Professional Documents
Culture Documents
Unit 1
1. Explain the necessity and scope of irrigation.
Necessity of irrigation: 8
1.Less rainfall :
Total rainfall is less- artificial supply is necessary
2. Non uniform rainfall:
Less yield or the crop may die
3. Commercial crops with additional water:
More water may be necessary for raising commercial and cash crops
4. Controlled water supply:
Proper distribution system, the yield of the crop may be increased.
Benefits of irrigation:
Definition 2
Duty represents the irrigating capacity of a unit of water. It is the relation between the area of a crop irrigated
and the quantity of irrigation water required during the entire period of the growth of that crop.
3. Method of cultivation:
Ploughed -retention capacity-increasing the duty.
4. Time and frequency of tilling:
evaporation losses from the surface of soil is less- properly aerated, and hence the yield of crop is also better
6. Base period of the crop: If the base period of the crop is more, the amount of water required will be high,
hence duty will be low.
8. Quality of water:
Salt-content and alkali - water have to be applied to leach off the salts - reduces the duty.
More fertilizing matter -less consumption of water- increase duty.
Efficiency of water-storage. It is the ratio of the water stored in the root zone during irrigation to the water
needed in the root zone prior to irrigation (i.e. field capacity existing moisture content). It may be
represented by ηs
water stored in the root zone during irrigation
ηs= water needed in the root zone prior to irrigation
Efficiency of water use. It is the ratio of the water beneficially used, including leaching water, to the quantity
of water delivered. It may be represented by η u.
water beneficially used,including leaching water
ηu= quantity of water delivered
Uniformity coefficient or Water distribution efficiency. The effectiveness of irrigation may also be
measured by its water distribution efficiency ηd which is defined below where ηd= Water distribution
efficiency.
𝑑
ηd= (1- 𝐷)
D = Mean depth of water stored during irrigation. d= Average of the absolute values of deviations from the
mean.
6. A water course has culturable commanded area of 2600 hectares, out of which the intensities of
irrigation for perennial sugar-cane and rice crops are 20% and 40% respectively. The duty for these
crops at the head of water course is 750 hectares/cumec and 1800 hectares/cumec respectively. Find the
discharge required at the head of water course if the peak demand is 20% of the average requirement.
Solution:
Given: CCA = 2600 hectares.
Area under sugar cane = (20/100) * 2600 = 520 hectares. 2
The peak requirements may be taken to be equal to 20% to 25% higher than the average requirement.
Therefore the design discharge = 1.271 + [1.271*(20/100)]
= 1.52 cumecs. 3
UNIT 2
1. Write a note on sprinkler method of irrigation and condition favoring the adoption of this method.
Definition 2
Water is applied to the soil in the form of a spray through a network of pipes and pumps.
It can be used for all types of soils and for widely different topographies and slopes.
It fulfills the normal requirement of uniform distribution of water.
Types of sprinkler systems. 6
A sprinkler system can be classified under three heads, as :
1. Permanent system ;
2. Semi-permanent system and
3. Portable system
In permanent system, pipes are permanently buried in such a way that they do not interfere with the farming
operations.
In the semi permanent system, the main lines are buried in the ground, while the laterals are portable.
In the portable system, the mains as well as laterals are portable. These portable networks can be moved from
farm to farm.
In the sprinkler irrigation network, we have the mains and the sub-mains, through which water under
pressure is made to flow. Revolving sprinkler heads are then usually mounted on rising pipes attached to the
laterals. The water jet comes out through the revolving sprinkler heads, with, force. When sprinkler heads are
not provided, perforations are made in the pipes, and they are provided with nozzles, through which water jets
out and falls on the ground. Generally, such a perforated pipe system operates at low heads; whereas, the
revolving head sprinklers operate on high as well as low heads, depending upon the type of rotary head used.
CHECK FLOODING:
Figure 4
Explanation 6
Excessive long furrows may result in too much percolation near the upper end, and too little water near the
down-slope end. Deep furrows are widely used for row crops. Small shallow furrows called corrugations,
are particularly suitable for relatively irregular topography and close growing crops, such as meadows and
small grains.
Water may be diverted into the furrows by an opening in the bank of the supply ditch or preferably by using
rubber hose tubing, which can be primed by immersion in the ditch. The use of hose prevents the necessity of
breaking the ditch bank and provides a uniform flow into the furrow
Reduces pudding and crusting of the soil. Evaporation losses are also reduced.
Earlier cultivation is possible in heavy soil and may be adapted to use without erosion on a wide range of
natural slope by carrying furrows across a sloping field rather than the slope.
Labour requirements in land preparation and irrigation are very much reduced.
No wastage of land in field ditches.
UNIT III
Figure 4 marks
Raise its water level and divert the water in to the canal
Provided with crest shutters..
Stores water
The water supply for a short period.
Barrage or Regulator:
Raised to different level
Arrangement of adjustable gates
Divide Wall or Divide Groyne:
Long wall constructed at right angles to the weir or barrage
Stone masonry or cement concrete.
Still water pocket
Suspended silt can be settled down
Controls the eddy current.
Straight approach in front of the canal head.
Resists the overturning effect on the weir and barrage
Scouring Sluices or Under Sluices
Openings provided at the base
Adjustable Gates
Deposited silt is loosened with an agitator mounting on boat
Fish Ladder
Provided just by the side of the divide wall for the free movement of fishes.
The tendency of fish is to move from upstream to downstream.
Zig-zag manner -velocity of flow within the ladder does not exceed 3m/sec
3
b. Rockfill weir 3
Masonry breast wall-adjustable crust shutters
Upstream rock fill portion – boulders -1 in 4
The boulders are grouted with cement mortar
Downstream sloping apron consists of core walls
The intermediate spaces between the core walls are filled up with boulders maintaining a slope of 1 in 20
Figure 3
C. Concrete weir 3
Now-a-days, the weir is constructed with reinforced cement concrete.
The impervious floor and the weir are made monolithic.
The cut off walls are provided at the upstream and downstream end of the floor and the toe of the weir .
Sheet piles are provided below the cut-off walls.
The crest shutters are also provided which are dropped down during the flood
Figure 3
5
Shape of the lower nappe of the free falling waterjet from a sharp crested weir.
The shape of the lower nappe -the parabolic path
Shape of the letter S. –ogee spillway
Curved profile of the spill way - no gap between the water and the spill way surface and the discharge is
maximum.
The lower nappe does not follow the ogee profile and gets separated from the spill way surface. Thus a
negative pressure develops at the point of separation.
Due to the negative pressure, air bubbles are formed within the flowing water. These air bubbles are
responsible for the frictional force which causes much damage to spill way surface
Saddle Siphon Spill Way 6
Explanation (3x4=12)
1. Weight of the Dam
The weight of the dam -counters balances all the external forces acting on the darn.
Heavy materials of high specific gravity.
Specific weight of concrete and stone masonry should not be less than 2400 kg/m3 and 2300 kg/m3 respectively.
2. Water pressure
Major external force acting on a dam. When the upstream face of the dam is vertical, the water pressure acts
horizontally. The intensity of pressures varies triangular with a zero intensity at the water surface, to a value
WH at any depth H below water surface. When the upstream face is partly vertical and partly inclined, the
resultant water pressure can be resolved into component.(i) Horizontal component P
Horizontal force P= WH2 / 2, Where H = height of water (F.R.L.)
This force acts at a height H/3 from the base of the dam.
3. Uplift pressure:
The stored water - tendency to seep through the soil below the foundation. -exerts uplift pressure on the
base of the dam which depends on the head of water,
This uplift pressure reduces the self weight of the dam. If the depth of water on the upstream side be H and that
on the downstream side be H1, then the intensity of pressure on U/S base is WH and on the D/S, base is WH1.
4. Seismic Force:
The seismic zone - earthquake waves – account
The vertical and horizontal components of the earthquake waves are considered for the design of a dam -
recorded by seismic recorder.
The acceleration of earthquake waves consist of two components vertical acceleration and horizontal
acceleration
(a) Effect of vertical component: The vertical component may act upwards or downwards
Earthquake wave act upwards the foundation of the dam will be lifted up and thus the stress on the dam -the
dam may fail by crushing.
Act downwards the foundation of the dam has a tendency to move downwards and thus a gap may be formed -
dam to settle down and cracks may be formed within foundation or on the body of the dam. The vertical
acceleration exerts a downward force on the dam which is given by
W/g x fv
This force reduces the effective weight of the dam. So, the net effective weight of dam,
Wf = W-W/g fv
=W(1- Cv)
Cv is the coefficient of vertical acceleration. It varies from 0.1g to 0.3g.
Wf = Net effective weight of dam
(b) Effect of horizontal component :The horizontal component imparts following two forces:
(1)Hydrodynamic force: Due to horizontal acceleration (fh), the water pressure is increased momentarily. -
hydrodynamic pressure. The expression given by
(2) Inertia force: Due to the horizontal acceleration ‘ fh ‘an inertia force will be developed on the body of the
dam this force is given by,
Where, I = inertia force, W= total weight of dam, g= acceleration due to gravity, fh=horizontal acceleration, Ch=
a coefficient adopted for horizontal acceleration 0.1 g to 0.3 g.
5. Silt Pressure : The silt - deposited - exerts pressure on the dam.
(a) When the upstream face is completely vertical, the silt pressure is given by Rankine's formula
Where, Ws = submerged sp.wt of silt, h= depth of silt deposit, ϕ= angle of
internal friction.
6. Wave Pressure: When very high wind or tornado flows over the water surface of the reservoir, waves are
formed which exert pressure on the upper part of the dam. The magnitude of the wave depends on the velocity
of wind, depth of reservoir and the area of water surface. The wave pressure is calculated by Moliter’s formula
as follows
7. Ice Pressure: formation of ice is expected on the reservoir surface-exerts pressure on the dam at the point of
contact during the process of contraction and expansion with the change of temperature.
In India - ice pressure - 25,000 kg/m2
8. Wind Pressure: The top exposed portion- wind pressure at the rate of about 150 kg/m2
UNIT 4
Branch Canal:
Taken from either side of the main canal
The discharge varies from 5 to 10 cumec
Distributory Canal:
Taken from the branch canals
Discharge - varies from 0.25 to 3 cumec
Field Channels:
Taken from the outlets of the distributory.
Based on alignment 6
Depending upon the alignment, the canals are designated as (a) Ridge or watershed canal (b) Contour canal, (c)
Side slope canal.
Contour Canal:
Aligned approximately parallel to the contour lines is known as contour canal.
Irrigate the areas one side only- cross natural drainage - cross-drainage works are necessary.
3. Why are canal falls necessary? Describe with sketch briefly any three types of canal falls.
These hydraulic structures-negotiate the difference in bed slope and ground slope and 2
to bring down the canal bed line.
Rapid fall:
Stepped fall:
Glacis Fall
4. What are the types of cross drainage works? Describe them briefly with sketches.
When an irrigation canal crosses a natural drainage course (such as stream, river, etc.,) a
masonry work known as a cross drainage work is provided for the safe disposal of drainage water across the
canal.
At the crossing, it may be possible to have different site conditions.
The canal bed level may be higher than the bed level of drain.
The bed levels of canal and drainage may almost be same.
The canal bed level may be lower than the bed level of dam.
Types of crossings:
The crossing may necessitate,
To take the canal above the drain (aqueduct)
To siphon the drain below the canal (siphon aqueduct)
To take the canal below the drain (super passage)
To siphon the canal below the drain (siphon super passage)
To let the drain in to the canal on one side and take out from the other side of the canal (level crossing)
Aqueduct:
Canal is taken over the deck supported by piers.
Shape -rectangular trough - reinforced cement concrete.
An inspection road-the bed and banks - boulder pitching with cement grouting .
The piers may be of brick masonry, stone masonry or reinforced cement concrete.
The concrete foundation - the depth of foundation according to the availability of hard soil.
Fig. Aqueduct
Siphon Aqueduct:
The bed of the drainage is depressed below the bottom level of the canal trough by providing
sloping apron on both sides of the crossing.
The sloping apron - stone pitching or cement concrete.
This tunnel acts as a siphon.
Cut off walls - prevent scouring.
Boulder pitching should he provided on the upstream and downstream of the cut-off walls.
Superpassage
The bed level of drainage is above the fully supply level of the canal.
The drainage - rectangular or trapezoidal trough - on the deck supported by piers.
The trough - reinforced cement concrete.
The bed and banks of the canal -boulder pitching or lining with concrete slabs.
Level Crossing:
To regulate the flow of water through the drainage and the canal when they cross each other
approximately at the same bed level.
The level crossing consists of the following components
(1) Crest Wall:
Upstream side of the crossing point.
The top level of the crest wall is kept at the full supply level of the canal
(2)Drainage Regulator:
It is provided across the drainage just at the downstream side of the crossing point.
The regulator consists of adjustable shutters at different tiers
(3) Canal regulator: adjustable shutters at different tiers.
Inlet and outlet
An inlet is provided in the channel bank simply by open cut and the drainage water is allowed to join the
channel,
Downstream side of the channel - stream outlet is provided by open cut and the water from the irrigation
channel is allowed to flow through a leading channel towards the original course of the drainage.
At the points of inlet and outlet the bed and banks - stone pitching.
5. What are the components of river training work? Explain Marginal embankment in detail.
Components of river training work 4
Marginal embankment
Guide bank
Spur
Groynes
Bank protection
Figure 4
UNIT 5
1. Discuss the inadequacies of present – day canal irrigation management in India.(any 8x2=16)
Insufficient planning and preparation at the stage of execution of the project which results in longer
construction time and escalated project cost,
Involvement of more than one ministry/department and poor coordination among them,
Non-responsive, authoritarian, and poor administration resulting in increased malpractices,
Lack of interaction between engineering and agricultural experts,
Lag between creation of potential and its utilization,
Improper assessment of personnel, equipment, and other facilities for proper operation and maintenance of
reservoirs and canal systems resulting in erratic (unreliable and insufficient) supplies inequitable distribution of
available water,
Higher conveyance losses,
Absence of conjunctive use of ground water and surface water,
Insufficient drainage, excessive seepage, and waterlogging,
Poor on-farm management,
Absence of farmer’s participation in the management,
Lack of communication facilities in the command area,
Poor extension services – lack of pilot projects, demonstration farms, etc.,
Problems related to land settlement and rehabilitation of displaced persons, and
Recovery of the project cost.
2. Describe the common criteria for judging the performance of an irrigation system.
2
Measures are lining of canals and field channels, on-farm development, farmers organization, warabandi system
of water distribution, charging farmers volumetrically for water, and education farmers in water use
management.
Criteria of good irrigation system performance 8
Type of person Possible first criterion of good system performance
Landless Labourer Increased labour demand, days of working, and wages
Farmer Delivery to his or her farm of an adequate, convenient,
predictable, and timely water supply for preferred farming
practices
Irrigation engineer Efficient delivery of water from headworks to outlet
Agricultural Efficient delivery and field application of irrigation water from
engineer the outlet to the root zone of the crop
Agronomist Creation and maintenance of the optimum moisture regime and
plant growth and, in particular, maximizing production of that
part of the plant which is the harvestable product
General economist A high internal rate of return
Political economist Equitable distribution of benefits, especially to disadvantaged
groups
Sociologist Participation of irrigators in management
3. What are the methods adopted for improving canal irrigation management? Explain any four in detail.
Any 4x4=16
Irrigation management is an interdisciplinary system process with a built-in learning mechanism to improve
system performance by adjusting physical, technological, and institutional inputs to achieve the desired
levels of output.
Cropping Pattern
An optimum cropping pattern - systems analysis.
Local preferences and requirements of the area
Necessary inputs are made available,
The farmers will adopt the cropping pattern arrived at using systems analysis.
Conjunctive Use
Conjunctive use means that water lifted from below the ground is used in conjunction with canal waters.
It results in the coordinated, combined, and creative exploitation of ground water and surface water so as to
minimize the dislocation caused by nature’s inconsistent rainfall pattern
Channel Capacity
Decided on the concept of evapotranspiration rather than the ‘kor’ period.
Canal Lining
Lining of canals is a means to reduce the seepage losses from canals.
slope of a lined channel - reduced.
Regulators and escapes
Proper distribution
A suitable number of canal regulators and canal escapes must be provided
Canal escapes are needed for the safety as well as for regulating canal supplies in areas
Canal Outlets
Controlling the distribution of water
Link between the administration and the farmer.
Equitable distribution of water- a regulated outlet would be an ideal choice
Main System Management
Future allocation, scheduling, delivery of water on main systems down to and including outlets, and the disposal
of water in drains below chaks (i.e. The irrigated fields).
It includes planning, decision making, the operation of controls, and communications both upwards to
managers and downwards to groups of farmers so that equitable supplies can be ensured throughout the
command area.
Main system management (MSM) is capable of reducing gross inequities of water supply to tail-end farmers
and increasing the farm yield from the command area.
Night Irrigation
In most of the canal irrigation projects, the canal water continues to flow at nights as well and is either badly
used or wasted. Darkness, cold, fear, normal working hours and desire for sleep discourage the irrigation staff,
farmers, and labourers to work at night.
Measures to reduce night irrigation with water saving involve storage of water which can be achieved in
five different ways – in main reservoirs, in canals, in intermediate storage reservoirs, on-farm storage, and in
ground water storage. On the other hand, three obvious measures to reduce night irrigation without saving water
are:
Stopping river diversion flows,
Redistributing day water so that even tail-enders get adequate supplies,
Passing water to escapes and drains.
Water Delivery System
Water delivery systems can be of three types:
Demand – based,
Continuous, and
Rotational (also known as warabandi).
The warabandi system -system of equitable water distribution by turns according to a predetermined
schedule specifying the day, time, and duration of supply to each irrigator in proportion to land holdings in
outlet command
Irrigation Scheduling
The water is supplied to the plants when they need it and in quantities actually required by the plants.
Estimating the starting time, stopping time, and the quantity of water for different cycles of irrigation during the
crop period. Irrigation scheduling can be determined by using one of three approaches, viz.,
The soil-moisture depletion approach,
The climatological approach using evapotranspiration and effective rainfall data, and
The farmer’s existing schedule approach.
Irrigation Methods
. The drip irrigation method is highly efficient and better suited for fruit crops, vegetables, and cash crops like
sugarcane, cotton, groundnut, etc.
Sprinklers, drip irrigation - need to save water and extend irrigation facility to as large a cropped area as
possible for producing food for the growing population.
Use of Waste Water
Used water is suitably treated and used for irrigation. Such measures can provide additional irrigation potential
Conservation of Water on the Field.
The percolation losses can also be reduced by puddling the soil using improved puddlers and the saving of
water can be between 16 and 26 percent depending upon the type of soil and puddlers used.
Water logging
Water logging results in lowered yields, loss of lands for useful activities, and health hazards. To eliminate or
control water logging one or more of the following, remedial measures have usually been used:
Reducing inflow to the ground through lining of canals,
Removing ground water through pumping,
Removing surface and ground waters through drainage,
Educating farmers in water management, and
Conjunctive use.
Water logging can also be reduced by supplying less water during nights (, cutting off water supplies
during rains, rotating supplies in distributaries and minors instead of continuous supply, shortening irrigation
periods, and zoning for crop type.
Soil Reclamation
Magnitude, saline and alkaline soils - joint efforts of agricultural chemists, agronomists, agricultural experts,
and irrigation engineers. The role of an irrigation engineer is important in lowering the water table if it is high
and also providing irrigation water of good quality for leaching out the salts.
Water Charges and Pricing of the Agricultural Output
Water charges - on the basis of area served and the crop irrespective of the volume of water supplied. -
leads to inefficient use of water.
Managing internal distribution and collection of charges from its members, may possibly result in
efficiently use of water.
Farmer’s Participation
The participation of the farmer in all stages of the irrigation system would be very beneficial.
Phase 1 – Invitation
- Publicising the proposal, without restriction, as a promotional measure to gain popular support.
- Extending invitations for information meeting.
- Scheduling public hearing.
Phase 2 – Invitation
- Establishing formal organizations of farmers.
- Recognizing the roles of organization.
- Forming joint committees charged with proposing and reviewing.
- Conducting training courses.
Phase 3 – Invitation
- Assisting farmers to maintain their level of participation and increase its intensity.
- Relating their duties to improve their socio-economic status.
- Monitoring the performance of programmes to generate feedback into assistance and instruction.
5. Why should lining be provided in canals? What are the merits and demerits of canal lining?
The following are the main objects of canal lining: any 4x2=8
To Control Seepage
To seepage- the duty of canal water is much reduced - enhancement of storage capacity of a reservoir by
constructing high dam- expenditure of the project is increased
To Prevent Water-Logging
Areas may get converted into marshly lands.
Land alkaline - unsuitable for agriculture.
Breeding place of mosquitoes - many infectious diseases.
To Increase the Capacity of Canal
Silting and scouring is avoided.
Velocity and the discharge of the canal are more with minimum cross-sectional area.
To Increase the Command Area
losses - controlled - command area of the project may be enhanced.