ANG-RGN-OSS-QMS-PRO-0042 Rev A1 Risk Subsea Ops Management and Reporting Procedure PDF
ANG-RGN-OSS-QMS-PRO-0042 Rev A1 Risk Subsea Ops Management and Reporting Procedure PDF
Abstract:
tony.hunt@uk. Digitally
Issuing Authority Approved by: signed by
tony.hunt@uk.bp.com
bp.com
DN: cn=tony.hunt@uk.bp.com
Date: 2012.11.09 16:14:35 +01'00'
Tony Hunt- Subsea Operations Manager
Document Location:
Last update/Timecheck
Applicable OMS
OMS SPA: S&OR Region Risk Director
Links/Essentials/SPA:
Revision Control
Revision Description Date Prepared Reviewed Approved
A1 Approved for Use 11/10/12 MC TH TH
CONTENTS
1 PURPOSE ....................................................................................................................... 4
2 SCOPE ............................................................................................................................ 4
3 ABBREVIATIONS........................................................................................................... 4
3.1 Abbreviations............................................................................................... 4
4 PROCEDURE .................................................................................................................. 4
4.1 Introduction ................................................................................................. 4
4.2 Subsea Operations’ Risk Identification team/personnel .............................. 5
4.3 Recording Subsea Operations’ Risks........................................................... 5
4.4 Subsea Operations Risk Grouping ............................................................... 7
4.5 Subsea Operations’ Risk Extraction and Escalation..................................... 8
4.6 Reporting. .................................................................................................... 8
APPENDIX 1. Subsea Operations Risk Reporting Template ............................................. 9
APPENDIX 2. Subsea Operations Risk Matrix Tool ......................................................... 10
1 PURPOSE
The purpose of this document is to identify the process that Subsea Operations utilise to
manage and report risk. This procedure solely covers Subsea Operations’ method of
reviewing and reporting risk. All Risk Assessment, Prioritisation and Management activity
will be carried out in accordance with the S&OR regional document; Assessment,
Prioritisation and Management of Risk Procedure (ANG-RGN-SOR-PRO-0002).
2 SCOPE
This procedure shall be read, used and complied with by all BP employees and contractors
with roles and responsibilities for the assessment and prioritisation of risks within the BP
Angola Region, Subsea Operations function
3 ABBREVIATIONS
3.1 Abbreviations
4 PROCEDURE
4.1 Introduction
The Angola Region Operations Function, of which Subsea Operations is a sub-function, use
RAT as the tool for managing risks. It is expected that Operations, e.g. AOM, and the VP
Operations review RAT on the frequency set in the Angola Region Assessment,
Prioritisation and Management of Risk Procedure (ANG-RGN-SOR-PRO-0002) to
understand all the risks they are managing.
Subsea Operations shall use the following risk registers to manage their risks:
1. Microsoft XL Risk Register held on Angola One as a data recording and reviewing
tool used to record and review risks only.
2. The Risk Register within RAT as the required system for the record, report and
manage risk.
3. Production Division Risk Register within RAT as the required risk register to report
risks outside of the subsea function. (Grouped Risks are held and reported on this
register)
Subsea Subsea
Team risk operations risk operations
registers in register in RAT grouped risks
Angola One All risks Risks for within Region risk
(excel) migrated - edited by reporting register in RAT
Subsea Risk migrated
- edited by Champion only to Extracted risks-
subsea team capture all escalation made
changes made to by Subsea Risk
the excel register
Subsea shall ensure that certain risks (criteria below) are escalated up to the Production
Division risk register in RAT for inclusion in risk conversations at a facility or function level.
Risks not escalated would be considered not reported by the subsea function.
Teams shall be supported in the development of their risks by the Subsea Operations Risk
Champion, where necessary.
Risks can be identified either at formal risk workshops, via the TQ process, informally at
team meetings or by an individual. It is everyone’s responsibility to identify and highlight
risks.
Typical sources of risks may come from:
-project handover (outstanding design, commissioning, handover risks)
-project risk studies (MAR, HAZOPs, FMECAs)
-emerging risks (typically resulting from feedback from the integrity management process in
place)
These macros prevent errors or changes being made without the knowledge of the Risk
Champion.
The Subsea Operations XL Risk Register ultimately is used as a “data recording and
reviewing” tool only and the amended data on that register is then loaded into the Risk
Assurance Tool (RAT).
RAT is the required system for the recording, reporting and managing risk. Subsea
Operations utilise RAT for Managing and Reporting Risk and also to allow us to interface
with the regional registers and S&OR.
RAT operation is currently restricted to trained users. S&OR are currently drafting the RAT
user procedure. Any questions regarding the operation of RAT can be passed to the
Operations Subsea Risk Champion. The Operations Subsea Tier 4 full risk register is held
on the Risk Assurance Tool (RAT) is located:
http://projects.bpweb.bp.com/bprat/risk_register.asp?id=382
Note:
Approval and authority is required to view, add or edit risks within RAT. For approval
contact the Operation Subsea Risk Champion or the S&OR Region Risk Director.
These individual risks will either be new risks events which have been identified (ie do not fit
within the grouped risk events identified in the list above) or specific components of the
grouped risk events (ie a specific cause which has been identified, or a significant weak
barrier) which ais deemed to require specific attention, or due to severity or likelihood levels,
to be monitored, managed and reported to Regional level, even though it is are part of a
grouped risk.
Both these types of new risks should be reported immediately using the emerging risk
process (detailed in the Region Procedure ANG-RGN-SOR-PRO-0002).
This extraction and escalation will result in the individual risk being reported along side the
grouped risks within the Region Production Division Risk register (normally used for subsea
grouped risks.)
4.6 Reporting.
The risk champion, or delegated personnel, will be responsible for ensuring that risk is
reported on a monthly basis to the Subsea Operations Manger using the risk register
reporting template. Appendix 1.
The Subsea Operations manager can also request risk updates, full register on individual, as
required. These requests will also be submitted via the risk register reporting template.
Appendix 1.