Professional Documents
Culture Documents
Electric Specifications PDF
Electric Specifications PDF
1.0 The intent of this chapter of the specification is to define the general
technical requirements of internal electrical wiring works.
1.1 STANDARDS
The work shall be carried out in conformi ty with this specification, the
relevant specifications / code of practice of the Indian Standards
Institutions, approved drawings and instructions of the Engineer -in-
Charge or his authorized representative issued from time to time. In
addition to the above, all works shall conform to the requirements of
the following :
a) Indian Electricity Act and Rules.
b) Regulations laid down by Chief Electrical Inspector of the
state, power supply authority.
c) Relevant Indian Standards and National Electrical Cod e.
d) Any other regulation laid down by the local authorities.
1.3.1 Switches
1.3.2 Receptacles
a) All rigid metallic conduit pipes shall be of steel and be ISI marked.
The minimum wall thickness shall be 1.6 mm (16 SWG) up to 32 mm
dia and 2 mm (14 SWG) above 32 mm dia. The conduit shall be solid
drawn or reamed by welding and finished with galvanized or stove
enameled surface.
d) All metallic conduit accessories shall be only threaded type, pin grip
or clamp type accessories are not acceptable.
a) Casing and capping shall be of good quality PVC, free from defects
like deformations, unevenness, blisters, cavities, etc.
a) Wiring cables
- Wires shall be PVC insulated 1100 V grade as per IS:1554.
- Conductors shall be of st randed copper.
- The smallest size of conductor for lighting circuits shall have a
nominal cross-sectional area of not less than 1.5 sq.mm, while
minimum size of power wiring shall be 2.5 sq.mm.
- All wires shall be ISI marked.
b) Flexible cable
- Flexible cables shall be PVC insulated having a minimum size
of 14/0.0193 mm.
- All flexible wires shall be mechanically protected by tough
rubber or PVC sheath.
c) Underground cables
- Power cables:
d) Communication cables :
The switchboard shall be sheet steel clad with the frame fabricated out
of 14 SWG cold rolled sheet steel and doors / covers out of 15 SWG
cold rolled sheet steel;having integral base frame for each vertical
panel. All hardware shall be corrosion resistant. All joints and
connections of the panel members shall be made of galvanised, zinc
passivated or cadmium plated high quality steel bolts, nuts and
washers, secured against loosening.
The switchgear shall be suitable for bottom cable entry. Provision for
incoming connection through busduct shall be made as per
requirement of the specificat ion and schedule of rates.
Individual circuit breakers, switch fuse units, MCCBs, bus -bars, cable
termination compartment shall be housed in separate enclosed
compartments separated from each other by metallic barriers.
Circuit breaker panel shall be in single front execution only. Not more
than two breaker cubicles shall be housed in single vertical panel
except for the incomer and bus-coupler, which shall each be housed in
independent vertical panels. Motor starters, switch fuse units, MCCBs
shall be in suitable arrangement in single or double front as specified in
the schedule of items. All auxiliary devices for control, indications,
measurement and protection such as push -button, control and selector
switches, indicating lamp, metering instruments prot ective relays
except bimetallic relays shall be mounted on the front side of the
respective compartment Components requiring frequent inspection
during operation shall be easily accessible.
The air circuit breakers shall be fully drawout type, Circuit breaker
panel shall have three distinct positions : viz – ‘service’, ‘test’, ‘full out ’
position complete with necessary safety interlocks, scraping, earth
connection, shutters, safety barriers and suitable guides for easy
movement of the trolley. Access to the cables shall be from the rear
side after opening the door of the separate cablin g compartment.
Circuit breakers shall be trip free type having antipumping features and
electrically operated mechanism suitable for control supply specified in
the schedule of items/ specification. Circuit breaker trip coils shall be
rated for satisfactory operation with 50% to 110% of rated voltage and
the closing coil shall be rated for 85% to 110% of the rated voltage.
All switch fuse units shall be load break, heavy duty, air break type
(double break) with the operating handle mounted on compartment
door, complete with necessary interlocking mechanism.
All relays shall be back connected, drawout type suitable for flush
mounting and fitting with dust tight covers along wit h hand reset type
built in flag indication.
Current transformers for metering shall have an accuracy class 1.0 and
instrument accuracy class 5 P and accuracy limit factor greater than
10.
All indicating instruments shall be flush mounting type and of 96 x 96
mm squarepattern, except the digital instruments. Digital instruments if
required shall be as per schedule of items / specific technical
specifications.
b) “L” series MCBs shall be used only for normal lighting circuits.
c) “G” series MCBs shall be used for all motor loads, air conditioners,
halogen and other discharge lamps and all power circuits.
d) All MCBs shall be of 9 KA breaking capacity, unless specifically
mentioned otherwise in the schedule of items.
b) Current rating and the short circuit rating of the MCCBs shall be as
per
schedule of items.
A. General
d) All bends in the wiring system shall be done either by bending the
pipes neatly without any crack or by inserting suitable accessories like
bends, elbows or similar fittings. Radius of bends in conduit pipes shall
not be less than 7.5 cm.
c) Where conduits are required to be lai d along the trusses / joist etc.,
the same shall be secured by means of saddles / girder clips etc. As
per instruction /approval of the Engineer -in-Charge.
d) In all the cases when conduits are laid in masonry / concrete work,
saddles shall be properly secured by inserting polyethylene plugs
approved by the Engineer-in-Charge.
i) The conduit pipes shall be laid in position and firmly secured to the
steel reinforcement bars by steel binding wires before concreting is
done.
ii) Instead of using standard bends or elbows the conduit itself should
be bent in long radius to facilitate easy drawing of conductors.
iii) Inspection and junction boxes should be suitabl y located to avoid
long conduit runs and such boxes shall be properly identified to avoid
unnecessary chipping of the RCC slab subsequently to locate these
boxes.
iv) Special care shall be taken in laying the conduits and during the
concreting work to avoid damage to the conduits.
A) Materials
ii) The main earthing conductor (from earth electrode to the main
switch board or earth bus) shall be of G.I. or copper as specifi ed.
The sizes shall also be as per specification. However, in no case
the size of the main earthing conductor be less than
Copper strip 20 x 3 mm
5. All metallic finials, chimneys, ducts, vent pipes, railings, gutters and
the like,on or above the main surface of the roof of the structure shall
be bonded to and form part of, the air termination network. If portions of
a structure vary considerably in height any necessary air termination of
air termination network of the lower portions, in addition to their own
conductors be bonded to the down conductor s of the taller portions.
1. The number and spacing of the down conductors shall be as per the
tender specification as directed by the Engineer -in-Charge. However,
there shall be minimum 2 down conductors for structures up to 400
sq.m area and one extra down conductor for every additional 300 sq.m
or part thereof.
3. Down conductors shall be laid in such a way that they follow the
most direct path possible between the air termination and the earth
termination, avoiding sharp bends, upturns and kinks. Joints shall as
far as possible be avoided in down conductors. Adequate protection
may be provided to the conductors against mechanical damage. Metal
pipes should not be used as protection for conductors.
4. Metal pipes leading rain water from the roof to the ground may be
connected to the down conductors. Such connections should have
disconnecting joints for testing purpose.
viii) Fasteners
c) All electrodes are connected to the grid and the earth resistance of
the entire earthing system is measured.
1.5.1 Route
i) Before the cable laying work is undertaken, the route layout of the
cable shall be submitted to the Engineer -in-Charge and the work shall
be undertaken only after approval of the route layout.
ii) a) Whenever cables of different voltages are laid following points
shall be noted while laying along well demarcated or established roads,
the LV / MV cables shall be laid further from the kerb line than HV
cables.
b) Cables of different voltages and also power and control cables shall
be kept in different trenches with adequate separ ation. Where available
space is restricted such that this requirement cannot be met, LV / MV
cables shall be laid above HV cables.
c) Where cables cross one another, the cable of higher voltage shall be
laid at a lower level than the cable of lower voltag e.
The cables shall be laid direct in ground, pipe, closed or open ducts,
cable trays or on surface of wall etc. The method(s) of laying required
shall be specified in the tender / schedule of work.
ii) Trenching
TABLE – 2
MINIMUM BENDING RADIUS – PAPER INSULATED CABLES AND XLPE
CABLES
System voltage Minimum bending
radius
The excavated trench shall be provided with a layer of clean, dry sand
cushion of not less than 8 cm in depth, before la ying the cables therein.
However, sand cushioning may not be provided for MV cables, where
there is no possibility of any mechanical damage to the cables due to
heavy or shock loading on the soil above if so specified in the tender
document and as per appr oval of the Engineer-in-Charge. Sand
cushioning shall however be invariably provided in the case of HV
cables.
c) The cable shall be pulled over in rollers in the trench steadily and
uniformly without jerks and strain. The entire cable length shall be far
as possible laid off in one stretch. PVC / XLPE cables less than 120
sq.mm size may be removed by “Flaking” i.e. by making one long loop
in the reverse direction.
d) After the cable has been so uncoiled, it shall be lifted slightly over
the rollers beginning from one end by helpers standing about 10 m
apart and drawn straight.The cable shall then be lifted off the rollers
and laid in a reasonably straight line.
f) Sand covering
In the case of vertical multi -tier formation, after the first cable has been
laid, a sand cushion of 30 cm shall be provided over the base cushion
before the second tier is laid. If additional tiers are formed, each of the
subsequent tiers also shall have a sand cushion of 30 cm as stated
above. Cables in the top most tier shall have a final sand covering not
less than 17 cm before the protective cover is laid.
Sand covering as stated above need not be provided for MV cabl es
where a decision is taken by the Engineer -in-Charge as per sub clause
(iii-a) above, but theater tier spacing should be maintained with soft soil
instead of sand between tiers and for covering. Sand cushioning shall
however be invariably provided in the case of HV cables.
iv) Backfilling
a) The trenches shall be then backfilled with excavated earth, free from
stones or other shall edged debris and shall be rammed and watered, if
necessary in successive layers not exceeding 30 cm depth.
e) Where road berms of lawns have been cut out of necessity, or kerb
stones displaced, the same shall be repaired and mad e good, except
for turfing /asphalting, to the satisfaction of the Engineer -in-Charge and
all the surplus earth or rock shall be removed to places as specified.
Three single core cables forming one three phase circuit shal l normally
be held inclose trefoil formation and shall be bound together at
intervals of approximately 1m.
The relative position of the three cables shall be changed at each joint
at the time of original installation, complete transposition being effected
in every three consecutive cable lengths.
ii) Following guide of the pipe fill shall be used for sizing the pipe size:
iv) At road crossing and other places where cables enter pipe sleeves
adequate bed of sand shall be given so that the cables do not slack
and get damaged by pipe ends.
vii) All G.I. pipes shall be laid as per layout drawings and site
requirements.Before fabrication of various profiles of pipe by
hydraulically operated bending machine (which is to be arranged by the
Contractor), all the burrs from the pipes shall be removed. G.I. pipes
with bends shall be buried in soil / concrete in such a way that the
bends shall be totally concealed. For G.I. pipes buried in soil, bitumen
coating shall be applied on the buried lengths. Installation o f G.I. pipes
shall be undertaken well before paving is completed and necessary
coordination with paving agency shall be the responsibility of Electrical
Contractor. The open ends of pipes shall be suitably plugged with G.I.
plugs after they are laid in fin al position. G.I. plugs shall be supplied by
the Contractor at no extra cost.
1.5.5 Laying in Open Ducts.
b) Laying of cables with different voltage ratings in the same duct shall
be Avoided. Where it is inescapable to take HV & MV cables s ame
trench, they shall be laid with a barrier between them or alternatively,
one of the two (HV / MV) cables may be taken through pipe(s).
Splices or joints of any type shall not be permitted inside the ducts.
a) The cables shall be laid directly in the duct such that unnecessary
crossing of cables is avoided.
b) Where specified, cables may be fixed with clamps on the walls of the
duct or taken in hooks / brackets / cable trays through in ducts.
c) Where specified, ducts may be filled with dry sand aft er the cables
are laid and covered as above, or finished with cement plaster,
specially in high voltage applications.
b) Supported on cradles
i) Location
a) Before laying a cable, proper locations for the proposed cable joints,
if any, shall be decided, so that when the cable is actually laid, the
joints are made in the most suitable places. As far as possible, water
logged locations, carriage ways, pavements, proximity to telephone
cables, gas or water mains, inaccessible places, ducts, pipes, racks etc.
shall be avoided for locating the cable joints.
iv) Jointer
1.5.9 Testing
i) Testing before laying All cables, before laying, shall be tested with a
500 V megger for cables of 1.1 KV grade, or with a 2500 / 5000 V
megger for cables of higher voltage. The cable cores shall be tested for
continuity, absence of cross phasing , insulation resistance from
conductors to earth / armour and between conductors.
1.5.10 Measurement
A. Equipment
1. Portable grinder
2. Portable welding machine
3. Portable gas cutting / welding set
4. Pipe threading machine
5. Pipe bending machine (hydraulic)
6. Portable drill machine suitable to take up drilling for different
sizes as per requirement
7. Dewatering pumpsets (diesel driven)
8. Power hacksaw
9. Conduit dye set
10. Hydraulic crimping machine
11. Hand crimping tool
12. Portable electric blowers, vacuum cleaners
13. Miscellaneous items such as sling, pulleys tarpaulins,
wooden sleepers, ladders, etc. as required.
14. Safety belts, safety goggles, hand gloves
15. Separate tool kit for each electrician
B. Test Instruments
1.7.1 All wirings for light and power circuits shall be in PVC conduits
recessed in wall / ceiling.
1.7.2 All 5A and 15A switches shall be piano type of approved make.
17.3 All wires for point wiring and the single core wires specified for sub
main and circuit wirings shall be 1.1 KV grade PVC insulated FRLS
copper multistoried wires of approved brand. The multicore cables
indicated in the drawings shall, however, be PVC insul ated and
sheathed armored aluminium underground cables of approved brands.
1.7.4 Supply of light fittings, fans and exhaust fans have been included in the
scope of this tender.
1.7.5 All 6A receptacles shall be flush type and shall have 5 pins with 1 pi n
for earth connection and 2 pins each for Phase and neutral
connections. 16A receptacles shall have 6 pins (suitable for connecting
both 6A and 16A plug tops) with 2 pins each for phase, neutral and
earth connections.
1.7.6 Samples of all the materials t o be used in the work shall be submitted
to the Engineer-in-Charge (Elect.) for approval. No material other than
those approved by the NRL shall be used in any of the works.
In case of any materials other than those approved by the E iC (Elect.)
is detected, the same shall be replaced by the Tenderer with the
approved quality, free of cost, failing which, the owner shall have right
to withhold all pending bills due to the Contractor, until the rectification /
replacement work is completed.
viii) The indoor and outdoor unit of the Air conditioners shall be
connected through flare nuts with necessary reducers and
fasteners.
3.1.1. The scope of work shall include designing supplying and installing testing and
commissioning of Analogue Addressable Fire Detection cum Alarm System
with central monitoring system. This shall conform to r elevant latest standards
for fire alarm systems.
3.1.2 It shall be possible to trip from the Fire Alarm Panel through the use of
Addressable Output Modules, individual AHU activated by the fire signal of
specified detectors.
3.1.4 The Building shall have a multi zone panel with each area forming of one or
more software programmed zones.
3.1.5 All wiring shall be done using 2c x 1.5mm2 PVC insulated armored copper
cable. (FRLS).
b) The Fire alarm control panel shall be able to supervise individual detectors
for proper performance as well as to give pinpoint location of fire alarm.
c) The panel shall have hooter alarm as well as facility for cutting off of AHUs
and ventilation fans.
3.2.1. LOOP
b) The loop card shall have built -in circuit isolator to accommodate Class ‘A’
wiring.
3.2.3 DETECTORS
d) The detectors shall have a common base to allow easy interchange of various
types of detectors.
a) The Manual Call Station shall be addressable typ e with input modules to
define the device/location.
b) The Manual call station shall be breakable type with suitable protection and
base box. .
a) Output module shall mean addressable points from the Fire alarm control
panel with potential free contacts for tripping of AHUs, power supply etc. as
required.
b) The dual channel module shall be selectable for Normally Open or closed.
a) This unit shall be placed on the loop preferably after every 20 devices and
shall be able to isolate electrical short circuit in the wiring.
b) All the other detectors shall remain functional because of the Class A wiring
of the loop.
c) The isolator shall not utilize an address and shall be built into the detector
base wherever required.
3.2.8 SOUNDERS
b) The sounders shall derive power from separate cable with vo ltage adopter.
d) The sounder shall have an output of at least 85 db at 1 mtr. The sounder shall
be programmed to get activated in event of an alarm from a single
detector/device or a group of detectors/ devices.
3.3.2 The system shall give pinpoint location of fire with warning system.
3.3.3 The system shall have a microprocessor -based control and monitoring facility.
3.3.4 It shall be possible to program each loop with up to minimum 126 /159
detectors/devices.
3.3.5 Annunciation facility shall also be inbuilt into the Fire alarm control panel, the
panel being able to initiate alarm signal for any particular zone.
3.3.6 a) The system shall be fully supervised for all fault conditions with distinctive
alarm operated for fault and fire conditions.
b) Test buttons and software features shall be provided to test the electronic
circuits and detector health.
3.3.7 a) The Fire alarm control panel shall be so programmed that when a
particular detector or group of detectors gives a fire signal the Fire alarm
control panel should be able to trip AHU/AHU’s/Ventilation fans etc
b) In case of Fire in a area handled by an AHU the Fire alarm control panel
shall be able to trigger a Relay that shall shut off th e AHU through an
additional contact provided in the AHU panel by the AC contractor.
3.4.1 The Fire Alarm Control Panel shall be micro proc essor based fully Analogue
Addressable, Analogue Control Unit with centralized monitoring which shall
control all Analogue Addressable Detectors, Manual Call Stations and
Switching Systems (for disconnecting AHU and power supply) connected with
IP card output for communication with other panel and central control station
(CCS).
3.4.2 a) All addressable units shall be connected to the Fire alarm control panel
through the Loop Cards and shall be addressed through individual numbers.
b) The Fire alarm control panel shall be able to obtain analogue value for all
detectors in the circuit through a pulsed digitalized current data.
c) The Fire alarm control panel shall be able to analyses all analogue inputs
from all addressable units, and through its own softw are and ambient level
screening the Fire alarm control panel shall be able to identify fire, possible
fire or fault conditions.
3.4.3 a) The Fire alarm control panel shall also give adequate warni ng signal
whenever there is dust accumulation in detectors.
b) It should be possible to change the level of ambient alarm calibration
condition by the use of software program.
3.4.4 a) Short / Open circuit fault shall also be reported at the Fire alarm control
panel.
b) In such cases, the system through the use of fault isolators shall be able to
isolate that segment.
3.4.5 a) The Fire alarm control panel shall have the facility to set each smoke
sensor sensitivity remotely.
b)It shall also be possible to set the sensitivity to a high level or low level
based on night or day time.(time based sensing)
3.4.6 a) When an alarm condition is sensed at the Fire alarm control panel from a
smoke or heat detector, a delay time/alarm verification period shall be started.
b) If the sensor is still in alarm after the delay time expires, an alarm condition
is reported.
3.4.7 The Fire alarm control panel shall have the facility to perform walk test.
3.4.8 In the walk test mode, the performance of each device is checked out by
initiating the device.
3.4.9 As each device is placed into alarm the Fire alarm control panel shall print
the condition and automatically reset the device.
3.4.11 If a zone is inadvertently left in walk test mode, it shall automatically reset to
normal after the idle time is exceeded.
3.4.12 During the walk test the zones other than the programmed zones shall be
under continuous supervision (normal mode).
3.4.13 In case of any alarm initiated by detector/devices the walk test shall get
terminated automatically.
3.4.15 Programming shall be carried out from the Fire alarm control panel keyboard
or utilizing the authorized laptop/desktop computer software.
3.4.16 The Fire alarm control panel shall have a Liquid Crystal Display of
Alphanumeric type.
3.4.17 The display should have high resolution, backlit 2 (lines) x 40 character.
3.4.18 In case of testing of the system from the Fire alarm control panel the Display
shall be able to give readouts of analogue value of all detectors
being tested.
3.4.19 The Fire alarm control panel shall also be able to carry out continuous self
monitoring when in normal condition.
3.4.20 The Fire alarm control panel shall have either an in -built or external printer
coupled to the Fire alarm control panel, which shall log all events with time.
3.4.21 The printout shall clearly indicate the event - Fire/Pre Alarm/Fault etc. With
the unit address and time.
3.4.22 The Fire alarm control panel shall also be able to discriminate between false
alarms and fire conditions.
3.4.23 The Fire alarm control panel shall carry out priority selection of alarm in case
alarm activities in two or more remotely located units simultaneously. In such
cases, the manual call stations shall have the highest priority.
3.4.24 The Fire alarm control panel shall also be able to actuate switches
automatically in case of Fire co ndition that of AHU’s and power supply or
other systems such as piped pressurized gas supply /Access control doors.
3.4.25 The System shall be fail safe and adequate safe guards should be ensured
that in the event of a failure of a part of the System it shall not handicap the
complete System.
3.4.26 The agency shall be responsible for preparation and installation of System
Software into the Fire Alarm Control Panel.
3.4.29 The system shall have the ability to be upgraded so as to incorporate more
features at a later date.
3.4.30 a)The Fire alarm control panel shall have its own Battery Backup of a
minimum of 40 hours in normal run and then half an hour in alarm condition.
b) The back up time calculation shall be done as per relevant standards and
produced for approval.
c) The Battery shall be 2*12V (24V) DC and of sealed lead acid rechargeable
maintenance free type, housed inside the FACP.
3.4.32 The voltage rating shall be from 14V DC to 31V DC, though the voltage may
be change.
3.4.33 a)The Fire alarm control panel shall be totally enclosed dust and vermin proof
type made of minimum 13 gauge dust inhibited sheet with even baked finish.
b) The Fire alarm control panel shall be of completely solid state design.
3.4.34 a) The logic circuitry shall be based on high noise immunity solid state
hardware employing modular construction.
3.4.36 The system shall be designed such that it shall be possible to add at least
20% of the Detectors for future expansion without extra cost on the panel.
3.4.37 a)The panel should have the facility to interface with an automatic two
channel programmable speech dialer for verbal reporting of fire.
b) Fire alarm control panel shall be able to call four telephone numbers per
channel.
c) The programmable speech dialer shall have two alarm inputs and shall
provide listen-in capabilities through the built-in microphone.
d) The dialer shall have a built -in keypad for easy operation, programming
and voice recording.
3.4.39 The fire alarm panel should be provided with IP integration card
3.5.1 a) All detectors shall be fitted with plug -in system type, from the maintenance
and compatibility point of views.
c) After resetting the alarm, the detector shall resume operations without
readjustment of any kind.
3.5.2. a) The detector shall have a Multisensor type integrates photoelectric smoke
and fixed temperature heat sensing technology.
b) It shall be possible to use a s ingle detector type for both above and below
false ceiling applications.
c) The detector shall be capable of detecting fast flaming fires and slow
smoldering fires equally well.
3.5.3 a)The detector shall be able to sense incipient fire by detecting the presence
of visible and invisible products of combustion.
b) The detector shall be suitable for low voltage (between 13 to 31V DC) two
wire supply.
d) The sensitivity of the detector shall not vary with change in ambient
temperature, humidity, pressure or voltage variation, air currents and should
not trigger the false alarm due to the above condition.
3.5.4 a) The detector shall be suitably protected against dust accumulation/ ingress.
b) The detector shall be free from maintenance and function ally tested at
periodic intervals.
3.5.5 a) The coverage per smoke detector shall strictly follow r elevant standards.
c) The sensitivity of detector shall be set from the Fire alarm control panel to
suit the site requirement.
B. HEAT DETECTOR
3.5.6 a) Heat detector shall go into the alarm mode when the temperature reaches
34degree Centigrade in normal course.
b) The operator (users) shall have the option of calling up the temperature
measured by the specific detector as and when required .
3. 5.7 a) It shall have in-built locking mechanism to check the removal and pilferage
of the detector.
b) The quiescent current flow must not exceed 400 micro amps and alarm
condition current shall be maximum 40 mille amps.
3.5.8 a) The heat detector shall be Analogue Addressable type and be able to send
analogue output to the Fire alarm control panel regarding its condition.
b) It shall be able to communicate with the Fire alarm control panel by the
pulses emitted from the Fire alarm control panel
3.5.9 a) The base of the Detector shall be electronics free and interchangeable with
other smoke or heat detec tors.
c) The voltage rating shall be between 15V -30V DC though the voltage may
be changed depending upon the working voltages of a proprietary FACP.
3.5.10 a) The Detector shall have UL approval.
b) It shall be possible to test the Detectors working both from the FACP as
well as locally.
3.5.11 a) It shall be possible to mount the detectors in Duct Casting Unit for
sampling of Supplying Air from the AHUs.
b) Secondary response indica tors shall be provided for all the Above False
Ceiling Detectors.
3.5.12 a) The detector shall have twin LED’s/Single LED for 380/180 degree viewing
angle.
b) LED on the detector shall blink each time the sensor is scanned by the Fire
alarm control panel.
c) If the Fire alarm control panel determines that the sensor is in alarm, the Fire
alarm control panel will command the sensor LED to remain on to indicate the
same.
d) Each sensor shall be capable of being tested for alarm via command from
the Fire alarm control panel
e) Each sensor shall respond to Fire alarm control scan with the information
about its type for identification.
3.6.1 a)The Manual call station shall be breakable type with suitable protection and
base box. .
b) The device shall be red in colour and suitable for surface or flush mounting.
3.6.2 a) The Manual Call Station shall be fully addressable with its own
addressable module and operated by digitized signals from the FACP.
3.7 SOUNDER
3.7.1 The sounder shall be addressable electronic type and shall give
discontinuous/ intermittent audible alarm whenever any detector or call box
operates.
3.7.2 The sound output from the Hooter should not be less than 85 decibels at one
meter.
3.7.3 The sounder shall be powered from Main Fire alarm control panel through
separate 2 wire cable.
3.8.1 FACP:
a) The FACP shall be visually checked for input voltage and ampere. All
zones one by one shall be de wired to check for fault signal indication in the
FACP.
b) The Power Source shall be cut off and checked for stand by Supply from
the Batteries. After six hours the FACP Source shall be switched on to check
for auto switch over to the Mains mode.
d) The FACP should indicate increased analogue output for that address and
after the programmed delay time, a fire alarm signal shall be indicated. This
delay shall be utilized for alarm verification.
a) The same tests in the same sequence shall be carried out for this detector
but with the application of hot air from a hair dryer.
a) One detector of each type will be disconnected and subjected to slow dust
build - up by means as desired by the Consultant/client and again connected
in the circuit.
b) Any part of the Loop shall be short circuited. The FACP shall indicate the
communication failure of all the devices connected in the short circuited
segment.
c) After the short circuit is corrected, the Fault Isolator shall return to its
normal status automatically, this being reflected in the FACP.
d) The Loop shall then be in normal operation again. Any part of the Loop
shall be de wired and tested as given above for open fault.
3.8.6 All other tests as required by the client at the time of handing over shall also
to be conducted
a) A mimic panel shall be provided at lobby indicating the location of fire. (For
design office)
d) The mimic panel shall be of adequate size to give clarity to the fire
protection personal and its size and layout be subject to the approval from
client.
• Alarm mode : flash and sound alarm, shut off gas valve and network
• alarm signal
• Detector type : Suitable for integrating with the existing Fire alarm loop.
5.0 Strob:
The strob light should have lamp supported from fire panel. The lamp shall be
fixed with reflector. This should be fixed in ceiling and wall as per the site
condition.
1.0 SCOPE
1.1 System
This specification describes a continuous duty, three -phase, on-line, solid-
state uninterruptible power supply system, hereafter referred to as the UPS.
2.2 Components
The UPS shall consist of the following components:
A. Converter
B. Chopper / Charger
G. Battery System
A. UPS Input
14) Overload Cap. (on inverter) 125% for 90 sec., 150% for
30 sec.
15) Overload Cap. (on bypass) 1000% for 10ms, 125% for 10
min.
C. Batteries
3) DC Voltage Range:
UPS Capacity 25 kVA
Nominal Voltage 360 VDC
Alarms Voltage(V low) 350 VDC
Shutdown Voltage (V min) 320 VDC
D. Environmental
A. UPS Enclosure
The UPS shall be in a freestanding, NEMA1 enclosure equipped
with
casters and leveling feet. The overall dimensions and weights
shall be as follows (without internal batteries ):
UPS Size Dimensions Weight
B. Cable Entry
The UPS shall be provided with cable entry from the bottom of
the UPS enclosure.
1) UPS On
2) Bypass Active
B. Maintainability
Calculated and demonstrated MTTR (Mean -Time-To-
Repair) shall be 30 minutes including time to diagnose
the problem and replace subassembly.
C. Warranty
The UPS system shall be provided with a comprehensive
three-year on-site warranty (when purchased with a
Factory-Authorized Start-up). The warranty shall cover
parts, labor, travel and freight for the UPS. The battery
system has a full 2 year warr anty with 3 year’s prorata
total of 5 year warranty. Typical on -site response time
shall be 4 hours (24 hours maximum). The warranty
period shall expire three years for UPS and two years for
the battery system from date of shipment from
manufacturer’s facility.
TECHNICAL SPECIFICATION OF DISTRIBUTION TRANSFORMER,
200 KVA, QTY-01 Nos.
1. SCOPE:
2. CLIMATIC CONDITION:
3. WINDINGS:
The HV and LV windings are shall be copper wound and suitable for
insulation system of class ‘ F’ and completely made of Cast Resin
Encapsulated under vacuum into moulds and to be a much higher degree
thermal short circuit resistant. The HV and LV windings o f per phase shall be
separately cast to form one rigid tubular coil, and no rigid keys shall be
present between their co -axial arrangements. The coil shall be non -
inflammable and are self -extinguishing.
OFF – LOAD Tap changer links with +/ - 7.5% in 2.5% on each side shall be
provided along with tap position indication. The locking arrangement sha ll be
provided for this if it is designed in out side the enclosure.
6. PROTECTION:
The Transformer windings shall be protected against the thermal over load in
two thermister system, one for warning and other for automatic switch off
when the permitted t emperature is exceeded. Any other protection is
applicable for this dry type Transformer as per IS specification 11171 & 2026
also to be provided. Measuring system of winding temperature also shall be
provided along with instrument.
7. ENCLOSURE:
Transformer shall be with a protective enclosure, so that the ambient Air to be
circulated so as to cool the core and winding. The enclosure shall be
confirming to IS 2147 of 1962.
8. TESTING:
All the Routine tests like voltage ratio test, temperature rise test, partial
discharge test, impedance voltage test etc. as mentioned in the IS
specification 11171 shall be carried out at the manufacturer works with the
presence of NRL Officials. For Type test such as lightning impulse test,
induced over voltage withstand t est, short circuit test, and other tests
mentioned in the IS specification 11171, a test report obtained from CPRI or
ERADA or other Government authorized agency for such model, type
transformer already manufactured by firm should be produced along with th e
store. The Transformer shall be free of partial discharge at least up to 12
times of the rated voltage and shall be resistant against atmosphere impulse
voltages.
9 STANDARD ACCESSORIES :
The following are shall be provided with the Transformer: - Bi-directional
rollers, Earthling terminals, lifting hooks 2Nos. and the Rating/name plate
details as per IS 11171, section 2.
c) Phases : Three.
d) Frequency : 50 Hz.
e) Enclosure : Enclosed Dry- Type Transformer.
f) Method of cooling : AN
LV SIDE : 433 V
n) Insulation Level: