You are on page 1of 38

Costruction Proxy

Building Item Cost Estimate

assumed OH+Profit=> 1.35


Item Description Unit Qty Direct Rate Bidding Rate Amount
01. EXCAVATION & EARTH WORK
Site clearing and removing of top 200mm
1 thick soil m2 1 21.77 29.40 29.40
3
2 Bulk excavation in expansive soil to a depth notmexceeding 1500
1 mm. 76.21 102.88 102.88
3 Ditto over 1.5m but not exceeding 3.0m m3 1 115.84 156.38 156.38
4 Trench excavation not exceeding 1.5m m3 1 76.21 102.88 102.88
Compaction fill shall be every 20cm thick
until it atains a minimum of 95% CBR with
5 Selected borrowed fill . m3 1 309.08 417.26 417.26
6 Disposal of excavated material and wast. m3 1 30.60 41.31 41.31
Sub Base
7 25cm thick hard core m3 1 197.41 266.50 266.50
Total to Summary Birr 1,116.62

03. CONCRETE WORK

xy
In Situ Concrete
1 Plain blinding concrete C-5 m3 1 1,751.52 2,364.55 2,364.55

ro
Reinforced sub structure concrete

np
Use ordinary Portland cement
2 C-25 in isolated footing m3 1 2,370.53 3,200.22 3,200.22
3 C-25 in foundation column m3
io
1 2,370.53 3,200.22 3,200.22
ct
4 C-25 in beam m3 1 2,370.53 3,200.22 3,200.22
ru
5 C-20 in slab (Ground floor) m3 1 2,288.95 3,090.08 3,090.08
st

Reinforced super structure concrete


Use ordinary Portland cement
on

6 C-25 in elecvation column m3 1 2,370.53 3,200.22 3,200.22


C

7 C-25 in beams m3 1 2,370.53 3,200.22 3,200.22


e/

8 C-25 in suspended slab m3 1 2,370.53 3,200.22 3,200.22


m3
.m

9 C-25 in stair case & landing 1 2,370.53 3,200.22 3,200.22


Form work
//t

Sub structure normal finish to:-


m2
s:

10 Isolated footing 1 200.81 271.10 271.10


11 Foundation column m2 1 200.81 271.10 271.10
tp

12 Beam m2 1 200.81 271.10 271.10


ht

Super structure normal finish to:-


13 Elevation column m2 1 200.81 271.10 271.10
14 Beams m2 1 200.81 271.10 271.10
15 Susspended slab m2 1 200.81 271.10 271.10
16 Staire case & landing m2 1 200.81 271.10 271.10
Reinforcement steel bar sub structure
17 Diameter, 8mm Kg 1 46.86 63.26 63.26
18 Diameter, 14mm Kg 1 46.86 63.26 63.26
19 Diameter, 16mm Kg 1 46.86 63.26 63.26
20 Diameter, 20mm Kg 1 46.86 63.26 63.26
21 Diameter, 24mm Kg 1 46.86 63.26 63.26
Super Structure
22 Diameter, 8mm Kg 1 46.86 63.26 63.26
23 Diameter, 10mm Kg 1 46.86 63.26 63.26
24 Diameter, 12mm Kg 1 46.86 63.26 63.26
25 Diameter, 14mm Kg 1 46.86 63.26 63.26
26 Diameter, 16mm Kg 1 46.86 63.26 63.26
27 Diameter, 20mm Kg 1 46.86 63.26 63.26
28 Diameter, 24mm Kg 1 46.86 63.26 63.26
29 In 8mm thick chip wood depth 10cm m 1 29.67 40.05 40.05
Total to Summary Birr 30,552.95
04. MASONRY WORK
Stone Wall
In cement mortar
1 Concealed from view m3 1 1,123.63 1,516.90 1,516.90
Exposed face for further finish (Roughly
2 dressed stone wall) m3 1 1,311.41 1,770.40 1,770.40
Concrete block works
Class "B" in cement mortar above grade
3 20cm thick both faces for plaster m2 1 201.90 272.56 272.56
4 15cm thick both faces for plaster m2 1 176.80 238.68 238.68
Total to Summary Birr 3,798.54

05. ROOFING
Galvanized steel sheet & accessories
1 CIS G-28 m2 1 383.07 517.15 517.15
2 0.4mm thick, girth 65cm m 1 310.53 419.22 419.22
3 G-28 Flat steel sheet copping m 1 310.53 419.22 419.22
Total To Summary Birr 1,355.59

06. CARPENTRY & JOINERY


Eucalyptus Truss
1 Diameter, 10cm m 1 63.63 85.90 85.90
2 Diameter, 8cm m 1 45.78 61.80 61.80

xy
Zigba Purlin -

ro
3 Size 5 x 7cm m 1 61.66 83.24 83.24
Soffit nailed to supports Chipwood ceiling

np
4 Acoustic ceiling m2 1 380.00 513.00 513.00

io
0.4mm thick Ribbed steel sheet (Check your
m2
ct
5 detail drawing) 1 467.81 631.55 631.55
Fascia board
ru

6 2.5 x 20cm Sawn Eucalyptus m 1 120.59 162.80 162.80


st

Band iron
on

7 6mm diameter, L = 1m pcs 1 10.00 13.50 13.50


Joinery
C

Flush wooden doors hard pine frame &


e/

Mahog ply wood 4mm thick play wood


.m

1.5mm thick black steel frame & rubber


silencer Door locks shall be of mortice type
//t

standard double cylinder type comply with


s:

ASTM or EN quality standard Price includes


tp

all accessories locks, hinges etc... all


complete work according to detail
ht

drawings
Door
8 Type D1 size 100 x 100cm No 1 4,106.46 5,543.72 5,543.72
Total to Summary Birr 7,095.50
10. ALMUNIUM WORK
Almunium framed windows & window doors.
_ Thickness of aluminium profiles should be
2mm thick and plate should be 3mm thick
Window
Price includes 5mm thick clear glass
1 Type W size 100 x 100cm No 1 2,012.50 2,716.88 2,716.88
Almunium Stair case hand rail & baluster
Complete all according to drawing m2 1 2,415.00 3,260.25 3,260.25
Total To Summary Birr 5,977.13
07. FINISHING
07.1 PLASTERING & POINTING
Two coats of plater
In cement mortar to internal surface of:-
1 Hollow concrete block work m2 1 123.21 166.33 166.33
2 Concrete vertical surface m2 1 123.21 166.33 166.33
3 Concrete soffit m2 1 147.85 199.59 199.59
Target Project Online Project

DATE 22/01/2020

Site clearing to Total direct


Item of work :1.1 a depth of 20cm cost 21.77 Engineering Assumptions Other than Standards & diferent reference if there is
m2/hr/cre
Performance/hr : 1.33 w Profit 0% 0.00

xy
Direct unit cost: 21.77 Overhead cost 0% 0.00 Labor DC EQ DC

ro
Total

np
Small plants and Aggregate unit
21.77
tools cost (2%) cost 18.95 2.83

io
21.77

ct
Material cost Labour cost Equipment cost

ru
Cost per Labour By Indexed Horly. Type Of Hrly.Rent

st
Type Of Material Unit QTY Rate Unit Trade No. U.F Hourly Cost Equipement NO UF al Rate HRLY COST

on
D. labour 2.00 1.00 12.60 25.20 Tools 2.00 1.00 1.88 3.76

C
e/
.m
//t
s:
tp
ht

Total Material Cost (A) - Total Labour Cost (B) 25.20 Total Equipment (A) 3.76

PREPARED BY:-H.O.Office Eng. CHEKED BY:-H.O.Office Eng.Head APPROVED BY:-General Manager


Target Project Online Project

DATE 22/01/2020

Bulk excavation
<= 1.50m in Total direct
Item of work :1.2 ordinary soil cost 76.21 Engineering Assumptions Other than Standards & diferent reference if there is
m3/hr/cr
Performance/hr : 0.38 ew Profit 0% 0.00

xy
Direct unit cost: 76.21 Overhead cost 0% 0.00 Labor DC EQ DC

ro
Total

np
Small plants and Aggregate unit
76.21
tools cost (2%) cost 66.32 9.89

io
76.21

ct
Material cost Labour cost Equipment cost

ru
Cost per Labour By Indexed Horly. Type Of Hrly.Rent

st
Type Of Material Unit QTY Rate Unit Trade No. U.F Hourly Cost Equipement NO UF al RATE HRLY COST

on
D. labour 2.00 1.00 12.60 25.20 Tools 2.00 1.00 1.88 3.76

C
e/
.m
//t
s:
tp
ht

Total Material Cost (A) - Total Labour Cost (B) 25.20 Total Equipment (C) 3.76

PREPARED BY:-H.O.Office Eng. CHEKED BY:-H.O.Office Eng.Head APPROVED BY:-General Manager


Target Project Online Project

DATE 22/01/2020

Bulk excavation
Item of work :1.3 in Soft Total direct
(a) Rock.<1.5m cost 115.84 Engineering Assumptions Other than Standards & diferent reference if there is
m3/hr/cr
Performance/hr : 0.25 ew Profit 0% 0.00

xy
Direct unit cost: 115.84 Overhead cost 0% 0.00 Labor DC EQ DC

ro
Total

np
Small plants and Aggregate unit
115.84
tools cost (2%) cost 100.80 15.04

io
115.84

ct
Material cost Labour cost Equipment cost

ru
Cost per Labour By Indexed Horly. Type Of Hrly.Rent

st
Type Of Material Unit QTY Rate Unit Trade No. U.F Hourly Cost Equipement NO UF al RATE HRLY COST

on
D. labour 2.00 1.00 12.60 25.20 Tools 2.00 1.00 1.88 3.76

C
e/
.m
//t
s:
tp
ht

Total Material Cost (A) - Total Labour Cost (B) 25.20 Total Equipment (C) 3.76

PREPARED BY:-H.O.Office Eng. CHEKED BY:-H.O.Office Eng.Head APPROVED BY:-General Manager


Target Project Online Project

DATE 22/01/2020

Ditto but in Hard Total direct


Item of work :1.6 rock < 1.50m cost 112.36 Engineering Assumptions Other than Standards & diferent reference if there is
m3/hr/cr
Performance/hr : 0.28 ew Profit 0% 0.00

xy
Direct unit cost: 112.36 Overhead cost 0% 0.00 Labor DC EQ DC

ro
Total

np
Small plants and Aggregate unit
112.36

io
tools cost (2%) cost 90.00 22.36 112.36

ct
Material cost Labour cost Equipment cost

ru
Cost per Labour By Indexed Horly. Type Of Hrly.Rent

st
Type Of Material Unit QTY Rate Unit Trade No. U.F Hourly Cost Equipement NO UF al RATE HRLY COST

on
D. labour 2.00 1.00 12.60 25.20 Tools 2.00 1.00 3.13 6.26

C
e/
.m
//t
s:
tp
ht

Total Material Cost (A) - Total Labour Cost (B) 25.20 Total Equipment (A) 6.26

PREPARED BY:-H.O.Office Eng. CHEKED BY:-H.O.Office Eng.Head APPROVED BY:-General Manager


Target Project Online Project

DATE 22/01/2020
Ditto but >
150cm but <
200cm.(HARD Total direct
Item of work :1.6 ROCK) cost 112.36 Engineering Assumptions Other than Standards & diferent reference if there is
m3/hr/cr
Performance/hr : 0.28 ew Profit 0% 0.00

xy
Direct unit cost: 112.36 Overhead cost 0% 0.00 Labor DC EQ DC

ro
Total

np
Small plants and Aggregate unit
112.36

io
tools cost (2%) cost 90.00 22.36 112.36

ct
Material cost Labour cost Equipment cost

ru
Cost per Labour By Indexed Horly. Type Of Hrly.Rent

st
Type Of Material Unit QTY Rate Unit Trade No. U.F Hourly Cost Equipement NO UF al RATE HRLY COST

on
D. labour 2.00 1.00 12.60 25.20 Tools 2.00 1.00 3.13 6.26

C
e/
.m
//t
s:
tp
ht

Total Material Cost (A) - Total Labour Cost (B) 25.20 Total Equipment (A) 6.26

PREPARED BY:-H.O.Office Eng. CHEKED BY:-H.O.Office Eng.Head APPROVED BY:-General Manager


Target Project Online Project

DATE 22/01/2020

Selected Total direct


Item of work :1.7 borrowed Fill cost 309.08 Engineering Assumptions Other than Standards & diferent reference if there is
m3/hr/cr
Performance/hr : 0.75 ew Profit 0% 0.00

xy
Direct unit cost: 309.08 Overhead cost 0% 0.00 Labor DC EQ DC

ro
Total

np
Small plants and Aggregate unit
309.08

io
tools cost (2%) cost 50.40 25.91 76.31

ct
Material cost Labour cost Equipment cost

ru
Cost per Labour By Indexed Horly. Type Of Hrly.Rent

st
Type Of Material Unit QTY Rate Unit Trade No. U.F Hourly Cost Equipement NO UF al RATE HRLY COST

on
Select Material M3 1.20 193.97 232.77 D. labour 3.00 1.00 12.60 37.80 Tools 2.00 1.00 1.88 3.76
plate Compactor
1.00 0.33 47.50 15.68

C
e/
.m
//t
s:
tp
ht

Total Material Cost (A) 232.77 Total Labour Cost (B) 37.80 Total Equipment (A) 19.44

PREPARED BY:-H.O.Office Eng. CHEKED BY:-H.O.Office Eng.Head APPROVED BY:-General Manager


Target Project Online Project

DATE 22/01/2020

Total direct
Item of work :1.9 Cart Away cost 30.60 Engineering Assumptions Other than Standards & diferent reference if there is
m3/hr/cr
Performance/hr : 110.00 ew Profit 0% 0.00

xy
Direct unit cost: 30.60 Overhead cost 0% 0.00 Labor DC EQ DC

ro
Total

np
Small plants and Aggregate unit
30.60

io
tools cost (2%) cost 2.48 28.12 30.60

ct
Material cost Labour cost Equipment cost

ru
Cost per Labour By Indexed Horly. Type Of Hrly.Rent

st
Type Of Material Unit QTY Rate Unit Trade No. U.F Hourly Cost Equipement NO UF al RATE HRLY COST

on
Loader Operator 1.00 1.00 71.50 71.50 Tools 1.00 1.00 3.13 3.13
Truck Driver 4.00 1.00 50.00 200.00 Loader 1.00 1.00 970.00 970.00

C
Daily Labor 1.00 0.10 12.6 1.26 Dum Truck 4.00 1.00 530.00 2120.00

e/
.m
//t
s:
tp
ht

Total Material Cost (A) - Total Labour Cost (B) 272.76 Total Equipment (A) 3,093.13

PREPARED BY:-H.O.Office Eng. CHEKED BY:-H.O.Office Eng.Head APPROVED BY:-General Manager


Target Project Online Project

DATE 22/01/2020

backfill with Total direct


Item of work :1.9 Aggregeta cost 852.87 Engineering Assumptions Other than Standards & diferent reference if there is
m3/hr/cr
Performance/hr : 0.63 ew Profit 0% 0.00

xy
Direct unit cost: 852.87 Overhead cost 0% 0.00 Labor DC EQ DC

ro
Total

np
Small plants and Aggregate unit
852.87

io
tools cost (2%) cost 81.37 125.21 206.57

ct
Material cost Labour cost Equipment cost

ru
Cost per Labour By Indexed Horly. Type Of Hrly.Rent

st
Type Of Material Unit QTY Rate Unit Trade No. U.F Hourly Cost Equipement NO UF al RATE HRLY COST

on
Aggregate m3 1.15 562.00 646.30 Mason 4.00 1.00 50.00 50.00 Tools 1.00 1.00 1.88 1.88
Daily Labor 1.00 0.10 12.60 1.26 Roller, Vibrator,1.00 0.20
2 drums 385.00 77.00

C
e/
.m
//t
s:
tp
ht

Total Material Cost (A) 646.30 Total Labour Cost (B) 51.26 Total Equipment (A) 78.88

PREPARED BY:-H.O.Office Eng. CHEKED BY:-H.O.Office Eng.Head APPROVED BY:-General Manager


Target Project Online Project

DATE 22/01/2020

Ditto but with Total direct


Item of work :1.9 fine sand cost 1075.85 Engineering Assumptions Other than Standards & diferent reference if there is
m3/hr/cr
Performance/hr : 0.13 ew Profit 0% 0.00

xy
Direct unit cost: 1075.85 Overhead cost 0% 0.00 Labor DC EQ DC

ro
Total

np
Small plants and Aggregate unit
1075.85

io
tools cost (2%) cost 317.38 14.46 331.85

ct
Material cost Labour cost Equipment cost

ru
Cost per Labour By Indexed Horly. Type Of Hrly.Rent

st
Type Of Material Unit QTY Rate Unit Trade No. U.F Hourly Cost Equipement NO UF al RATE HRLY COST

on
Fine Sand m3 1.20 620.00 744.00 Mason 4.00 1.00 50.00 40.00 Tools 1.00 1.00 1.88 1.88
Daily Labor 1.00 0.10 12.60 1.26

C
e/
.m
//t
s:
tp
ht

Total Material Cost (A) 744.00 Total Labour Cost (B) 41.26 Total Equipment (A) 1.88

PREPARED BY:-H.O.Office Eng. CHEKED BY:-H.O.Office Eng.Head APPROVED BY:-General Manager


Target Project Online Project

DATE 22/01/2020

25cm thick
basaltic hard Total direct
Item of work :2 core cost 197.41 Engineering Assumptions Other than Standards & diferent reference if there is
m2/hr/cr
Performance/hr : 5.00 ew Profit 0% 0.00

xy
Direct unit cost: 197.41 Overhead cost 0% 0.00 Labor DC EQ DC

ro
Total

np
Small plants and Aggregate unit
197.41

io
tools cost (2%) cost 45.04 1.25 46.29

ct
Material cost Labour cost Equipment cost

ru
Cost per Labour By Indexed Horly. Type Of Hrly.Rent

st
Type Of Material Unit QTY Rate Unit Trade No. U.F Hourly Cost Equipement NO UF al RATE HRLY COST

on
Basaltic Stone M3 0.35 431.76 151.12 Mason 1.00 4.00 50.00 200.00 Tools II 2.00 1.00 3.13 6.26
Daily Labor 2.00 1.00 12.60 25.20

C
e/
.m
//t
s:
tp
ht

Total Material Cost (A) 151.12 Total Labour Cost (B) 225.20 Total Equipment (A) 6.26

PREPARED BY:-H.O.Office Eng. CHEKED BY:-H.O.Office Eng.Head APPROVED BY:-General Manager


Target Project Online Project

DATE 22/01/2020

25cm thick
basaltic hard Total direct
Item of work :2 core cost 333.29 Engineering Assumptions Other than Standards & diferent reference if there is
m2/hr/cr
Performance/hr : 2.50 ew Profit 0% 0.00

xy
Direct unit cost: 333.29 Overhead cost 0% 0.00 Labor DC EQ DC

ro
Total

np
Small plants and Aggregate unit
333.29

io
tools cost (2%) cost 100.16 82.01 182.17

ct
Material cost Labour cost Equipment cost

ru
Cost per Labour By Indexed Horly. Type Of Hrly.Rent

st
Type Of Material Unit QTY Rate Unit Trade No. U.F Hourly Cost Equipement NO UF al RATE HRLY COST

on
Basaltic Stone M3 0.35 431.76 151.12 Mason 1.00 4.00 50.00 200.00 Tools II 4.00 1.00 3.13 12.52
Daily Labor 4.00 1.00 12.60 50.40 Roller, Vibrator,1.00 0.50
2 drums 385.00 192.50

C
e/
.m
//t
s:
tp
ht

Total Material Cost (A) 151.12 Total Labour Cost (B) 250.40 Total Equipment (A) 205.02

PREPARED BY:-H.O.Office Eng. CHEKED BY:-H.O.Office Eng.Head APPROVED BY:-General Manager


Target Project Online Project

DATE 22/01/2020
Ditto item
1.2,But
Exceeding 1.5 Total direct
Item of work :1.3 but < 3m cost 115.84 Engineering Assumptions Other than Standards & diferent reference if there is

m3/hr/cr
Performance/hr : 0.25 ew Profit 0% 0.00

xy
Direct unit cost: 115.84 Overhead cost 0% 0.00

ro
np
Small plants and Aggregate unit
115.84
tools cost (2%) cost

io
ct
Material cost Labour cost Equipment cost

ru
Cost per Labour By Indexed Horly. Type Of Hrly.Rent

st
Type Of Material Unit QTY Rate Unit Trade No. U.F Hourly Cost Equipement NO UF al RATE HRLY COST

on
D. labour 2.00 1.00 12.60 25.20 Tools 2.00 1.00 1.88 3.76

C
e/
.m
//t
s:
tp
ht

Total Material Cost (A) - Total Labour Cost (B) 25.20 Total Equipment (A) 3.76

PREPARED BY:-H.O.Office Eng. CHEKED BY:-H.O.Office Eng.Head APPROVED BY:-General Manager


Target Project Online Project

DATE 22/01/2020

Ditto item
1.2,But Total direct
Item of work :1.3 Exceeding 4.5 cost 115.84 Engineering Assumptions Other than Standards & diferent reference if there is

m3/hr/cr
Performance/hr : 0.25 ew Profit 0% 0.00

xy
Direct unit cost: 115.84 Overhead cost 0% 0.00

ro
np
Small plants and Aggregate unit
115.84
tools cost (2%) cost

io
ct
Material cost Labour cost Equipment cost

ru
Cost per Labour By Indexed Horly. Type Of Hrly.Rent

st
Type Of Material Unit QTY Rate Unit Trade No. U.F Hourly Cost Equipement NO UF al RATE HRLY COST

on
D. labour 2.00 1.00 12.60 25.20 Tools 2.00 1.00 1.88 3.76

C
e/
.m
//t
s:
tp
ht

Total Material Cost (A) - Total Labour Cost (B) 25.20 Total Equipment (A) 3.76

PREPARED BY:-H.O.Office Eng. CHEKED BY:-H.O.Office Eng.Head APPROVED BY:-General Manager


Target Project Online Project

DATE 22/01/2020

Total direct
Item of work :1.3 Fence Work cost 193.97 Engineering Assumptions Other than Standards & diferent reference if there is

m2/hr/cr
Performance/hr : 5.00 ew Profit 0% 0.00

xy
Direct unit cost: 193.97 Overhead cost 0% 0.00

ro
np
Small plants and Aggregate unit
193.97
tools cost (2%) cost

io
ct
Material cost Labour cost Equipment cost

ru
Cost per Labour By Indexed Horly. Type Of Hrly.Rent

st
Type Of Material Unit QTY Rate Unit Trade No. U.F Hourly Cost Equipement NO UF al RATE HRLY COST

on
ml
40x40x2.5mm angle iron 1.10 45.00 49.50 D. labour 4.00 1.00 15.80 63.20 Tools 3.00 1.00 1.88 5.64

C
barbed Wire ml 11.40 6.00 68.40 Carpenter II 2.00 1.00 50.00 100.00

Paint gall 0.01 540.00 2.70 e/


.m
concrete m3 0.02 2288.95 35.76
//t
s:

Excavation m3 0.02 76.21 1.71


tp

Fill m3 0.01 309.08 2.12


ht

Total Material Cost (A) 160.20 Total Labour Cost (B) 163.20 Total Equipment (A) 5.64

PREPARED BY:-H.O.Office Eng. CHEKED BY:-H.O.Office Eng.Head APPROVED BY:-General Manager


Target Project Online Project

DATE 22/01/2020

xy
ro
np
io
ct
ru
st
on
C
e/
.m
//t
s:
tp
ht

Pit excavation < Total direct


Item of work :1.3 1.50m cost 125.91 Engineering Assumptions Other than Standards & diferent reference if there is

PREPARED BY:-H.O.Office Eng. CHEKED BY:-H.O.Office Eng.Head APPROVED BY:-General Manager


Target Project Online Project

DATE 22/01/2020
m3/hr/cr
Performance/hr : 0.23 ew Profit 0% 0.00

Direct unit cost: 125.91 Overhead cost 0% 0.00


Small plants and Aggregate unit
tools cost (2%) cost 125.91

xy
Material cost Labour cost Equipment cost
Cost per Labour By Indexed Horly. Type Of Hrly.Rent

ro
Type Of Material Unit QTY Rate Unit Trade No. U.F Hourly Cost Equipement NO UF al RATE HRLY COST

np
D. labour 2.00 1.00 12.60 25.20 Tools 2.00 1.00 1.88 3.76

io
ct
ru
st
on
C
e/
.m
//t
s:
tp
ht

Total Material Cost (A) - Total Labour Cost (B) 25.20 Total Equipment (A) 3.76

Ditto but >


150cm but < Total direct
Item of work :1.4 300cm. cost 160.89 Engineering Assumptions Other than Standards & diferent reference if there is

PREPARED BY:-H.O.Office Eng. CHEKED BY:-H.O.Office Eng.Head APPROVED BY:-General Manager


Target Project Online Project

DATE 22/01/2020
m3/hr/cr
Performance/hr : 0.18 ew Profit 0% 0.00

Direct unit cost: 160.89 Overhead cost 0% 0.00

Small plants and Aggregate unit


160.89
tools cost (2%) cost

xy
Material cost Labour cost Equipment cost

ro
Cost per Labour By Indexed Horly. Type Of Hrly.Rent

np
Type Of Material Unit QTY Rate Unit Trade No. U.F Hourly Cost Equipement NO UF al RATE HRLY COST
D. labour 2.00 1.00 12.60 25.20 Tools 2.00 1.00 1.88 3.76

io
ct
ru
st
on
C
e/
.m
//t
s:
tp

Total Material Cost (A)


ht

- Total Labour Cost (B) 25.20 Total Equipment (A) 3.76

Excavation for
garaj toadepth Total direct
Item of work :1.5 1.7m cost 144.80 Engineering Assumptions Other than Standards & diferent reference if there is
m3/hr/cr
Performance/hr : 0.20 ew Profit 0% 0.00

PREPARED BY:-H.O.Office Eng. CHEKED BY:-H.O.Office Eng.Head APPROVED BY:-General Manager


Target Project Online Project

DATE 22/01/2020

Direct unit cost: 144.80 Overhead cost 0% 0.00

Small plants and Aggregate unit


tools cost (2%) cost 144.80
Material cost Labour cost Equipment cost
Cost per Labour By Indexed Horly. Type Of Hrly.Rent

xy
Type Of Material Unit QTY Rate Unit Trade No. U.F Hourly Cost Equipement NO UF al RATE HRLY COST

ro
D. labour 2.00 1.00 12.60 25.20 Tools 2.00 1.00 1.88 3.76

np
io
ct
ru
st
on
C
e/
.m
//t
s:
tp

Total Material Cost (A) - Total Labour Cost (B) 25.20 Total Equipment (A) 3.76
ht

Trench
Excavation to Total direct
Item of work :1.6 adepth of 120cm cost 115.84 Engineering Assumptions Other than Standards & diferent reference if there is
m3/hr/cr
Performance/hr : 0.25 ew Profit 0% 0.00

Direct unit cost: 115.84 Overhead cost 0% 0.00

PREPARED BY:-H.O.Office Eng. CHEKED BY:-H.O.Office Eng.Head APPROVED BY:-General Manager


Target Project Online Project

DATE 22/01/2020

Small plants and Aggregate unit


tools cost (2%) cost 115.84
Material cost Labour cost Equipment cost
Cost per Labour By Indexed Horly. Type Of Hrly.Rent
Type Of Material Unit QTY Rate Unit Trade No. U.F Hourly Cost Equipement NO UF al RATE HRLY COST
D. labour 2.00 1.00 12.60 25.20 Tools 2.00 1.00 1.88 3.76

xy
ro
np
io
ct
ru
st
on
C
e/
.m
//t

Total Material Cost (A) - Total Labour Cost (B) 25.20 Total Equipment (A) 3.76
s:
tp

Total direct
ht

Back fill (From


Item of work :1.8 Site), cost 55.41 Engineering Assumptions Other than Standards & diferent reference if there is
m3/hr/cr
Performance/hr : 0.75 ew Profit 0% 0.00

Direct unit cost: 55.41 Overhead cost 0% 0.00

PREPARED BY:-H.O.Office Eng. CHEKED BY:-H.O.Office Eng.Head APPROVED BY:-General Manager


Target Project Online Project

DATE 22/01/2020

Small plants and Aggregate unit


tools cost (2%) cost 55.41
Material cost Labour cost Equipment cost
Cost per Labour By Indexed Horly. Type Of Hrly.Rent
Type Of Material Unit QTY Rate Unit Trade No. U.F Hourly Cost Equipement NO UF al RATE HRLY COST

xy
3
Select Material M 1.20 - D. labour 3.00 1.00 12.60 37.80 Tools 2.00 1.00 1.88 3.76

ro
plate Compactor
1.00 1.00 0.00 0.00

np
io
ct
ru
st
on
C
e/
.m
//t

Total Material Cost (A) - Total Labour Cost (B) 37.80 Total Equipment (A) 3.76
s:
tp
ht

PREPARED BY:-H.O.Office Eng. CHEKED BY:-H.O.Office Eng.Head APPROVED BY:-General Manager


Target Project Online Project

DATE 22/01/2020

C-5 lean
Item of work concrete 50mm Total direct
:1.12 thick cost 1,751.52
m3/hr/c
Performance/hr 1.25 rew Profit 0% 0.00

xy
Direct unit cost: 1,751.52 Overhead cost 0% 0.00 Labor DC EQ DC

ro
Total
Aggregate unit

np
Tools cost (2%) cost 1,751.52 475.20 78.04 553.24 per/m2

io
Material cost Labour cost Equipment cost

ct
ru
Cost per Labour By Indexed Horly. Hrly Rental HRLY

st
Material Unit QTY Rate Unit Trade No. U.F Hourly Cost Cost Equipt. NO UF RATE COST

on
Cement qtl 1.575 292.65 460.92 Mason 1.00 1.00 50.00 50.00 Mixer 1.00 1.00 66.25 66.25

C
Sand m3 0.50 620.00 312.48 Mixer opr
e/ 1.00 1.00 40.00 40.00
.m
Agregate m3 0.76 562.00 424.87 D.labour 40.00 1.00 12.60 504.00 Tools II 10.00 1.00 3.13 31.30
//t
s:
tp
ht

Total Material Cost (A) 1,198.28 Total Labour Cost (B) 594.00 Total Equipment (A) 97.55

PREPARED BY:-H.O.Office Eng. CHEKED BY:-H.O.Office Eng.Head APPROVED BY:-General Manager


Target Project Online Project

DATE 22/01/2020

Item of work
:3.1 C-20 concrete Total direct cost 2288.95
m3/hr/c
Performance/hr : 1.50 rew Profit 0% 0.00

Direct unit cost: 2288.95 Overhead cost 0% 0.00 Labor DC EQ DC Total

xy
Small plants and Aggregate unit
tools cost (2%) cost 2288.95

ro
415.33 103.80 519.13 per/m2

np
Material cost Labour cost Equipment cost

io
ct
Cost per Labour By Indexed Horly. Type Of Hrly.Rental HRLY

ru
Type Of Material Unit QTY Rate Unit Trade No. U.F Hourly Cost Cost Equipement NO UF RATE COST

st
Cement Qtl 3.36 292.65 983.30 Mason II 1.00 0.50 50 25.00 Mixer 1.00 1.00 96.25 96.25

on
Agregate m3 0.81 562.00 453.20 D.labour 40.00 1.00 12.60 504.00 Tools II 15.00 1.00 3.13 46.95
Sand m3 0.54 620.00 333.31 Mixer opr 1.00 1.00 40 40.00 Vibrator 1.00 1.00 12.50 12.50

C
vib. Opret 1.00 1.00 24 24.00
Barbender
e/ 1.00 0.10 50.00 5.00
.m
Carp.1 1.00 0.10 50.00 5.00
//t

G.leader 1.00 1.00 20 20.00


s:
tp
ht

Total Material Cost (A) 1,769.81 Total Labour Cost (B) 623.00 Total Equipment (A) 155.70

PREPARED BY:-H.O.Office Eng. CHEKED BY:-H.O.Office Eng.Head APPROVED BY:-General Manager


Target Project Online Project

DATE 22/01/2020

Item of work C-20 concrete


:3.1 with re-bar Total direct cost 3495.27
m3/hr/c
Performance/hr : 1.50 rew Profit 0% 0.00

Direct unit cost: 3495.27 Overhead cost 0% 0.00 Labor DC EQ DC

xy
Total
Small plants and Aggregate unit

ro
tools cost (2%) cost 3495.27 415.33 103.80 519.13 0

np
Material cost Labour cost Equipment cost

io
ct
Cost per Labour By Indexed Horly. Type Of Hrly.Rental HRLY

ru
Type Of Material Unit QTY Rate Unit Trade No. U.F Hourly Cost Cost Equipement NO UF RATE COST

st
Cement Qtl 3.20 292.65 936.48 Mason II 1.00 0.50 50 25.00 Mixer 1.00 1.00 96.25 96.25

on
Agregate m3 0.75 562.00 421.50 D.labour 40.00 1.00 12.60 504.00 Tools II 15.00 1.00 3.13 46.95
Sand m3 0.45

C
620.00 279.00 Mixer opr 1.00 1.00 40 40.00 Vibrator 1.00 1.00 12.50 12.50

e/
Rebar kg 28.84 46.44 1,339.15 vib. Opret 1.00 1.00 24 24.00
.m
Barbender 1.00 0.10 50.00 5.00
Carp.1 1.00 0.10 50.00 5.00
//t

G.leader 1.00 1.00 20 20.00


s:
tp
ht

Total Material Cost (A) 2,976.13 Total Labour Cost (B) 623.00 Total Equipment (A) 155.70

PREPARED BY:-H.O.Office Eng. CHEKED BY:-H.O.Office Eng.Head APPROVED BY:-General Manager


Target Project Online Project

DATE 22/01/2020

Item of work
:3.1 C-25 concrete Total direct cost 2370.53
m3/hr/c
Performance/hr : 1.50 rew Profit 0% 0.00

Direct unit cost: 2370.53 Overhead cost 0% 0.00 Labor DC EQ DC Total

xy
Small plants and Aggregate unit
tools cost (2%) cost 2370.53

ro
331.33 136.64 467.97

np
Material cost Labour cost Equipment cost

io
ct
Cost per Labour By Indexed Horly. Type of Hrly.Rental HRLY

ru
Type Of Material Unit QTY Rate Unit Trade No. U.F Hourly Cost Cost Equipement NO UF RATE COST

st
Cement Qtl 3.78 292.65 1,106.22 Mason II 1.00 0.50 50 25.00 Mixer 1.00 1.00 96.25 96.25

on
Agregate m3 0.82 562.00 458.86 D.labour 30.00 1.00 12.60 378.00 Tools II 15.00 1.00 3.13 46.95
Sand m3 0.54 620.00 337.48 Mixer opr 1.00 1.00 40 40.00 Vibrator 2.00 1.00 30.88 61.76

C
Vib. Opret 1.00 1.00 24 24.00
Barbender
e/ 1.00 0.10 50.00 5.00
.m
Carp.1 1.00 0.10 50.00 5.00
//t

G.leader 1.00 1.00 20 20.00


s:
tp
ht

Total Material Cost (A) 1,902.56 Total Labour Cost (B) 497.00 Total Equipment (A) 204.96

PREPARED BY:-H.O.Office Eng. CHEKED BY:-H.O.Office Eng.Head APPROVED BY:-General Manager


Target Project Online Project

DATE 22/01/2020

Item of work Total direct


:5.1 Form work cost 200.81
m2/hr/c
Performance/hr : 1.25 rew Profit 0% 0.00

Direct unit cost: 200.81 Overhead cost 0% 0.00 Labor DC EQ DC Total


Small plants and Aggregate unit

xy
tools cost (2%) cost 200.81 60.16 10.02 70.18

ro
Material cost Labour cost Equipment cost

np
Cost per Labour By Indexed Horly. Type Of Hrly.Rental HRLY

io
Type Of Material Unit QTY Rate Unit Trade No. U.F Hourly Cost Cost Equipement NO UF RATE COST

ct
Wooden timber m3 0.03 2000.00 50.00 Carpenter II 1.00 1.00 50.00 50.00 Tools II 4.00 1.00 3.13 12.52
Pcs 1.00

ru
Eucaly. Dia. 6 cm 20.05 20.05 D.labour 2.00 1.00 12.60 25.20
Eucaly. Dia. 8cm Pcs 1.50 25.05 37.58

st
Eucaly. Dia. 10cm Pcs 0.75 16.68 12.51

on
Nails kg 0.20 45.00 9.00

C
Mould Oil lit 0.06 20.00 1.20
Black wire 2.5mm kg 0.01 29.00 0.29
e/
.m
//t
s:
tp
ht

Total Material Cost (A) 130.64 Total Labour Cost (B) 75.20 Total Equipment (A) 12.52

PREPARED BY:-H.O.Office Eng. CHEKED BY:-H.O.Office Eng.Head APPROVED BY:-General Manager


Target Project Online Project

DATE 22/01/2020
Rebar
cutting,bending &
Item of work place in
:5.1 position(6mm) Total direct cost 44.70
kg/hr/c
Performance/hr : 20 rew Profit 0% 0.00

Direct unit cost: 44.70 Overhead cost 0% 0.00 Labor DC EQ DC

xy
Total
Small plants and Aggregate unit

ro
tools cost (2%) cost 44.70 3.76 0.47 4.23

np
Material cost Labour cost Equipment cost

io
Cost per Labour By Indexed Horly. Type Of Hrly.Rental HRLY

ct
Type Of Material Unit QTY Rate Unit Trade No. U.F Hourly Cost Cost Equipement NO UF RATE COST

ru
Rebar kg 1.10 36.00 39.60 D.labour 2.00 1.00 12.60 25.20 Tools II 3.00 1.00 3.13 9.39

st
kg
Tying wire diam. 1.5mm 0.03 29.00 0.87 Barbender 1.00 1.00 50.00 50.00

on
C
e/
.m
//t
s:
tp
ht

Total Material Cost (A) 40.47 Total Labour Cost (B) 75.20 Total Equipment (A) 9.39

PREPARED BY:-H.O.Office Eng. CHEKED BY:-H.O.Office Eng.Head APPROVED BY:-General Manager


Target Project Online Project

DATE 22/01/2020
Rebar
cutting,bending &
Item of work place in position
:5.1 8mm Total direct cost 46.44
kg/hr/c
Performance/hr : 22.50 rew Profit 0% 0.00

Direct unit cost: 46.44 Overhead cost 0% 0.00 Labor DC EQ DC

xy
Total
Small plants and Aggregate unit

ro
tools cost (2%) cost 46.44 3.34 0.42 3.76

np
Material cost Labour cost Equipment cost

io
Cost per Labour By Indexed Horly. Type Of Hrly.Rental HRLY

ct
Type Of Material Unit QTY Rate Unit Trade No. U.F Hourly Cost Cost Equipement NO UF RATE COST

ru
Rebar m3 1.15 36.11 41.52 D.labour 2.00 1.00 12.60 25.20 Tools II 3.00 1.00 3.13 9.39

st
Black wire 1.5mm Pcs 0.04 29.00 1.16 Barbender 1.00 1.00 50.00 50.00

on
C
e/
.m
//t
s:
tp
ht

Total Material Cost (A) 42.68 Total Labour Cost (B) 75.20 Total Equipment (A) 9.39

PREPARED BY:-H.O.Office Eng. CHEKED BY:-H.O.Office Eng.Head APPROVED BY:-General Manager


Target Project Online Project

DATE 22/01/2020
Rebar
cutting,bending &
Item of work place in position
:5.1 10mm Total direct cost 46.33
kg/hr/c
Performance/hr : 25.00 rew Profit 0% 0.00

Direct unit cost: 46.33 Overhead cost 0% 0.00 Labor DC EQ DC

xy
Total
Small plants and Aggregate unit

ro
tools cost (2%) cost 46.33 3.01 0.38 3.38

np
Material cost Labour cost Equipment cost

io
Cost per Labour By Indexed Horly. Type Of Hrly.Rental HRLY

ct
Type Of Material Unit QTY Rate Unit Trade No. U.F Hourly Cost Cost Equipement NO UF RATE COST

ru
Rebar m3 1.15 36.08 41.49 D.labour 2.00 1.00 12.60 25.20 Tools II 3.00 1.00 3.13 9.39

st
Black wire 1.5mm Pcs 0.05 29.00 1.45 Barbender 1.00 1.00 50.00 50.00

on
C
e/
.m
//t
s:
tp
ht

Total Material Cost (A) 42.94 Total Labour Cost (B) 75.20 Total Equipment (A) 9.39

PREPARED BY:-H.O.Office Eng. CHEKED BY:-H.O.Office Eng.Head APPROVED BY:-General Manager


Target Project Online Project

DATE 22/01/2020
Rebar
cutting,bending &
Item of work place in position
:5.1 12mm Total direct cost 46.38
kg/hr/c
Performance/hr : 27.50 rew Profit 0% 0.00

Direct unit cost: 46.38 Overhead cost 0% 0.00 Labor DC EQ DC

xy
Total
Small plants and Aggregate unit

ro
tools cost (2%) cost 46.38 2.28 0.34 2.62

np
Material cost Labour cost Equipment cost

io
Cost per Labour By Indexed Horly. Type Of Hrly.Rental HRLY

ct
Type Of Material Unit QTY Rate Unit Trade No. U.F Hourly Cost Cost Equipement NO UF RATE COST

ru
Rebar m3 1.15 36.04 41.44 D.labour 2.00 1.00 0.00 12.60 Tools II 3.00 1.00 3.13 9.39

st
Black wire 1.5mm Pcs 0.08 29.00 2.32 Barbender 1.00 1.00 50.00 50.00

on
C
e/
.m
//t
s:
tp
ht

Total Material Cost (A) 43.76 Total Labour Cost (B) 62.60 Total Equipment (A) 9.39

PREPARED BY:-H.O.Office Eng. CHEKED BY:-H.O.Office Eng.Head APPROVED BY:-General Manager


Target Project Online Project

DATE 22/01/2020
Rebar
cutting,bending &
Item of work place in position
:5.1 14mm Total direct cost 46.41
kg/hr/c
Performance/hr : 27.50 rew Profit 0% 0.00

Direct unit cost: 46.41 Overhead cost 0% 0.00 Labor DC EQ DC

xy
Total
Small plants and Aggregate unit

ro
tools cost (2%) cost 46.41 2.28 0.34 2.62

np
Material cost Labour cost Equipment cost

io
Cost per Labour By Indexed Horly. Type Of Hrly.Rental HRLY

ct
Type Of Material Unit QTY Rate Unit Trade No. U.F Hourly Cost Cost Equipement NO UF RATE COST

ru
Rebar m3 1.15 36.06 41.47 D.labour 2.00 1.00 0.00 12.60 Tools II 3.00 1.00 3.13 9.39

st
Black wire 1.5mm Pcs 0.08 29.00 2.32 Barbender 1.00 1.00 50.00 50.00

on
C
e/
.m
//t
s:
tp
ht

Total Material Cost (A) 43.79 Total Labour Cost (B) 62.60 Total Equipment (A) 9.39

PREPARED BY:-H.O.Office Eng. CHEKED BY:-H.O.Office Eng.Head APPROVED BY:-General Manager


Target Project Online Project

DATE 22/01/2020
Rebar
cutting,bending &
Item of work place in position
:5.1 16mm Total direct cost 46.86
kg/hr/c
Performance/hr : 27.50 rew Profit 0% 0.00

Direct unit cost: 46.86 Overhead cost 0% 0.00 Labor DC EQ DC

xy
Total
Small plants and Aggregate unit

ro
tools cost (2%) cost 46.86 2.73 0.34 3.08

np
Material cost Labour cost Equipment cost

io
Cost per Labour By Indexed Horly. Type Of Hrly.Rental HRLY

ct
Type Of Material Unit QTY Rate Unit Trade No. U.F Hourly Cost Cost Equipement NO UF RATE COST

ru
Rebar m3 1.15 36.05 41.46 D.labour 2.00 1.00 12.60 25.20 Tools II 3.00 1.00 3.13 9.39

st
Black wire 1.5mm Pcs 0.08 29.00 2.32 Barbender 1.00 1.00 50.00 50.00

on
C
e/
.m
//t
s:
tp
ht

Total Material Cost (A) 43.78 Total Labour Cost (B) 75.20 Total Equipment (A) 9.39

PREPARED BY:-H.O.Office Eng. CHEKED BY:-H.O.Office Eng.Head APPROVED BY:-General Manager


Target Project Online Project

DATE 22/01/2020

Item of work
:3.1 Expantion Joint Total direct cost 29.67
ml/hr/c
Performance/hr : 5.00 rew Profit 0% 0.00

Direct unit cost: 29.67 Overhead cost Labor DC EQ DC

xy
0% 0.00 Total
Small plants and Aggregate unit

ro
tools cost (2%) cost 29.67 7.32 1.25 8.57

np
io
Material cost Labour cost Equipment cost

ct
Cost per Labour By Indexed Horly. Type Of Hrly.Rental HRLY

ru
Type Of Material Unit QTY Rate Unit Trade No. U.F Hourly Cost Cost Equipement NO UF RATE COST

st
Exp.Joint pcs 0.08 250.00 19.10 Tools II 2.00 1.00 3.13 6.26

on
Olio lit 0.10 20.00 2.00 D.labour 2.00 1.00 15.80 31.60

C
Carp.1 1.00 0.10 50.00 5.00

e/
.m
//t
s:
tp
ht

Total Material Cost (A) 21.10 Total Labour Cost (B) 36.60 Total Equipment (A) 6.26

PREPARED BY:-H.O.Office Eng. CHEKED BY:-H.O.Office Eng.Head APPROVED BY:-General Manager


Target Project Online Project

Complite work of DATE 22/01/2020


ground slab (for
Item of work comparision
:3.1 only(+) Total direct cost 628.32
ml/hr/c
Performance/hr : 1.00 rew Profit 0% 0.00

Direct unit cost: 628.32 Overhead cost Labor DC EQ DC

xy
0% 0.00 Total
Small plants and Aggregate unit

ro
tools cost (2%) cost 628.32 0.00 0.00 0.00

np
io
Material cost Labour cost Equipment cost

ct
Cost per Labour By Indexed Horly. Type Of Hrly.Rental HRLY

ru
Type Of Material Unit QTY Rate Unit Trade No. U.F Hourly Cost Cost Equipement NO UF RATE COST

st
Excavation M3 0.50 76.21 38.11

on
FILL M3 0.25 309.08 77.27
hard core M2 0.60

C
197.41 118.45

e/
Concrete M3 0.10 3495.27 349.53
.m
Cart away M3 0.50 30.60 15.30
Exp.Joint ML 1.00 29.67 29.67
//t
s:
tp
ht

Total Material Cost (A) 628.32 Total Labour Cost (B) - Total Equipment (A) -

PREPARED BY:-H.O.Office Eng. CHEKED BY:-H.O.Office Eng.Head APPROVED BY:-General Manager


Target Project Online Project

DATE 22/01/2020
Item of work C-15 290 kg
:3.1 cment /m3.. Total direct cost 1669.84
m3/hr/c
Performance/hr : 2.13 rew Profit 0% 0.00

Direct unit cost: 1669.84 Overhead cost 0% 0.00

xy
Small plants and Aggregate unit
tools cost (2%) cost 1669.84

ro
np
Material cost Labour cost Equipment cost

io
Cost per Labour By Indexed Horly. Type Of Hrly.Rental HRLY

ct
Type Of Material Unit QTY Rate Unit Trade No. U.F Hourly Cost Cost Equipement NO UF RATE COST

ru
Cement Qtl 2.90 240.65 697.88 Mason II 1.00 0.50 50 25.00 Mixer 1.00 1.00 96.25 96.25

st
Agregate m3 0.75 562.00 421.50 D.labour 20.00 1.00 15.8 316.00 Tools II 15.00 1.00 3.13 46.95

on
Sand m3 0.45 620.00 279.00 Mixer opr 1.00 1.00 40 40.00

C
vib. Opret 1.00 1.00 24 24.00
Barbender
e/ 1.00 0.10 50.00 5.00
.m
Carp.1 1.00 0.10 50.00 5.00
//t

G.leader 1.00 1.00 20 20.00


s:
tp
ht

Total Material Cost (A) 1,398.38 Total Labour Cost (B) 435.00 Total Equipment (A) 143.20

PREPARED BY:-H.O.Office Eng. CHEKED BY:-H.O.Office Eng.Head APPROVED BY:-General Manager


Target Project Online Project

DATE 22/01/2020

Item of work C-20 concrete


:3.1 +Exp.Joint Total direct cost 1930.37
m3/hr/c
Performance/hr : 2.00 rew Profit 0% 0.00

Direct unit cost: 1930.37 Overhead cost Labor DC EQ DC

xy
0% 0.00 Total
Small plants and Aggregate unit

ro
tools cost (2%) cost 1930.37 185.50 77.85 263.35

np
io
Material cost Labour cost Equipment cost

ct
Cost per Labour By Indexed Horly. Type Of Hrly.Rental HRLY

ru
Type Of Material Unit QTY Rate Unit Trade No. U.F Hourly Cost Cost Equipement NO UF RATE COST

st
Cement Qtl 3.20 292.65 936.48 Mason II 1.00 0.50 50 25.00 Mixer 1.00 1.00 96.25 96.25

on
Agregate m3 0.75 562.00 421.50 D.labour 20.00 1.00 12.60 252.00 Tools II 15.00 1.00 3.13 46.95
Sand m3 0.45

C
620.00 279.00 Mixer opr 1.00 1.00 40 40.00 Vibrator 1.00 1.00 12.50 12.50

e/
Exp.Joint pcs 0.10 250.00 26.04 vib. Opret 1.00 1.00 24 24.00
.m
Olio lit 0.20 20.00 4.00 Barbender 1.00 0.10 50.00 5.00
Carp.1 1.00 0.10 50.00 5.00
//t

G.leader 1.00 1.00 20 20.00


s:
tp
ht

Total Material Cost (A) 1,667.02 Total Labour Cost (B) 371.00 Total Equipment (A) 155.70

PREPARED BY:-H.O.Office Eng. CHEKED BY:-H.O.Office Eng.Head APPROVED BY:-General Manager


Target Project Online Project

DATE 22/01/2020
Item of work C-15 290 kg
:3.1 cment /m3.. Total direct cost 1820.64
m3/hr/c
Performance/hr : 2.13 rew Profit 0% 0.00

Direct unit cost: 1820.64 Overhead cost 0% 0.00

xy
Small plants and Aggregate unit
tools cost (2%) cost 1820.64

ro
np
Material cost Labour cost Equipment cost

io
Cost per Labour By Indexed Horly. Type Of Hrly.Rental HRLY

ct
Type Of Material Unit QTY Rate Unit Trade No. U.F Hourly Cost Cost Equipement NO UF RATE COST

ru
Cement Qtl 2.90 292.65 848.68 Mason II 1.00 0.50 50 25.00 Mixer 1.00 1.00 96.25 96.25

st
Agregate m3 0.75 562.00 421.50 D.labour 20.00 1.00 15.8 316.00 Tools II 15.00 1.00 3.13 46.95

on
Sand m3 0.45 620.00 279.00 Mixer opr 1.00 1.00 40 40.00

C
vib. Opret 1.00 1.00 24 24.00
Barbender
e/ 1.00 0.10 50.00 5.00
.m
Carp.1 1.00 0.10 50.00 5.00
//t

G.leader 1.00 1.00 20 20.00


s:
tp
ht

Total Material Cost (A) 1,549.18 Total Labour Cost (B) 435.00 Total Equipment (A) 143.20

PREPARED BY:-H.O.Office Eng. CHEKED BY:-H.O.Office Eng.Head APPROVED BY:-General Manager

You might also like