OKI SINARMAS

INSPECTION AND CALIBRATION ON-OFF VALVE


Cost Estimate
CP No. : Total Cost (round
Cost Center :
No Item Description Weight Required Unit Unit Rate
1 Instrument
- Control Valve 88 unit
- On Off Valve 68 unit
Subtotals 0.00

2 Man Power
- Supervisor 1 person 15,000,000.00
- Teknisi 2 person 11,000,000.00
- Helper 2 person 6,000,000.00
- Dok Control 1 person 8,000,000.00
Subtotals 57,000,000.00

7 Tools, Transport and accomodation


- On Site tool rental 1 Lot 0.00
- Accommodations 0 Room
- Mob Demob 1 lot
- Local Transportation (Hotel-OKI Plant daily) 0 Unit

Subtotals for Tools, Transport and accomodation 0.00


8 Materials
- Consumable Parts 1.00 1 Lot 0.00
- PPE 1.00 1 Lot 0.00
Subtotals for Materials 0.00
(Contract Period :) Total
Total Cost (round-up) $57,000,000.00

Subtotals

0.00

15,000,000.00 estimation 30 days


22,000,000.00 estimation 30 days
12,000,000.00 estimation 30 days
8,000,000.00 estimation 30 days

0.00
0.00
0.00
0.00

0.00
0.00

Rp 57,000,000.00
Table 8.1 Field Instrumentation Summary

System Total Man


Grand Cost hour
Instrument Category CLO2 SO2 PAC NAOH Total Percentage Required
Control valve 58 2 0 28 88 56.4% 1056
ON Off Valve 50 0 10 8 68 43.6% 816
Grand Total 108 2 10 36 156 100.0% 1872
Unit rate
[Rp]

0.00
Additional Work and Emergency Work

No Item Description Personnel Rate Unit


1 Additional Rate Week Day Field Supervisor Per day
Senior Technician Per day
Technician Per day
Local Helper Per day
Accomodation Per day
Saturday 1.5 x normal weekday daily rate
Sunday and Public Holiday 2.0 x normal weekday daily rate

2 Overtime Week Day Field Supervisor Per hour


Senior Technician Per hour
Technician Per hour
Local Helper Per hour
Saturday 1.5 x normal weekday daily rate
Sunday and Public Holiday 2.0 x normal weekday daily rate
3 Emergency Rate Week Day Technician Per Day
Overtime Technician Per Hour
Holiday Technician Per Day
Overtime Technician Per hour
All Season Local Helper Per Day
4 Transportation Person Lot
5 Accomodation Person Per Day
6 Equipment Tool and Equipment Per Day
Excess Baggage Lot
Owner Estimate for Tools and Equipments, Consumables, Transportation

UO Unit Price
Descriptions QTY M Rp
A. Tools and Equipment rental
1 Multimeter 2 ea
2 Loop Validator/ 4-20mA standard signal injector 2 ea
3 Hart Communicator 2 ea
4 Hand Tools : screw driver, combination wrench, etc 2 lot
5 Small Tools 2 lot
6 Document Process 744 Fluke 1 ea
B. Consumables, consists of:
Silicon Sealant 10 can
WD-40 36 can
Rubber tape 20 ea
Electrical Insulation tape 40 ea
Seal Tape 40 Roll
Sub Total
Price Total
0

Total 0