You are on page 1of 2

Project Scope Management - Answers

45. Answer: A.

Project Scope Statement

The project scope statement describes, in detail, the project’s deliverables and the work
required to create those deliverables. The project scope statement also provides a common
understanding of the project scope among all project stakeholders and describes the project’s
major objectives. It also enables the project team to perform more detailed planning, guides
the project team’s work during execution, and provides the baseline for evaluating whether
requests for changes or additional work are contained within or outside the project’s
boundaries.

46 . Answer: D.

Approved Change Requests

An approved change request impacting project scope is any modification to the agreed-upon
project scope baseline, as defined by the approved project scope statement, WBS, and WBS
dictionary.

47. Answer: D.

Requirement Management Plan

The Requirement Management Plan provides guidance on how project scope will be defined,
documented, verified, managed, and controlled by the project management team.

48 . Answer: D.

Change Control System

A project scope change control system, documented in the Requirement Management Plan,
defines the procedures by which the project scope and product scope can be changed. The
system includes the documentation, tracking systems, and approval levels necessary for
authorizing changes. The scope change control system is integrated with any overall project
management information system to control project scope...

49. Answer: D.

50. Answer: A.

Scope verification is the process of obtaining the stakeholders’ formal acceptance of the
completed project scope and associated deliverables. Verifying the project scope includes
reviewing deliverables to ensure that each is completed satisfactorily...

51. Answer: A.

Create WBS

The WBS is a deliverable-oriented hierarchical decomposition of the work to be executed by


the project team, to accomplish the project objectives and create the required deliverables...

Work Breakdown Structure


...The WBS should not be confused with other kinds of breakdown structures used to present
project information. Other structures used in some application areas or other Knowledge
Areas include:

• Organizational Breakdown Structure (OBS)...

• Bill of Materials (BOM)...

• Risk Breakdown Structure (RBS)...

• Resource Breakdown Structure (RBS)...

52. Answer: A.

Project constraints. Lists and describes the specific project constraints associated with the
project scope that limit the team’s options. For example, a predefined budget or any imposed
dates (schedule milestones) that are issued by the customer or performing organization are
included. When a project is performed under contract, contractual provisions will generally be
constraints. The constraints listed in the detailed project scope statement are typically more
numerous and more detailed than the constraints listed in the project charter.

53. Answer: B.

54. Answer: A.

Create WBS

The WBS is a deliverable-oriented hierarchical decomposition of the work to be executed by


the project team, to accomplish the project objectives and create the required deliverables.
The WBS organizes and defines the total scope of the project. The WBS subdivides the
project work into smaller, more manageable pieces of work, with each descending level of the
WBS representing an increasingly detailed definition of the project work. The planned work
contained within the lowest-level WBS components, which are called work packages, can be
scheduled, cost estimated, monitored, and controlled.

55. Answer: B.

Create WBS

The WBS is a deliverable-oriented hierarchical decomposition of the work to be executed by


the project team, to accomplish the project objectives and create the required deliverables.
The WBS organizes and defines the total scope of the project. The WBS subdivides the
project work into smaller, more manageable pieces of work, with each descending level of the
WBS representing an increasingly detailed definition of the project work. The planned work
contained within the lowest-level WBS components, which are called work packages, can be
scheduled, cost estimated, monitored, and controlled.

56. Answer: C.

You might also like