Professional Documents
Culture Documents
1 Application
This note explains the welding method (MMAW-Manual Metal Arc Welding) at site for repairing
a leak through the welded joint of power transformer tanks and fittings.
2.1 De-energize the transformer and check the earthing of tank is proper.
2.3 Create a vacuum above the oil level in tank to temporarily stop the leak.
This may be done by closing buchholz relay valve and draining sufficient oil from bottom filter
valve (1ZYN 200820-068) on pumping out to conservator to obtain necessary vacuum inside
the tank. Vacuuming is not essential if the leak is only a sweating one. Welding without oil can
be done if the tank wall thickness is more than 9 mm. In that case steps are to be taken to
repaint inside burnt paint and also to cover from inside to prevent welding sparks entering into
tank.
2.4 If oil level cannot be maintained above the welding point, keep a nitrogen blanket inside the tank
In that condition there is chance for burning of the inside painting.
2.5 Cleaning:
Remove the oil and paint from the surface to be welded. Prepare a suitable point on
transformer tank for clamping the earth lead of the arc welding set.
3 Leak Welding
Use type 308 stainless steel electrode for making repairs on non-magnetic steel (e.g.: High current
LV bushing mounting flange, turret). When DC current is used, straight polarity is preferred,with
the electrode negative.
3.3 Liquid interferes with the welding operation and the quality of the deposited metal. It should be
wiped off with a dry cloth. All welds should be deposited in this sequence to prevent any liquid
seepage interfering with the welding operation.
1 2
This welding sequence is recommended to prevent any liquid interfering with or contaminating the
weld.
2. Find the exact position of the leak by cleaning with wire brush and sandex
3. If the leak is around the flange (i.e. Mig welded areas), weld the leak with 3.15 mm electrode
(E-6012 orE-7018) with current setting 110-125 Amps.
4. If the leak is along the edges of the fin (i.e. TIG and Seam welded area ), use slightly reducing
oxy-acetylene welding flame under neutral flame to remove oil traces and to pre heat damaged
area. After 5 minutes carry out GTAW (Gas tungsten arc welding) with DC power source.
Set the current approx. 80/100 A and fuse the edges slowly. Check visually for total fusion.
5. Clean the repaired area and check with a suitable leak detector after filling with air or oil
5 Inspection of weld:
Clean the repaired area and check the weld with chalk powder if the transformer is filed with oil and
with soap water in case of nitrogen filling. Liquid dye penetration test may be done to ensure
soundness of welding.
6 Finishing
After checking for the leak, clean the area completely and apply touch up paint (Primer+ Finish
Paint)
Do not energize the transformer without oil circulation with vacuum chamber in the filter machine
(Min 48 hrs.) plus settling time (more than 3-8 days).