You are on page 1of 4

Feature

Cover Story
Report

PEMS: The Low-Cost Alternative


To Emissions Monitoring
Real-world experience with
installing and using both PEMS
and CEMS at this methanol
manufacturing facility is shared.
The advantages of PEMS are many
Amer Khaqan FIGURE 1. This photo shows the methanol production facility of
Arrazi in Saudi Arabia
Saudi Methanol Co. (Arrazi)

R
egulatory authorities around the more than 99.99%. The site has six re- CEMS
world require continuous emis- formers, ten boilers, two incinerators A CEMS consists of specific hardware
sions monitoring of certain pol- and two pre-heaters. — installed on combustion equipment
lutants from large combustion The environmental performance at stacks and in the field — that collects
sources. There are two main technolo- Arrazi is regulated by the Royal Com- samples of exhaust gases and then
gies for monitoring these emissions mission for Jubail and Yanbu (RCJY) analyses them to report the “real”
on a continuous basis — the more and the Presidency for Meteorology emissions levels. A typical hardware-
traditional one relies on sampling & Environment (PME), which can based CEMS consists of the following
and analyzing exhaust gases from a be considered to be the equivalent to major parts: analyzer, sample han-
continuous emissions monitoring sys- the U.S.’s Environmental Protection dling system (which includes pumps,
tem (CEMS); and the newer one relies Agency (EPA). The Royal Commission chillers, heated sample line and so
on software that uses mathematical Environmental Regulations (RCER) on), flow-monitoring hardware in the
algorithms and equations to predict rely heavily on the EPA for guidelines. stack, analyzer house, air conditioner,
emissions levels from existing control- As per RCER, Arrazi is required to calibration gas cylinders and more. In
system data. This second system is continuously monitor nitrogen oxides addition to all of this, the CEMS also
called a predictive emissions monitor- (NOx) emissions from combustion contains a data acquisition system
ing system (PEMS). sources, namely reformers and boilers. (DAS), which stores the data gathered
In this article, practical experience The reason why NOx is monitored by the CEMS analyzer. A DAS is ba-
and installation details of both CEMS on a continuous basis is a huge topic sically a computer running software
and PEMS at the reformers and boil- in itself and beyond the scope of this that is specially designed for data ac-
ers of the Arrazi methanol manufac- article. Here it will just be mentioned quisition and reporting.
turing complex are presented. The that NOx can cause or contribute to
real-world experience gained in about serious environmental problems (such PEMS
two-and-a-half years of operation is as acid rain and smog), and regulatory PEMS consists of software in a
shared and can be used as a template authorities in almost all countries re- dedicated computer that collects
to implement PEMS at any site. quire around-the-clock monitoring of data from the plant’s existing con-
NOx from combustion sources. trol systems (for example a distrib-
THE MANUFACTURING SITE uted control system; DCS) and uses
The experiences described in this ar- CEMS VERSUS PEMS mathematical algorithms and equa-
ticle are those of the Arrazi Saudi As mentioned earlier, there are two tions to “predict” emissions levels.
Methanol Co., an affiliate of Sabic basic ways to continuously monitor The only piece of hardware that a
(www.sabic.com), and the world’s larg- emissions: a hardware-based con- PEMS requires is a dedicated com-
est methanol manufacturing complex, tinuous emissions monitoring system puter. Details of how PEMS works
located in Jubail, Saudi Arabia (Fig- (CEMS); and a software-based pre- can be found elsewhere, so here is
ure 1). Arrazi uses natural gas, both as dictive emissions monitoring system just a short summary: Simply put,
fuel and as a raw material to produce (PEMS). The EPA and the RCJY ap- PEMS is a computer model that is
grade AA methanol with a purity of prove both CEMS and PEMS. capable of predicting the outcome of
28 CHEMICAL ENGINEERING WWW.CHE.COM APRIL 2011
FIGURE 3. One of the requirements of
the PEMS was that it needed to be com-
patible with the DCS or PLC used for
plant control and operation

Gaining acceptance. The chemi-


cal process industries (CPI) are typi-
cally cautious in embracing new tech-
FIGURE 2. PEMS was implemented on the boiler stacks at Arrazi, three of which are
shown here nologies that have not been tried and
tested for a long time — our site was
a “known” process (in other words if vice factor above 80% was a continu- no exception in this regard. We ran
the input of a dynamic and live pro- ous struggle. (The regulations require into some resistance at our plant
cess is known). By using a sophisti- an uptime of more than 95%.) With a about whether or not PEMS would
cated computer model, the dynamic dedicated, CEMS-analyzer-mainte- work. Even after a couple of detailed
and live output can be predicted nance crew, the service factor could presentations about PEMS, the skep-
fairly accurately. For emissions mon- have been improved further. This re- ticism didn’t die completely. We knew
itoring, this “known” process is com- flects the simple logical conclusion that the technology had to be proven,
bustion. (For more on PEMS, see The that the more parts a system has, the just like in the old proverb “the proof
Maturation of a Technology: Predic- more often it is prone to fail. of the pudding lies in eating”.
tive Emissions Monitoring, Chem. Furthermore, the running cost of The senior management of our com-
Eng., July 2006, pp. 50–55.) extractive CEMS was high due to pany was convinced about the poten-
maintenance, manpower and energy tial of PEMS and directed us to proceed
CEMS EXPERIENCE requirements. Based on this experi- with its installation at our site, hence
In 2006, to meet the Royal Commis- ence, we knew that the total cost of op- we started the work on this project.
sion Environmental Regulations for erating the CEMS would grow higher We came across many vendors who
continuous emissions monitoring, we as the number of CEMS installations could provide PEMS, and we wanted
installed traditional, extractive-type at the site increased. to be careful to choose the right ven-
CEMS analyzers for NOx and CO on All of this inspired us to search for dor, since this was a new technology
three of our reformers and one incin- a more economical alternative for the for us and the Gulf Cooperation Coun-
erator. This was Phase-1 of a CEMS CEMS. The answer to this quest came cil (GCC) region as a whole.
installation at our site. from EPA regulations, which discussed Vendor selection criteria. The
The hardware-based CEMS was sup- an alternative method to the CEMS. toughest part was to identify the
plied by a well-known German vendor, That alternative was the PEMS. vendor who was right for us. We thor-
and was commissioned in 2007. Our oughly researched various existing
experience with the CEMS installa- PEMS EXPERIENCE PEMS installations worldwide, pin-
tion and subsequent usage brought its The technology of PEMS has been pointed the weaknesses that other
strengths and weaknesses to light. around in one or other form since the PEMS had and then developed strict
The biggest strength of the CEMS 1980s. The first commercial installa- criteria for vendor selection. Accord-
was its ability to report “actual” tion was done in 1992 and was subse- ing to our guidelines, the PEMS to
analyses, regardless of any upstream quently approved by the EPA in the be selected needed to have the fol-
process changes (namely feed compo- same year. Since then, hundreds of lowing characteristics:
sition). If the analyzer was calibrated PEMS have been installed around the • Installations in the U.S. that must
properly, those analytical results world, and this technology has seen be certified by the EPA
were guaranteed to be accurate to continuous growth and acceptance. • At least five of the installations must
within ±2.5%. each be certified as per 40CFR60
The biggest weakness of the hard- Installation and 40CFR75
ware-based CEMS turned out to be As our site approached the second • There should be no recurring li-
its low service factor and an average phase of continuous-emissions-moni- cense fees for the PEMS and DAS
downtime of more than 40% during toring installations, our research led software; and all licenses should be
the initial months. The service factor us to decide to install a PEMS instead perpetual in nature
improved over the next two years, but of a hardware-based CEMS on our • The PEMS model should be open
keeping the average cumulative ser- seven boilers (Figure 2). and fully configurable by the end
CHEMICAL ENGINEERING WWW.CHE.COM APRIL 2011 29
Cover Story

user with no support required from FIGURE 4. An onsite


the original vendor later on PEMS inspection and rel-
ative accuracy test audit
• The PEMS model must not use any (RATA) were conducted
humidity sensors (these sensors are by regulatory agencies
prone to drift and require frequent
calibration)
• The PEMS must be able to perform
accurately with a minimal amount
of stack-testing data
The reason for developing these
stringent guidelines was that we
didn’t want to be stuck with a PEMS
that was vendor specific or propri-
etary, and we wanted a system that
was very reliable and robust with no
hidden costs. The above criteria en-
sured that we chose the best possible
product. As a result of using these
guidelines, we chose a statistical
hybrid PEMS model provided by an
American vendor.
The regulatory criteria of the EPA
require an accuracy of 10%, whereas
our chosen vendor promised an ac-
curacy of 5–6%. After commissioning,
our PEMS was giving accuracy in the
range of 4–6%.

Implementation
For the PEMS to be successfully in- FIGURE 5. This typical DAS reporting screen shows the status of all input param-
eters for one of the seven boilers. The green boxes at the bottom of the screen show
stalled at the Arrazi site, the following that six of the seven boilers are running and one is shut down
were the mandatory pre-requisites:
• Compatibility with the plant’s and the OPC server • Almost all CEMS installations are
DCS or programmable logic con- 5. Developing the PEMS model and hazardous locations requiring clas-
trol (PLC) selecting the input parameters for sified explosion-proof equipment
• The initiation of an analyzer main- the PEMS model (for example Class-1, Div-2) which
tenance program (if one did not al- 6. Stacks testing to fine-tune the PEMS increases the cost of the CEMS tre-
ready exist) at the site model. (We used a Horiba PG-250 mendously. By choosing a PEMS we
• High speed (preferably > 500 kbps) for our stacks testing with a stand- avoided the use of any field-mounted
internet access to the PEMS server by analyzer available all the time) hardware and saved a lot
for remote support from the vendor 7. Pre-RATA (relative accuracy test • Operational cost savings of approxi-
• Availability of remote connection audit) to verify the predictions of mately 90%
(such as a virtual private network; the PEMS model • The air conditioning, heated sample
VPN) to the PEMS server 8. RATA verification by a regulatory line, analyzers, sample conditioning
The project execution involved the fol- agency (Figure 4) system and so on used in a CEMS
lowing main steps: 9. Report generation by the DAS (Fig- are all energy intensive and in-
1. Formation of a project team that in- ures 5 and 6) crease operational costs. A PEMS
cluded an environmental engineer, The PEMS has been successfully op- uses only a computer for running,
DCS control engineer, IT engineer, erational at our site for about two- hence huge savings were also real-
PEMS vendor specialist and DCS and-a-half years. It was certified and ized in this area
vendor specialist approved by the Royal Commission for • Maintenance cost savings were ap-
2. Site survey by vendor to establish Jubail and Yanbu. proximately 90%
site-specific data • With a complete absence of the hard-
3. Installation of the PEMS server and Benefits ware required for CEMS, there was
connection to the open-connectivity Once the project was completed and no maintenance to be carried out for
(OPC) server. The DCS vendor sup- running for over a year, we realized PEMS. Again it turned out to be an
ported this connection the following main benefits by using a area of immense savings
4. Ensuring trouble free and reliable PEMS instead of a CEMS: • Manpower cost savings of approxi-
communication between the PEMS • Capital savings of more than 50% mately 90%
30 CHEMICAL ENGINEERING WWW.CHE.COM APRIL 2011
FREQUENTLY ASKED QUESTIONS ABOUT PEMS
During the implementation of the project and even now, the Ar- racy improves with time as more and more operating data are fed
razi team has received many inquiries about its PEMS installation. into the PEMS model, increasing accuracy to 2–3%.
Some of the most commonly asked questions are shared here:
Q: What are the limitations of a PEMS?
Q: Does the U.S. EPA approve PEMS? A: PEMS can only predict what it has been “trained” to do. It
A: Yes, PEMS is approved by the U.S. EPA. can’t work outside of its “training” envelope. In other words, it can’t
accurately predict if you are operating outside of the operating
Q: Can PEMS be used for every combustion application? parameters that were initially fed into the model.
A: No, there will always be sources that can only have an ex-
tractive CEMS, such as incinerators burning hazardous waste of Q: If PEMS is such a good technology, why isn’t every site in the
hugely varying composition. world replacing their CEMS with it?
A: CEMS has been around for over 30 years and so is well known.
Q: What is the accuracy of a PEMS? PEMS is a “relatively” new technology and is catching up fast. We
A: Well-designed PEMS are accurate to within 5–6%. Their accu- expect to see it more once awareness about it increases.

we have put procedural and software


controls in place to ensure that when-
ever the OPC software is updated and
the OPC server rebooted, the correct
settings of the OPC server should be
insured by IT to avoid the communica-
tions failure and subsequent data loss.
What we would have done differ-
ently. If given a chance to redo the
whole project again, we would prob-
ably change only one thing: the DAS.
The existing DAS we are using is not
based on MS Windows. Almost all con-
temporary software packages are now
Windows-based and hence offer many
of the features and functionality that
we take for granted. We had to work
with our DAS supplier to have some
functions specially provided for us,
and this would have been easier to tai-
lor with Windows-based software.

FUTURE OF PEMS
FIGURE 6. The summary status of all crucial boiler parameters can be displayed on
one page Our confidence in PEMS has found
firm footing after almost two-and-a-
• The hardware of a CEMS requires addressed (remote VPN connection half years of trouble-free operation. In
dedicated manpower and analyzer problem and configuration error), the contrast, the CEMS has been pretty
technicians. A PEMS requires no problem never recurred. After the demanding in terms of maintenance.
such dedicated support project execution was completed and We are already reviewing the propos-
• Uptime of more than 98% handed over to us, we never experi- als to replace the existing CEMS with
• With no pumps, heated lines, air enced this problem, and the PEMS a PEMS. ■
conditioners, sample conditioning ran without a glitch thereafter. Edited by Dorothy Lozowski
system or analyzers, the PEMS had Problem 2: There was communica-
almost nothing that could go wrong tion failure between the PEMS server Author
• Short project time. The whole PEMS and the DCS/OPC server. Infrequently Amer Khaqan is the senior
safety, health and environ-
project was completed in less than 6 (approximately every two to three ment (SHE) engineer at Ar-
months as opposed to over a year for months), whenever our IT personnel razi, Saudi Methanol Co. (P.O.
Box 10065, Jubail-31961,
the CEMS uploaded any major updates to the Saudi Arabia; Phone: +966
OPC server (which required a reboot 3 345 5688; Fax: +966 3 358
2600; Email: akhaqan@
Problems of the OPC server), the communica- arrazi.sabic.com), where he
During our almost two-and-a-half tion between the PEMS server and has worked for the last ten of
his 16 years of experience. He
years of operation, we faced only the the OPC server failed. As a result, is a chemical engineer with
specialization in petroleum and gas from Punjab
following two problems: the PEMS server stopped reporting University, Lahore, Pakistan. Among his other
Problem 1: The PEMS server locked- the emissions. This problem, though duties related to SHE, Khaqan is the certified
lead auditor for ISO 14001 and OHSAS 18001.
up (hanging), requiring a reboot. This not caused by the failure of the PEMS His work involves managing the IMS (Inte-
happened a few times during the server itself, still caused a loss of data- grated Management System) of the site which is
compliant to ISO 9001, ISO 14001 and OHSAS
project implementation and commis- gathering capability until the OPC 18001. He has written several articles on the en-
sioning phase. Once the cause was settings could be fixed. To address this, vironment, energy and other topics.
CHEMICAL ENGINEERING WWW.CHE.COM APRIL 2011 31

You might also like