Professional Documents
Culture Documents
Cover Story
Report
R
egulatory authorities around the more than 99.99%. The site has six re- CEMS
world require continuous emis- formers, ten boilers, two incinerators A CEMS consists of specific hardware
sions monitoring of certain pol- and two pre-heaters. — installed on combustion equipment
lutants from large combustion The environmental performance at stacks and in the field — that collects
sources. There are two main technolo- Arrazi is regulated by the Royal Com- samples of exhaust gases and then
gies for monitoring these emissions mission for Jubail and Yanbu (RCJY) analyses them to report the “real”
on a continuous basis — the more and the Presidency for Meteorology emissions levels. A typical hardware-
traditional one relies on sampling & Environment (PME), which can based CEMS consists of the following
and analyzing exhaust gases from a be considered to be the equivalent to major parts: analyzer, sample han-
continuous emissions monitoring sys- the U.S.’s Environmental Protection dling system (which includes pumps,
tem (CEMS); and the newer one relies Agency (EPA). The Royal Commission chillers, heated sample line and so
on software that uses mathematical Environmental Regulations (RCER) on), flow-monitoring hardware in the
algorithms and equations to predict rely heavily on the EPA for guidelines. stack, analyzer house, air conditioner,
emissions levels from existing control- As per RCER, Arrazi is required to calibration gas cylinders and more. In
system data. This second system is continuously monitor nitrogen oxides addition to all of this, the CEMS also
called a predictive emissions monitor- (NOx) emissions from combustion contains a data acquisition system
ing system (PEMS). sources, namely reformers and boilers. (DAS), which stores the data gathered
In this article, practical experience The reason why NOx is monitored by the CEMS analyzer. A DAS is ba-
and installation details of both CEMS on a continuous basis is a huge topic sically a computer running software
and PEMS at the reformers and boil- in itself and beyond the scope of this that is specially designed for data ac-
ers of the Arrazi methanol manufac- article. Here it will just be mentioned quisition and reporting.
turing complex are presented. The that NOx can cause or contribute to
real-world experience gained in about serious environmental problems (such PEMS
two-and-a-half years of operation is as acid rain and smog), and regulatory PEMS consists of software in a
shared and can be used as a template authorities in almost all countries re- dedicated computer that collects
to implement PEMS at any site. quire around-the-clock monitoring of data from the plant’s existing con-
NOx from combustion sources. trol systems (for example a distrib-
THE MANUFACTURING SITE uted control system; DCS) and uses
The experiences described in this ar- CEMS VERSUS PEMS mathematical algorithms and equa-
ticle are those of the Arrazi Saudi As mentioned earlier, there are two tions to “predict” emissions levels.
Methanol Co., an affiliate of Sabic basic ways to continuously monitor The only piece of hardware that a
(www.sabic.com), and the world’s larg- emissions: a hardware-based con- PEMS requires is a dedicated com-
est methanol manufacturing complex, tinuous emissions monitoring system puter. Details of how PEMS works
located in Jubail, Saudi Arabia (Fig- (CEMS); and a software-based pre- can be found elsewhere, so here is
ure 1). Arrazi uses natural gas, both as dictive emissions monitoring system just a short summary: Simply put,
fuel and as a raw material to produce (PEMS). The EPA and the RCJY ap- PEMS is a computer model that is
grade AA methanol with a purity of prove both CEMS and PEMS. capable of predicting the outcome of
28 CHEMICAL ENGINEERING WWW.CHE.COM APRIL 2011
FIGURE 3. One of the requirements of
the PEMS was that it needed to be com-
patible with the DCS or PLC used for
plant control and operation
Implementation
For the PEMS to be successfully in- FIGURE 5. This typical DAS reporting screen shows the status of all input param-
eters for one of the seven boilers. The green boxes at the bottom of the screen show
stalled at the Arrazi site, the following that six of the seven boilers are running and one is shut down
were the mandatory pre-requisites:
• Compatibility with the plant’s and the OPC server • Almost all CEMS installations are
DCS or programmable logic con- 5. Developing the PEMS model and hazardous locations requiring clas-
trol (PLC) selecting the input parameters for sified explosion-proof equipment
• The initiation of an analyzer main- the PEMS model (for example Class-1, Div-2) which
tenance program (if one did not al- 6. Stacks testing to fine-tune the PEMS increases the cost of the CEMS tre-
ready exist) at the site model. (We used a Horiba PG-250 mendously. By choosing a PEMS we
• High speed (preferably > 500 kbps) for our stacks testing with a stand- avoided the use of any field-mounted
internet access to the PEMS server by analyzer available all the time) hardware and saved a lot
for remote support from the vendor 7. Pre-RATA (relative accuracy test • Operational cost savings of approxi-
• Availability of remote connection audit) to verify the predictions of mately 90%
(such as a virtual private network; the PEMS model • The air conditioning, heated sample
VPN) to the PEMS server 8. RATA verification by a regulatory line, analyzers, sample conditioning
The project execution involved the fol- agency (Figure 4) system and so on used in a CEMS
lowing main steps: 9. Report generation by the DAS (Fig- are all energy intensive and in-
1. Formation of a project team that in- ures 5 and 6) crease operational costs. A PEMS
cluded an environmental engineer, The PEMS has been successfully op- uses only a computer for running,
DCS control engineer, IT engineer, erational at our site for about two- hence huge savings were also real-
PEMS vendor specialist and DCS and-a-half years. It was certified and ized in this area
vendor specialist approved by the Royal Commission for • Maintenance cost savings were ap-
2. Site survey by vendor to establish Jubail and Yanbu. proximately 90%
site-specific data • With a complete absence of the hard-
3. Installation of the PEMS server and Benefits ware required for CEMS, there was
connection to the open-connectivity Once the project was completed and no maintenance to be carried out for
(OPC) server. The DCS vendor sup- running for over a year, we realized PEMS. Again it turned out to be an
ported this connection the following main benefits by using a area of immense savings
4. Ensuring trouble free and reliable PEMS instead of a CEMS: • Manpower cost savings of approxi-
communication between the PEMS • Capital savings of more than 50% mately 90%
30 CHEMICAL ENGINEERING WWW.CHE.COM APRIL 2011
FREQUENTLY ASKED QUESTIONS ABOUT PEMS
During the implementation of the project and even now, the Ar- racy improves with time as more and more operating data are fed
razi team has received many inquiries about its PEMS installation. into the PEMS model, increasing accuracy to 2–3%.
Some of the most commonly asked questions are shared here:
Q: What are the limitations of a PEMS?
Q: Does the U.S. EPA approve PEMS? A: PEMS can only predict what it has been “trained” to do. It
A: Yes, PEMS is approved by the U.S. EPA. can’t work outside of its “training” envelope. In other words, it can’t
accurately predict if you are operating outside of the operating
Q: Can PEMS be used for every combustion application? parameters that were initially fed into the model.
A: No, there will always be sources that can only have an ex-
tractive CEMS, such as incinerators burning hazardous waste of Q: If PEMS is such a good technology, why isn’t every site in the
hugely varying composition. world replacing their CEMS with it?
A: CEMS has been around for over 30 years and so is well known.
Q: What is the accuracy of a PEMS? PEMS is a “relatively” new technology and is catching up fast. We
A: Well-designed PEMS are accurate to within 5–6%. Their accu- expect to see it more once awareness about it increases.
FUTURE OF PEMS
FIGURE 6. The summary status of all crucial boiler parameters can be displayed on
one page Our confidence in PEMS has found
firm footing after almost two-and-a-
• The hardware of a CEMS requires addressed (remote VPN connection half years of trouble-free operation. In
dedicated manpower and analyzer problem and configuration error), the contrast, the CEMS has been pretty
technicians. A PEMS requires no problem never recurred. After the demanding in terms of maintenance.
such dedicated support project execution was completed and We are already reviewing the propos-
• Uptime of more than 98% handed over to us, we never experi- als to replace the existing CEMS with
• With no pumps, heated lines, air enced this problem, and the PEMS a PEMS. ■
conditioners, sample conditioning ran without a glitch thereafter. Edited by Dorothy Lozowski
system or analyzers, the PEMS had Problem 2: There was communica-
almost nothing that could go wrong tion failure between the PEMS server Author
• Short project time. The whole PEMS and the DCS/OPC server. Infrequently Amer Khaqan is the senior
safety, health and environ-
project was completed in less than 6 (approximately every two to three ment (SHE) engineer at Ar-
months as opposed to over a year for months), whenever our IT personnel razi, Saudi Methanol Co. (P.O.
Box 10065, Jubail-31961,
the CEMS uploaded any major updates to the Saudi Arabia; Phone: +966
OPC server (which required a reboot 3 345 5688; Fax: +966 3 358
2600; Email: akhaqan@
Problems of the OPC server), the communica- arrazi.sabic.com), where he
During our almost two-and-a-half tion between the PEMS server and has worked for the last ten of
his 16 years of experience. He
years of operation, we faced only the the OPC server failed. As a result, is a chemical engineer with
specialization in petroleum and gas from Punjab
following two problems: the PEMS server stopped reporting University, Lahore, Pakistan. Among his other
Problem 1: The PEMS server locked- the emissions. This problem, though duties related to SHE, Khaqan is the certified
lead auditor for ISO 14001 and OHSAS 18001.
up (hanging), requiring a reboot. This not caused by the failure of the PEMS His work involves managing the IMS (Inte-
happened a few times during the server itself, still caused a loss of data- grated Management System) of the site which is
compliant to ISO 9001, ISO 14001 and OHSAS
project implementation and commis- gathering capability until the OPC 18001. He has written several articles on the en-
sioning phase. Once the cause was settings could be fixed. To address this, vironment, energy and other topics.
CHEMICAL ENGINEERING WWW.CHE.COM APRIL 2011 31