Professional Documents
Culture Documents
Introduction
“A cofferdam is a temporary structure designed to keep water and/or soil out of the excavation in which a bridge pier
or other structure is built.”
A cofferdam is a temporary construction method used in order to do construction in wet excavations. It is installed in the
work area and water is pumped out to expose the bed of the body of water so that workers can construct structural
supports, perform repairs and any other types of work using construction equipment. A coffer dam is also called as
caisson in some parts of world.
Working inside a coffer dam can be dangerous if it is not installed properly or not safely pressurized. Various materials are
used for its construction and its design must be compatible with weather conditions, waves, currents, construction
equipment, construction methods, internal permanent structures and ground conditions. There are various types of
cofferdams such as braced, earth type, timber crib, double walled sheet pile and cellular .
Generally, major loads imposed on cofferdams are hydrostatic forces of water and dynamic forces due to current and
waves and heavy equipment is used for its construction such as pile drivers, cranes with clamshell buckets, concrete
pumps trucks as well as pumps for dewatering are used in the construction process. The effective management of
equipment on site as well as workers is an important step in cost control and maintaining efficient productivity.
2. Types of Cofferdam
Braced Timber Crib Double-Walled Sheet Pile Cellular Earth-Type
2.1 Braced Cofferdams
a- Formed from a single wall of sheet piling.
b- Driving sheet piles into the ground to
form a box around the excavation site
c -“box” is braced on the inside of it.
d - Interior is dewatering using pumps.
e - They are primarily used for bridge piers
in shallow water around 30-35ft depth.
5. Advantages of Cofferdam
• Allow excavation and construction of structures
in otherwise poor environment
• Provides safe environment to work
• Contractors typically have design responsibility
• Steel sheet piles are easily installed and removed
• Materials can typically be reused on other projects Force due to soil land
6. Installation of Cofferdam
The success of any piling scheme requires satisfactory
completion of the following stages.
• Competent site investigation, sampling and relevant
testing to build up an informed picture of the task.
• Adequate design of all the stages of the construction.
• Setting out and installation of the piles.
Hydrostatic pressure
Equipment’s:
• Pile driving hammer
Vibratory or Impact
• Crane of sufficient size-
clamshells and draglines
• Concrete pumps trucks
• Dewatering pumps
• Barges may be required Pile hammer Crane pile hammer Clamshells
• Dozer, loader, backhoe,
trucks be may required
Materials:
• Steel sheet piles are typically used
• H-piles and/or wide-flange beams
Sheet steel piling Dewatering pumps
for wales and stringers.
8. Cofferdam Components
• Sheet piling
• Bracing frame
• Concrete seal
• Bearing piles
Step 3 - Drive sheet piles to grade and ties are Step 4 - Excavate slightly below grade, while leaving the
provided for sheet piles at the top as necessary cofferdam full of water and drive bearing piles. Place
rockfill as a leveling and support course.
Step 5 -Place Tremie Concrete seal Step 6- Check blocking between bracing and sheets
and dewater
“Z” Type (U): Used for Larson / “U” Type (U): Used for Arch shaped & lightweight : Used for Flat / Straight Type (SA), (S):
Deep wall construction. applications similar to Z - Type shallower wall construction Used for filled cell construction
12- Safety
• good design 14- Application of coffer dam
• proper construction • Hydroelectric Dam Construction
• verification that the structure is • Bridge Construction
being constructed as planned • Ship repair
• monitoring the behavior of the • Oil Rig and Dam Construction
cofferdam and surrounding area • Sunken Vessel Recovery
provision of adequate access • Ship Recovery
• light and ventilation, and
• Attention to safe practices on the
part of all workers and supervisors 15- Disadvantages of cofferdams
• Special equipment required
13- Mode of failures • Relatively expensive
• Fabricated tees and wyes • Typically very time consuming & tedious
• Sheets and interlocks • If rushed, sheets can be driven out of
• Environmental condition locks or out of plumb
• Stability • When in flowing water “log jams” may
occur creating added stress on structure
16- Case Study
16 a- FORTH REPLACEMENT CROSSING. EDINBURGH
N1 Pier is the one located just adjacent to the northern tower being part of the cable-stayed section of the Firth of
Forth new bridge main crossing. It is located close to the northern shoreline and consists of a massive reinforced
concrete direct foundation, 26m x 29m and 5.5m deep, and is founded on Volcanic Tuff bedrock of the Sandy Craig
Formation.
This foundation is to be built in the dry. For making this possible, a temporary works structure had to be built in order
to resist the hydrostatic thrust forces.
Prefabrication of the cofferdam as opposed
to the more conventional form of
cofferdam construction by driving sheet
piles has the benefit of avoiding the
creation of airborne and underwater noise.
The method of pre excavation also removes
the risk of encountering obstructions.
The temporary works structure consisted
of a number of corrugated plates welded
side-by-side, arranged so the pier
foundation could be fit inside.
Location Structural elements of the cofferdam
The overall plan dimensions were 30m by 27m (transverse x longitudinal). Two levels of frames provide the required
stiffness to withstand the horizontal thrust forces.
The cofferdam rest on four bearing plates located at each corner at a level below the foundation bottom level. For
achieving this, a trench was excavated along the sides of the cofferdam prior to the cofferdam installation, which
were filled with concrete later on. This was required to provide the foundation of the cofferdam with the
corresponding water tightness, once it was dewatered.
The uplift forces were counterweight by a concrete plug beneath the foundation bottom level. Destressing wells
were also installed to minimize those forces.
3.Frame assembly: frames were typically compound 4.Cofferdam walls assembly: the cofferdam’s shorter
sections connected with intermediate plates. Sections walls were welded to form one piece, whereas the
were whether standard sections or welded beams longer walls were split in four and connected to the
shorter to for a half cofferdam
5. Internal de-stressing wells are then installed into the bedrock Concrete pouring of internal trench using underwater concrete (left) .
to lower the groundwater pressures below cofferdam and the Divers support during operation (right)
formation area.
In the initial stage of the construction materials like stone and earth fill was
brought to the site to dump in the upstream and downstream of the river in
large quantities to construct the sub weir. In this kind of construction the major
equipment’s used are excavators, dozers and dumpers. These dumpers dump the
stone on top of the embankment whereas dozers move across the flowing water
and also the earth fill material was dumped from top so that it settles down. But
during the built up of the cofferdam it should be monitored keenly time to time
Dumper unloading stones
thus to safe guard the area as well as to place the materials over the settled area
Material quantities for constructing a cofferdam:
Stone - 100,000 cft (3000m3)
Sheet piles - 224,000 sft (Area), 35 – 40 ft (Depth)
Sand bags - 60,000 No
Earth filling - 11.46 M cft (324,394 m3)
DEWATERING
EQUIPMENTS USED AND THEIR
PRODUCTIVITY ANALYSIS
EQUIPMENT USED:
Construction of cofferdam was carried out using heavy equipment’s
such as
Dozers. Loaders and Dump trucks.
Backhoe . Vibrating pile hammer.
Cofferdam with sheet Dewatering pumps- tube wells along with pumps and screens in
Construction of Sub – Weir the substrata.
piles during dewatering
In the process of construction of Sheet piles analysis and overall
coffer dam, the next step is Weight of the above mentioned machinery was around 10-
stability is calculated in a
dewatering. Dewatering method software called SEEP/W for 15 tons and can move freely on newly constructed
requires a lot of pumping of water cofferdam section seepage. embankment. First stone dump was constructed followed
with certain measures like maintain Thus a realistic model is by earthfill dump. To construct stone embankment, the
the water levels to a desired point. available where for different
dumper is used to dump stone in reverse on top of the
The main equipment’s used for parameters sensitivity analyses
dewatering are tube wells, pumps is done. Eventually based on embankment and dozer is used to move material across
and screens for concreting at flowing water.
these results a sheet pile is
required different areas of the installed.
compound.
PRODUCTIVITY ANALYSIS
PHRASE 1- STONE FILL LAYER AND EARTHFILL EMBANKMENT CONSTRUCTION
PHRASE 2 - SHEET PILE INSTALLATION
PHRASE3- DEWATERING USING PUMPS
PHRASE 4- EXCAVATION USING BACKHOE