TECHNICAL NARRATIVE
Plant Site:MPPCL 2x315MW Thermal Power Plant Date : February 27, 2020
Location: Brgy. Bani Masinloc, Zambales Philippines EISSS-QT-0220-----
PR4165633
Project description: Ovation Control System Upgrade
1.0 Methodology
The ability to move DCS equipment safely from ground level to turbine house is necessary for many site
activities in MPPCL facilities. Heavy hoists, cranes and cage equipment will be used on materials that are
too bulky or heavy to be moved manually.
While hoisting and rigging plays an important role in transporting such heavy and delicate items, proper
rigging methods and correct choice of equipment can avert physical impairments, serious injuries, and
fatalities.
All EISSS site personnel and contractors have been instructed on the potential dangers of equipment
handling, and have received equipment handling training. Staff and contractors will not lift items of
equipment beyond their capabilities.
The following are the control measures to be followed during supervision on transporting of fragile
equipment to central control room:
Heavy or awkward items will be broken down into smaller units or dual lifted where this is not possible. It
is the responsibility of the site supervisor to identify and control potentially dangerous handling situations
as they occur on site on a day to day basis.
2.0 Project Schedule
Listed hereunder are project timeline of each activity for the lifting and hoisting services for unit DCS
upgrade.
Task Name Duration Day_1 Day_2 Day_3 Day_4 Day_5 Day_6 Day_7
Lifting & Hoisting Services for Unit DCS Upgrade 7 days
Mobilization - (Manpower, Eqpt & Materials) 1 day
Manpower Mobilization 1 day
Equipment Mobilization 1 day
Client Kick-off Meeting 1 day
Preparatory Works 2 days
Visual Inspection of Lifting & Hoisting Equipment 1 day
Tools & Equipment Load Capacity Checking 1 day
Plant Plot Plan Identification on Crane Location 1 day
Barricading and Signages 1 day
Lifting & Hoisting Works 4 days
Work Permits 4 days
Lifting of Crates and Assembly Boxes to Control Room 4 days
De-mobilization - (Manpower, Eqpt & Materials) 1 day
Manpower Mobilization 1 day
Equipment Mobilization 1 day
# Description Qty
1 Lifting Slings 1 lot
2 Lifting Lugs 1 lot
3 Shackles 1 lot
4 Cage Equipment 1 unit
5 Working Bench 2 pcs.
6 Working Table 1 unit
7 Pallet Jack 2 pcs.
8 Consummable Items 1 lot
Prepared by:
Noted by: Eugene Nagtalon /Mike Garcia
Arnel Moreno
Supervisor