DAILY CONSTRUCTION LOG

PROJECT : 24 STOREY DORMITORY BUILDING WITH ROOF DECK DATE FEBRUARY 7, 2020
LOCATION : 1129 DOS CASTILLAS ST. SAMPALOC MANILA (FRIDAY)
OWNER : COMMUNITY SUITES REALTY DEVELOPMENT CORP. WEATHER CHART
CONTRACTOR : METRO STONERICH CORPORATION

LEGEND:
FAIR SHOWER
CLOUDY TYPHOON
RAINY UNWORKABLEGROUND

MANPOWER – STAFF & ADMIN


SCHEDULE ACTUAL
DESCRIPTION NO. OF HRS REMARKS
DAY SHIFT NIGHT SHIFT OT DAY SHIFT NIGHT SHIFT OT
OT
PROJECT MANAGER 1 0 0 1 0 0 0
OFFICE ENGINEER 1 0 0 1 0 0 0
HR/ADMIN OFFICER 1 0 0 1 0 0 0
SITE SUPERINTENDENT 1 0 0 0 0 0 0
QAQC 1 0 0 1 0 0 0
SITE ENGINEER 2 0 0 2 0 0 0
CAD OPERATOR 2 0 0 2 0 0 0
GEODETIC ENGINEER/SURVEYOR 2 0 0 1 0 0 0
ELECTRICAL ENGINEER 1 0 0 1 0 0 0
MECHANICAL ENGINEER 1 0 0 1 0 0 0
SENIOR MEPFS 1 0 0 0 0 0 0
SAFETY OFFICER 2 0 0 1 0 0 0
SECURITY GUARD 1 1 0 1 1 0 0
WAREHOUSEMAN 1 0 0 1 0 0 0
FOREMAN 1 0 0 1 0 0 0
CRANE OPERATOR 1 1 0 1 1 0 0
RIGGER 1 1 0 1 1 0 0
CARPENTER 5 0 0 2 0 0 0
WELDER 3 0 0 1 0 0 0
MASON 5 0 0 0 0 0 0
ELECTRICIAN 3 0 0 2 0 0 0
LABORER/HELPER 5 0 0 0 0 0 0
SURVEYOR AIDE 2 0 0 2 0 0 0
SAFETY CREW 3 0 0 2 0 0 0
SAFETY MARSHALL 1 0 0 0 0 0 0
TOTAL 46 3 0 25 3 0 0
MANPOWER – SUBCON
SCHEDULE ACTUAL
DESCRIPTION NO. OF HRS REMARKS
DAY SHIFT NIGHT SHIFT OT DAY SHIFT NIGHT SHIFT OT
OT
SITE ENGINEER/P.I.C. 2 0 0 2 0 0 0
SAFETY OFFICER 1 0 0 1 0 0 0
FOREMAN 5 0 0 3 0 0 0
STEELMAN 20 0 0 25 0 0 0
LEADMAN 4 0 0 0 0 0 0
CARPENTER 25 0 0 30 0 0 0
DAILY CONSTRUCTION LOG
STRIPPER 5 0 0 3 0 0 0
WELDER 10 0 0 3 0 0 0
MASON 5 0 0 2 0 0 0
LABORER 5 0 0 2 0 0 0
HAULERS 10 0 0 6 0 0 0
ELECTRICIAN 7 0 0 0 0 0 0
PLUMBER 7 0 0 4 0 0 0
TIME KEEPER 1 0 0 1 0 0 0
TOTAL 108 0 0 82 0 0 0
GRAND TOTAL 154 0 0 103 0 0 0
TOOLS/EQUIPMENT
SCHEDULE ACTUAL REMARKS
DESCRIPTION
DAY SHIFT NIGHT SHIFT OT DAY SHIFT NIGHT SHIFT OT
CHIPPING GUN 3 0 0 2 0 0
WELDING MACHINE 5 0 0 1 0 0
OXY ACETYLENE 2 0 2 1 0 0
AIR COMPRESSOR 1 1 1 0 0 0
JACKHAMMER 2 2 2 0 0 0
DEMOLITION HAMMER 1 0 0 0 0 0
SUBMERSSIBLE PUMP 4 0 0 1 0 0
VIBRATOR 1 1 0 0 1 0
TOTAL 20 4 3 6 1 0

ACTIVITIES
1. CURING AT 9TH FLOOR
2. LAY-OUT AT 10TH FLOOR LEVEL
3. INSTALLATION OF SCAFFOLDINGS & RUNNERS FOR 10TH FLOOR LEVEL
4. INSTALLATION OF TIES AND SPLICES FOR COLUMNS AND SHEARWALLS AT 9TH FLOOR – UP
5. CLEARING & HAULING AT SUBSTRUCTURE
6. CUTTING & DISMATLING OF WALER & STRUT
7. INSTALLATION OF REBAR FOR SUB STRUCTURE
PROBLEMS ENCOUNTERED
1. INSUFFICIENT SPACE FOR STORAGE PURPOSES
2. INSUFFICIENT MANPOWER
SIGNIFICANT EVENTS
1.
TOMORROW’S PLANNED ACTIVITIES
1. CURING AT 9TH FLOOR
2. INSTALLATION OF SCAFFOLDINGS & RUNNERS FOR 10TH FLOOR LEVEL
3. INSTALLATION OF REBAR (BEAMS) AT 10TH FLOOR
4. CLEARING & HAULING AT SUBSTRUCTURE
5. CUTTING & DISMATLING OF WALER & STRUT
VISITORS
1. _________________________________________________________________________________________________
REMARKS
1. 2,606 cu.m. OF CONCRETE POURED
2. 732,641.31 KGS OF REBAR DELIVERED ON SITE AS OF FEBRUARY 7, 2020

Prepared by: Noted by:

Engr. RICHARD G. ABUYAN Ar. GARRY LUCAS


QAQC Engineer – MSC Project Manager – RMCCMC

Verified Correct by:

Ar. ARMANDO DORIA


Project Manager – MSC