United Architects of the Philippines, the building in the amount of P13,661.28 while the Nakpils opposed the
Association of Civil Engineers, and the Philippine Institute of Architects payment of damages jointly and solidarity with UCCI.
filed with the Court a motion to intervene as amicus curiae. They
proposed to present a position paper on the liability of architects when a
The pivotal issue in this case is whether or not an act of God-an
building collapses and to submit likewise a critical analysis with
unusually strong earthquake-which caused the failure of the building,
computations on the divergent views on the design and plans as
exempts from liability, parties who are otherwise liable because of their
submitted by the experts procured by the parties. The motion having
negligence.
been granted, the amicus curiae were granted a period of 60 days within
which to submit their position.
The applicable law governing the rights and liabilities of the parties
herein is Article 1723 of the New Civil Code, which provides:
After the parties had all filed their comments, We gave due course to the
petitions in Our Resolution of July 21, 1978.
Art. 1723. The engineer or architect who drew up the
plans and specifications for a building is liable for
The position papers of the amicus curiae (submitted on November 24,
damages if within fifteen years from the completion of the
1978) were duly noted.
structure the same should collapse by reason of a defect in
those plans and specifications, or due to the defects in the
The amicus curiae gave the opinion that the plans and specifications of ground. The contractor is likewise responsible for the
the Nakpils were not defective. But the Commissioner, when asked by Us damage if the edifice fags within the same period on
to comment, reiterated his conclusion that the defects in the plans and account of defects in the construction or the use of
specifications indeed existed. materials of inferior quality furnished by him, or due to
any violation of the terms of the contract. If the engineer
Using the same authorities availed of by the amicus curiae such as the or architect supervises the construction, he shall be
Manila Code (Ord. No. 4131) and the 1966 Asep Code, the Commissioner solidarily liable with the contractor.
added that even if it can be proved that the defects in
the constructionalone (and not in the plans and design) caused the
Acceptance of the building, after completion, does not whole occurrence is thereby humanized, as it were, and removed from the
imply waiver of any of the causes of action by reason of rules applicable to the acts of God. (1 Corpus Juris, pp. 1174-1175).
any defect mentioned in the preceding paragraph.
Thus it has been held that when the negligence of a person concurs with
The action must be brought within ten years following the an act of God in producing a loss, such person is not exempt from liability
collapse of the building. by showing that the immediate cause of the damage was the act of God.
To be exempt from liability for loss because of an act of God, he must be
On the other hand, the general rule is that no person shall be responsible free from any previous negligence or misconduct by which that loss or
for events which could not be foreseen or which though foreseen, were damage may have been occasioned. (Fish & Elective Co. v. Phil. Motors,
inevitable (Article 1174, New Civil Code). 55 Phil. 129; Tucker v. Milan, 49 O.G. 4379; Limpangco & Sons v. Yangco
Steamship Co., 34 Phil. 594, 604; Lasam v. Smith, 45 Phil. 657).
An act of God has been defined as an accident, due directly and
exclusively to natural causes without human intervention, which by no The negligence of the defendant and the third-party defendants
amount of foresight, pains or care, reasonably to have been expected, petitioners was established beyond dispute both in the lower court and in
could have been prevented. (1 Corpus Juris 1174). the Intermediate Appellate Court. Defendant United Construction Co.,
Inc. was found to have made substantial deviations from the plans and
There is no dispute that the earthquake of August 2, 1968 is a fortuitous specifications. and to have failed to observe the requisite workmanship in
event or an act of God. the construction as well as to exercise the requisite degree of supervision;
while the third-party defendants were found to have inadequacies or
defects in the plans and specifications prepared by them. As correctly
To exempt the obligor from liability under Article 1174 of the Civil Code,
assessed by both courts, the defects in the construction and in the plans
for a breach of an obligation due to an "act of God," the following must
and specifications were the proximate causes that rendered the PBA
concur: (a) the cause of the breach of the obligation must be independent
building unable to withstand the earthquake of August 2, 1968. For this
of the will of the debtor; (b) the event must be either unforseeable or
reason the defendant and third-party defendants cannot claim exemption
unavoidable; (c) the event must be such as to render it impossible for the
from liability. (Decision, Court of Appeals, pp. 30-31).
debtor to fulfill his obligation in a normal manner; and (d) the debtor
must be free from any participation in, or aggravation of the injury to the
creditor. (Vasquez v. Court of Appeals, 138 SCRA 553; Estrada v. It is well settled that the findings of facts of the Court of Appeals are
Consolacion, 71 SCRA 423; Austria v. Court of Appeals, 39 SCRA 527; conclusive on the parties and on this court (cases cited in Tolentino vs. de
Republic of the Phil. v. Luzon Stevedoring Corp., 21 SCRA 279; Lasam v. Jesus, 56 SCRA 67; Cesar vs. Sandiganbayan, January 17, 1985, 134
Smith, 45 Phil. 657). SCRA 105, 121), unless (1) the conclusion is a finding grounded entirely
on speculation, surmise and conjectures; (2) the inference made is
manifestly mistaken; (3) there is grave abuse of discretion; (4) the
Thus, if upon the happening of a fortuitous event or an act of God, there
judgment is based on misapprehension of facts; (5) the findings of fact are
concurs a corresponding fraud, negligence, delay or violation or
conflicting , (6) the Court of Appeals went beyond the issues of the case
contravention in any manner of the tenor of the obligation as provided for
and its findings are contrary to the admissions of both appellant and
in Article 1170 of the Civil Code, which results in loss or damage, the
appellees (Ramos vs. Pepsi-Cola Bottling Co., February 8, 1967, 19 SCRA
obligor cannot escape liability.
289, 291-292; Roque vs. Buan, Oct. 31, 1967, 21 SCRA 648, 651); (7) the
findings of facts of the Court of Appeals are contrary to those of the trial
The principle embodied in the act of God doctrine strictly requires that court; (8) said findings of facts are conclusions without citation of specific
the act must be one occasioned exclusively by the violence of nature and evidence on which they are based; (9) the facts set forth in the petition as
all human agencies are to be excluded from creating or entering into the well as in the petitioner's main and reply briefs are not disputed by the
cause of the mischief. When the effect, the cause of which is to be respondents (Garcia vs. CA, June 30, 1970, 33 SCRA 622; Alsua-Bett vs.
considered, is found to be in part the result of the participation of man, Court of Appeals, July 30, 1979, 92 SCRA 322, 366); (10) the finding of
whether it be from active intervention or neglect, or failure to act, the fact of the Court of Appeals is premised on the supposed absence of
evidence and is contradicted by evidence on record (Salazar vs. Gutierrez, The collapse of the PBA building as a result of the August 2, 1968
May 29, 1970, 33 SCRA 243, 247; Cited in G.R. No. 66497-98, Sacay v. earthquake was only partial and it is undisputed that the building could
Sandiganbayan, July 10, 1986). then still be repaired and restored to its tenantable condition. The PBA,
however, in view of its lack of needed funding, was unable, thru no fault
It is evident that the case at bar does not fall under any of the exceptions of its own, to have the building repaired. UNITED, on the other hand,
above-mentioned. On the contrary, the records show that the lower court spent P13,661.28 to shore up the building after the August 2, 1968
spared no effort in arriving at the correct appreciation of facts by the earthquake (L-47896, CA Decision, p. 46). Because of the earthquake on
referral of technical issues to a Commissioner chosen by the parties April 7, 1970, the trial court after the needed consultations, authorized
whose findings and conclusions remained convincingly unrebutted by the the total demolition of the building (L-47896, Vol. 1, pp. 53-54).
intervenors/amicus curiae who were allowed to intervene in the Supreme
Court. There should be no question that the NAKPILS and UNITED are liable
for the damage resulting from the partial and eventual collapse of the
In any event, the relevant and logical observations of the trial court as PBA building as a result of the earthquakes.
affirmed by the Court of Appeals that "while it is not possible to state
with certainty that the building would not have collapsed were those We quote with approval the following from the erudite decision penned by
defects not present, the fact remains that several buildings in the same Justice Hugo E. Gutierrez (now an Associate Justice of the Supreme
area withstood the earthquake to which the building of the plaintiff was Court) while still an Associate Justice of the Court of Appeals:
similarly subjected," cannot be ignored.
There is no question that an earthquake and other forces
The next issue to be resolved is the amount of damages to be awarded to of nature such as cyclones, drought, floods, lightning, and
the PBA for the partial collapse (and eventual complete collapse) of its perils of the sea are acts of God. It does not necessarily
building. follow, however, that specific losses and suffering
resulting from the occurrence of these natural force are
The Court of Appeals affirmed the finding of the trial court based on the also acts of God. We are not convinced on the basis of the
report of the Commissioner that the total amount required to repair the evidence on record that from the thousands of structures
PBA building and to restore it to tenantable condition was P900,000.00 in Manila, God singled out the blameless PBA building in
inasmuch as it was not initially a total loss. However, while the trial Intramuros and around six or seven other buildings in
court awarded the PBA said amount as damages, plus unrealized rental various parts of the city for collapse or severe damage and
income for one-half year, the Court of Appeals modified the amount by that God alone was responsible for the damages and
awarding in favor of PBA an additional sum of P200,000.00 representing losses thus suffered.
the damage suffered by the PBA building as a result of another
earthquake that occurred on April 7, 1970 (L-47896, Vol. I, p. 92). The record is replete with evidence of defects and
deficiencies in the designs and plans, defective
The PBA in its brief insists that the proper award should be construction, poor workmanship, deviation from plans and
P1,830,000.00 representing the total value of the building (L-47896, specifications and other imperfections. These deficiencies
PBA's No. 1 Assignment of Error, p. 19), while both the NAKPILS and are attributable to negligent men and not to a perfect
UNITED question the additional award of P200,000.00 in favor of the God.
PBA (L- 47851, NAKPIL's Brief as Petitioner, p. 6, UNITED's Brief as
Petitioner, p. 25). The PBA further urges that the unrealized rental The act-of-God arguments of the defendants- appellants
income awarded to it should not be limited to a period of one-half year but and third party defendants-appellants presented in their
should be computed on a continuing basis at the rate of P178,671.76 a briefs are premised on legal generalizations or
year until the judgment for the principal amount shall have been speculations and on theological fatalism both of which
satisfied L- 47896, PBA's No. 11 Assignment of Errors, p. 19). ignore the plain facts. The lengthy discussion of United on
ordinary earthquakes and unusually strong earthquakes
and on ordinary fortuitous events and extraordinary why we have professional experts like architects, and
fortuitous events leads to its argument that the August 2, engineers. Designs and constructions vary under varying
1968 earthquake was of such an overwhelming and circumstances and conditions but the requirement to
destructive character that by its own force and design and build well does not change.
independent of the particular negligence alleged, the
injury would have been produced. If we follow this line of The findings of the lower Court on the cause of the
speculative reasoning, we will be forced to conclude that collapse are more rational and accurate. Instead of laying
under such a situation scores of buildings in the vicinity the blame solely on the motions and forces generated by
and in other parts of Manila would have toppled down. the earthquake, it also examined the ability of the PBA
Following the same line of reasoning, Nakpil and Sons building, as designed and constructed, to withstand and
alleges that the designs were adequate in accordance with successfully weather those forces.
pre-August 2, 1968 knowledge and appear inadequate
only in the light of engineering information acquired after The evidence sufficiently supports a conclusion that the
the earthquake. If this were so, hundreds of ancient negligence and fault of both United and Nakpil and Sons,
buildings which survived the earthquake better than the not a mysterious act of an inscrutable God, were
two-year old PBA building must have been designed and responsible for the damages. The Report of the
constructed by architects and contractors whose Commissioner, Plaintiff's Objections to the Report, Third
knowledge and foresight were unexplainably auspicious Party Defendants' Objections to the Report, Defendants'
and prophetic. Fortunately, the facts on record allow a Objections to the Report, Commissioner's Answer to the
more down to earth explanation of the collapse. The various Objections, Plaintiffs' Reply to the
failure of the PBA building, as a unique and distinct Commissioner's Answer, Defendants' Reply to the
construction with no reference or comparison to other Commissioner's Answer, Counter-Reply to Defendants'
buildings, to weather the severe earthquake forces was Reply, and Third-Party Defendants' Reply to the
traced to design deficiencies and defective construction, Commissioner's Report not to mention the exhibits and
factors which are neither mysterious nor esoteric. The the testimonies show that the main arguments raised on
theological allusion of appellant United that God acts in appeal were already raised during the trial and fully
mysterious ways His wonders to perform impresses us to considered by the lower Court. A reiteration of these same
be inappropriate. The evidence reveals defects and arguments on appeal fails to convince us that we should
deficiencies in design and construction. There is no reverse or disturb the lower Court's factual findings and
mystery about these acts of negligence. The collapse of the its conclusions drawn from the facts, among them:
PBA building was no wonder performed by God. It was a
result of the imperfections in the work of the architects
The Commissioner also found merit in the allegations of
and the people in the construction company. More
the defendants as to the physical evidence before and
relevant to our mind is the lesson from the parable of the
after the earthquake showing the inadequacy of design, to
wise man in the Sermon on the Mount "which built his
wit:
house upon a rock; and the rain descended and the floods
came and the winds blew and beat upon that house; and it
fen not; for it was founded upon a rock" and of the "foolish Physical evidence before the earthquake providing (sic)
upon the sand. And the rain descended and man which inadequacy of design;
built his house the floods came, and the winds blew, and
beat upon that house; and it fell and great was the fall of 1. inadequate design was the cause of the failure of the
it. (St. Matthew 7: 24-27)." The requirement that a building.
building should withstand rains, floods, winds,
earthquakes, and natural forces is precisely the reason
2. Sun-baffles on the two sides and in front of the earthquake shocks. He conceded, however, that the fact
building; that those deficiencies or defects may have arisen from an
obsolete or not too conservative code or even a code that
a. Increase the inertia forces that move the building does not require a design for earthquake forces mitigates
laterally toward the Manila Fire Department. in a large measure the responsibility or liability of the
architect and engineer designer.
b. Create another stiffness imbalance.
The Third-party defendants, who are the most concerned
3. The embedded 4" diameter cast iron down spout on all with this portion of the Commissioner's report, voiced
exterior columns reduces the cross-sectional area of each opposition to the same on the grounds that (a) the finding
of the columns and the strength thereof. is based on a basic erroneous conception as to the design
concept of the building, to wit, that the design is
essentially that of a heavy rectangular box on stilts with
4. Two front corners, A7 and D7 columns were very much
shear wan at one end; (b) the finding that there were
less reinforced.
defects and a deficiency in the design of the building
would at best be based on an approximation and,
Physical Evidence After the Earthquake, Proving therefore, rightly belonged to the realm of speculation,
Inadequacy of design; rather than of certainty and could very possibly be
outright error; (c) the Commissioner has failed to back up
1. Column A7 suffered the severest fracture and or support his finding with extensive, complex and highly
maximum sagging. Also D7. specialized computations and analyzes which he himself
emphasizes are necessary in the determination of such a
2. There are more damages in the front part of the highly technical question; and (d) the Commissioner has
building than towards the rear, not only in columns but analyzed the design of the PBA building not in the light of
also in slabs. existing and available earthquake engineering knowledge
at the time of the preparation of the design, but in the
3. Building leaned and sagged more on the front part of light of recent and current standards.
the building.
The Commissioner answered the said objections alleging
4. Floors showed maximum sagging on the sides and that third-party defendants' objections were based on
toward the front corner parts of the building. estimates or exhibits not presented during the hearing
that the resort to engineering references posterior to the
5. There was a lateral displacement of the building of date of the preparation of the plans was induced by the
about 8", Maximum sagging occurs at the column A7 third-party defendants themselves who submitted
where the floor is lower by 80 cm. than the highest slab computations of the third-party defendants are
level. erroneous.
6. Slab at the corner column D7 sagged by 38 cm. The issue presently considered is admittedly a technical
one of the highest degree. It involves questions not within
the ordinary competence of the bench and the bar to
The Commissioner concluded that there were deficiencies
resolve by themselves. Counsel for the third-party
or defects in the design, plans and specifications of the
defendants has aptly remarked that "engineering,
PBA building which involved appreciable risks with
although dealing in mathematics, is not an exact science
respect to the accidental forces which may result from
and that the present knowledge as to the nature of
earthquakes and the behaviour of forces generated by violations or deviations from the plans and specifications.
them still leaves much to be desired; so much so "that the All these may be summarized as follows:
experts of the different parties, who are all engineers,
cannot agree on what equation to use, as to what a. Summary of alleged defects as reported by Engineer
earthquake co-efficients are, on the codes to be used and Mario M. Bundalian.
even as to the type of structure that the PBA building (is)
was (p. 29, Memo, of third- party defendants before the (1) Wrongful and defective placing of reinforcing bars.
Commissioner).
(2) Absence of effective and desirable integration of the 3
The difficulty expected by the Court if tills technical bars in the cluster.
matter were to be tried and inquired into by the Court
itself, coupled with the intrinsic nature of the questions
(3) Oversize coarse aggregates: 1-1/4 to 2" were used.
involved therein, constituted the reason for the reference
Specification requires no larger than 1 inch.
of the said issues to a Commissioner whose qualifications
and experience have eminently qualified him for the task,
and whose competence had not been questioned by the (4) Reinforcement assembly is not concentric with the
parties until he submitted his report. Within the column, eccentricity being 3" off when on one face the
pardonable limit of the Court's ability to comprehend the main bars are only 1 1/2' from the surface.
meaning of the Commissioner's report on this issue, and
the objections voiced to the same, the Court sees no (5) Prevalence of honeycombs,
compelling reasons to disturb the findings of the
Commissioner that there were defects and deficiencies in (6) Contraband construction joints,
the design, plans and specifications prepared by third-
party defendants, and that said defects and deficiencies (7) Absence, or omission, or over spacing of spiral hoops,
involved appreciable risks with respect to the accidental
forces which may result from earthquake shocks. (8) Deliberate severance of spirals into semi-circles in
noted on Col. A-5, ground floor,
(2) (a) The deviations, if any, made by the defendants
from the plans and specifications, and how said deviations (9) Defective construction joints in Columns A-3, C-7, D-7
contributed to the damage sustained by the building. and D-4, ground floor,
(b) The alleged failure of defendants to observe the (10) Undergraduate concrete is evident,
requisite quality of materials and workmanship in the
construction of the building.
(11) Big cavity in core of Column 2A-4, second floor,
We now turn to the construction of the PBA Building and b. Summary of alleged defects as reported by Engr.
the alleged deficiencies or defects in the construction and Antonio Avecilla.
Columns are first (or ground) floor, unless otherwise c. Summary of alleged defects as reported by the experts
stated. of the Third-Party defendants.
(1) Column D4 — Spacing of spiral is changed from 2" to Ground floor columns.
5" on centers,
(1) Column A4 — Spirals are cut,
(2) Column D5 — No spiral up to a height of 22" from the
ground floor, (2) Column A5 — Spirals are cut,
(3) Column D6 — Spacing of spiral over 4 l/2, (3) Column A6 — At lower 18" spirals are absent,
(4) Column D7 — Lack of lateral ties, (4) Column A7 — Ties are too far apart,
(5) Column C7 — Absence of spiral to a height of 20" from (5) Column B5 — At upper fourth of column spirals are
the ground level, Spirals are at 2" from the exterior either absent or improperly spliced,
column face and 6" from the inner column face,
(6) Column B6 — At upper 2 feet spirals are absent,
(6) Column B6 — Lack of spiral on 2 feet below the floor
beams, (7) Column B7 — At upper fourth of column spirals
missing or improperly spliced.
(7) Column B5 — Lack of spirals at a distance of 26' below
the beam, (8) Column C7— Spirals are absent at lowest 18"
(8) Column B7 — Spirals not tied to vertical reinforcing (9) Column D5 — At lowest 2 feet spirals are absent,
bars, Spirals are uneven 2" to 4",
(10) Column D6 — Spirals are too far apart and
(9) Column A3 — Lack of lateral ties, apparently improperly spliced,
(10) Column A4 — Spirals cut off and welded to two (11) Column D7 — Lateral ties are too far apart, spaced
separate clustered vertical bars, 16" on centers.
(11) Column A4 — (second floor Column is completely There is merit in many of these allegations. The
hollow to a height of 30" explanations given by the engineering experts for the
defendants are either contrary to general principles of
(12) Column A5 — Spirals were cut from the floor level to engineering design for reinforced concrete or not
the bottom of the spandrel beam to a height of 6 feet, applicable to the requirements for ductility and strength
of reinforced concrete in earthquake-resistant design and
(13) Column A6 — No spirals up to a height of 30' above construction.
the ground floor level,
We shall first classify and consider defects which may
(14) Column A7— Lack of lateralties or spirals, have appreciable bearing or relation to' the earthquake-
resistant property of the building.
As heretofore mentioned, details which insure ductility at certainly be absorbed within the factor of safety, they
or near the connections between columns and girders are nevertheless diminish said factor of safety.
desirable in earthquake resistant design and construction.
The omission of spirals and ties or hoops at the bottom The cutting of the spirals in column A5, ground floor is
and/or tops of columns contributed greatly to the loss of the subject of great contention between the parties and
earthquake-resistant strength. The plans and deserves special consideration.
specifications required that these spirals and ties be
carried from the floor level to the bottom reinforcement of The proper placing of the main reinforcements and spirals
the deeper beam (p. 1, Specifications, p. 970, Reference in column A5, ground floor, is the responsibility of the
11). There were several clear evidences where this was general contractor which is the UCCI. The burden of
not done especially in some of the ground floor columns proof, therefore, that this cutting was done by others is
which failed. upon the defendants. Other than a strong allegation and
assertion that it is the plumber or his men who may have
There were also unmistakable evidences that the spacings done the cutting (and this was flatly denied by the
of the spirals and ties in the columns were in many cases plumber) no conclusive proof was presented. The
greater than those called for in the plans and engineering experts for the defendants asserted that they
specifications resulting again in loss of earthquake- could have no motivation for cutting the bar because they
resistant strength. The assertion of the engineering can simply replace the spirals by wrapping around a new
experts for the defendants that the improper spacings and set of spirals. This is not quite correct. There is evidence
the cutting of the spirals did not result in loss of strength to show that the pouring of concrete for columns was
in the column cannot be maintained and is certainly sometimes done through the beam and girder
contrary to the general principles of column design and reinforcements which were already in place as in the case
construction. And even granting that there be no loss in of column A4 second floor. If the reinforcement for the
strength at the yield point (an assumption which is very girder and column is to subsequently wrap around the
doubtful) the cutting or improper spacings of spirals will spirals, this would not do for the elasticity of steel would
certainly result in the loss of the plastic range or ductility prevent the making of tight column spirals and loose or
in the column and it is precisely this plastic range or improper spirals would result. The proper way is to
ductility which is desirable and needed for earthquake- produce correct spirals down from the top of the main
resistant strength. column bars, a procedure which can not be done if either
the beam or girder reinforcement is already in place. The
There is no excuse for the cavity or hollow portion in the engineering experts for the defendants strongly assert
column A4, second floor, and although this column did not and apparently believe that the cutting of the spirals did
fail, this is certainly an evidence on the part of the not materially diminish the strength of the column. This
contractor of poor construction. belief together with the difficulty of slipping the spirals on
the top of the column once the beam reinforcement is in
The effect of eccentricities in the columns which were place may be a sufficient motivation for the cutting of the
measured at about 2 1/2 inches maximum may be spirals themselves. The defendants, therefore, should be
approximated in relation to column loads and column and held responsible for the consequences arising from the
beam moments. The main effect of eccentricity is to loss of strength or ductility in column A5 which may have
change the beam or girder span. The effect on the contributed to the damages sustained by the building.
measured eccentricity of 2 inches, therefore, is to increase
or diminish the column load by a maximum of about 1% The lack of proper length of splicing of spirals was also
and to increase or diminish the column or beam proven in the visible spirals of the columns where spalling
movements by about a maximum of 2%. While these can of the concrete cover had taken place. This lack of proper
splicing contributed in a small measure to the loss of As the parties most directly concerned with this portion of the
strength. Commissioner's report, the defendants voiced their objections to the same
on the grounds that the Commissioner should have specified the defects
The effects of all the other proven and visible defects found by him to be "meritorious"; that the Commissioner failed to indicate
although nor can certainly be accumulated so that they the number of cases where the spirals and ties were not carried from the
can contribute to an appreciable loss in earthquake- floor level to the bottom reinforcement of the deeper beam, or where the
resistant strength. The engineering experts for the spacing of the spirals and ties in the columns were greater than that
defendants submitted an estimate on some of these called for in the specifications; that the hollow in column A4, second floor,
defects in the amount of a few percent. If accumulated, the eccentricities in the columns, the lack of proper length of splicing of
therefore, including the effect of eccentricity in the column spirals, and the cut in the spirals in column A5, ground floor, did not
the loss in strength due to these minor defects may run to aggravate or contribute to the damage suffered by the building; that the
as much as ten percent. defects in the construction were within the tolerable margin of safety; and
that the cutting of the spirals in column A5, ground floor, was done by the
To recapitulate: the omission or lack of spirals and ties at plumber or his men, and not by the defendants.
the bottom and/or at the top of some of the ground floor
columns contributed greatly to the collapse of the PBA Answering the said objections, the Commissioner stated that, since many
building since it is at these points where the greater part of the defects were minor only the totality of the defects was considered.
of the failure occurred. The liability for the cutting of the As regards the objection as to failure to state the number of cases where
spirals in column A5, ground floor, in the considered the spirals and ties were not carried from the floor level to the bottom
opinion of the Commissioner rests on the shoulders of the reinforcement, the Commissioner specified groundfloor columns B-6 and
defendants and the loss of strength in this column C-5 the first one without spirals for 03 inches at the top, and in the latter,
contributed to the damage which occurred. there were no spirals for 10 inches at the bottom. The Commissioner
likewise specified the first storey columns where the spacings were
It is reasonable to conclude, therefore, that the proven greater than that called for in the specifications to be columns B-5, B-6,
defects, deficiencies and violations of the plans and C-7, C-6, C-5, D-5 and B-7. The objection to the failure of the
specifications of the PBA building contributed to the Commissioner to specify the number of columns where there was lack of
damages which resulted during the earthquake of August proper length of splicing of spirals, the Commissioner mentioned
2, 1968 and the vice of these defects and deficiencies is groundfloor columns B-6 and B-5 where all the splices were less than 1-
that they not only increase but also aggravate the 1/2 turns and were not welded, resulting in some loss of strength which
weakness mentioned in the design of the structure. In could be critical near the ends of the columns. He answered the
other words, these defects and deficiencies not only tend supposition of the defendants that the spirals and the ties must have
to add but also to multiply the effects of the shortcomings been looted, by calling attention to the fact that the missing spirals and
in the design of the building. We may say, therefore, that ties were only in two out of the 25 columns, which rendered said
the defects and deficiencies in the construction supposition to be improbable.
contributed greatly to the damage which occurred.
The Commissioner conceded that the hollow in column A-4, second floor,
Since the execution and supervision of the construction did not aggravate or contribute to the damage, but averred that it is
work in the hands of the contractor is direct and positive, "evidence of poor construction." On the claim that the eccentricity could
the presence of existence of all the major defects and be absorbed within the factor of safety, the Commissioner answered that,
deficiencies noted and proven manifests an element of while the same may be true, it also contributed to or aggravated the
negligence which may amount to imprudence in the damage suffered by the building.
construction work. (pp. 42-49, Commissioners Report).
The objection regarding the cutting of the spirals in Column A-5,
groundfloor, was answered by the Commissioner by reiterating the
observation in his report that irrespective of who did the cutting of the MILLION (P5,000,000.00) Pesos to cover all damages (with the exception
spirals, the defendants should be held liable for the same as the general of attorney's fees) occasioned by the loss of the building (including
contractor of the building. The Commissioner further stated that the loss interest charges and lost rentals) and an additional ONE HUNDRED
of strength of the cut spirals and inelastic deflections of the supposed THOUSAND (P100,000.00) Pesos as and for attorney's fees, the total sum
lattice work defeated the purpose of the spiral containment in the column being payable upon the finality of this decision. Upon failure to pay on
and resulted in the loss of strength, as evidenced by the actual failure of such finality, twelve (12%) per cent interest per annum shall be imposed
this column. upon afore-mentioned amounts from finality until paid. Solidary costs
against the defendant and third-party defendants (except Roman
Again, the Court concurs in the findings of the Commissioner on these Ozaeta).
issues and fails to find any sufficient cause to disregard or modify the
same. As found by the Commissioner, the "deviations made by the SO ORDERED.
defendants from the plans and specifications caused indirectly the
damage sustained and that those deviations not only added but also
aggravated the damage caused by the defects in the plans and
specifications prepared by third-party defendants. (Rollo, Vol. I, pp. 128-
142)
Relative thereto, the ruling of the Supreme Court in Tucker v. Milan (49
O.G. 4379, 4380) which may be in point in this case reads:
As already discussed, the destruction was not purely an act of God. Truth
to tell hundreds of ancient buildings in the vicinity were hardly affected
by the earthquake. Only one thing spells out the fatal difference; gross
negligence and evident bad faith, without which the damage would not
have occurred.
(B)
IN REVERSING THE TRIAL COURT'S DECISION, THE Moreover, even in cases where a natural disaster is the proximate and
APPELLATE COURT GRAVELY ERRED IN CONTRADICTING only cause of the loss, a common carrier is still required to exercise due
AND IN DISTURBING THE FINDINGS OF THE FORMER; diligence to prevent or minimize loss before, during and after the
occurrence of the natural disaster, for it to be exempt from liability under
(C) the law for the loss of the goods.11 If a common carrier fails to exercise
due diligence--or that ordinary care which the circumstances of the
THE APPELLATE COURT GRAVELY ERRED IN REVERSING particular case demand12 -- to preserve and protect the goods carried by it
THE DECISION OF THE TRIAL COURT AND IN DISMISSING on the occasion of a natural disaster, it will be deemed to have been
THE COMPLAINT.6 negligent, and the loss will not be considered as having been due to a
natural disaster under Article 1734 (1).
Common carriers, from the nature of their business and for reasons of
public policy, are mandated to observe extraordinary diligence in the In the case at bar, the issues may be narrowed down to whether the loss
vigilance over the goods and for the safety of the passengers transported of the cargo was due to the occurrence of a natural disaster, and if so,
by them.7Owing to this high degree of diligence required of them, common whether such natural disaster was the sole and proximate cause of the
carriers, as a general rule, are presumed to have been at fault or loss or whether private respondents were partly to blame for failing to
negligent if the goods transported by them are lost, destroyed or if the exercise due diligence to prevent the loss of the cargo.
same deteriorated.8
The parties do not dispute that on the day the M/V Peatheray Patrick-G
However, this presumption of fault or negligence does not arise in the sunk, said vessel encountered strong winds and huge waves ranging from
cases enumerated under Article 1734 of the Civil Code: six to ten feet in height. The vessel listed at the port side and eventually
sunk at Cawit Point, Cortes, Surigao del Sur.
Common carriers are responsible for the loss, destruction, or
deterioration of the goods, unless the same is due to any of the The Court of Appeals, citing the decision of the Board of Marine Inquiry
following causes only: in the administrative case against the vessel's crew (BMI--646-87), found
that the loss of the cargo was due solely to the existence of a fortuitous
event, particularly the presence of strong winds and huge waves at
(1) Flood, storm, earthquake, lightning or other natural disaster
Cortes, Surigao del Sur on March 3, 1987:
or calamity;
xxx
(2) Act of the public enemy in war, whether international or civil;