Project Work Record

(Division : SAPULUH SUMBER ANUGRAH )


Project. Name : Faktory shoes Prepared Checked S-M'gr P-Director
Location : Temanggung Date : 29 Jan 2020
Site M'gr : Wahyu suryoadji Remaining Date :
Wahyu sa
Man Power (Workers) Staff Major Tools & Equipment
Classification Today Accu. Classi Today Accu. T & E - Name Today Accu.
Operator mesin 1 1 Bor Listrik 6 6
Operator w45 1 1 Wahyu ,s 1 1 Boor Charger 2 2
Electrik 1 1 Sopiudin 1 1 Safety body harnest 10 25
Erection 6 6 Helmet 17 25
Welder 2 2 Mesin Seaming 1 & 2 0 2
Picter 0 0 Seaming manual 1 & 2 2 5
Workers produksi 0 0 Genset 20kva 1 Pt Api
Workers fieber 4 4 Genset 50kva 1 Pt Ssa
Mesin las lakoni 2 2
Total 15 15 2 2
No. Item Volume Previous Today Accumulative Progress Remark
1 Pasang plat suport talang line B 612 Ea 612 ~ 612ea 100%
2 Pasang fieber talang line B 245,4m1 245,4 ~ 245,4m1 100%
3 Pasang fieber talang line C 245,4m1 40 ~ 40m1
4 Pasang fieber talang line A 245,4m1 245,4 ~ 245,4m1 100%
5 Produksi atap 28400m2 2,129,9m2 ~ 2,129,9m2
6 Pasang Plat support Gutter line C 503 ea 261 25 286ea 56%
7 Pasang Atap Production building 28,400m2 1,748 ~ 1,748 m2
8 Pasang plat support Gutter line A 488 ea 488 ~ 488ea 100%
9 Pasang Plat support Gutter Line E (Tb) 310 ea 25 15 40ea
10 Cat plat support gutter line A
11 Opening Corong ,pasang 6inc line A 31 ea 15 15ea

No. Works for Tomorrow Special Note / Proposal


1 Pasang Atap pb
2 Pengecatan supoort line C
3 Finishing join Gutter line A
4 Pasang plat support line C
5 Opening corong line donwspout line A

Over Time
Today's Weather ( Rain )
A.M
P.M 14:50 ~ 17,25