Bid Sheet Valve Project
2 Man Power
- Supervisor 1 person 15,000,000.00
- Teknisi 2 person 11,000,000.00
- Helper 2 person 6,000,000.00
- Dok Control 1 person 8,000,000.00
Subtotals 57,000,000.00
Subtotals
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Rp 57,000,000.00
Table 8.1 Field Instrumentation Summary
0.00
Additional Work and Emergency Work
UO Unit Price
Descriptions QTY M Rp
A. Tools and Equipment rental
1 Multimeter 2 ea
2 Loop Validator/ 4-20mA standard signal injector 2 ea
3 Hart Communicator 2 ea
4 Hand Tools : screw driver, combination wrench, etc 2 lot
5 Small Tools 2 lot
6 Document Process 744 Fluke 1 ea
B. Consumables, consists of:
Silicon Sealant 10 can
WD-40 36 can
Rubber tape 20 ea
Electrical Insulation tape 40 ea
Seal Tape 40 Roll
Sub Total
Price Total
0
Total 0