PDUGMC Rajkot site Work Status as on 30.04.

2019
Ground Second Fourth
Civil Works - Internal Works floor First Floor Floor Third Floor Floor Fifth Floor
Brick Work 100 100 100 100 100 100
Plastering 100 100 100 100 100 100
False Ceiling 100 100 100 100 100 100
Painting 100 100 100 100 100 100
Plumbing works 100 100 100 100 100 100
Plumbing and Sanitary Fixtures fixing 100 100 100 100 100 100
Tiling works (Floor & Dado) 100 100 100 100 100 100
Aluminium Joineries work 100 100 100 100 100 100
Steel Joineries Work 100 100 100 100 100 100
Wooden Joineries Works 100 100 100 100 100 100
Civil Worls - External Works
Plastering works 100
Painting works 100
Plumbing works 100
Structural glazing works 100
Water Proofing works 100

Electrical - Internal Works


Electrical Conduit 100 100 100 100 100 100
Electrical Wiring 100 100 100 100 100 100
DB Fixing 100 100 100 100 100 100
MCB fixing and DB connections 100 100 100 100 100 100
Light Fittings- All 100 100 100 100 100 100
LV Fittings-FAS,Detectors,CCTV 100 100 95 100 100 95
Switch and Sockets Fixing
Rising Main fixing 100 100 100 100 100 100
Cable tray fixing 100 100 100 100 100 100

Electrical - External Works


LT cable laying 100 100 100 100 100 100
HT cable laying 100 N.A N.A N.A N.A N.A
SITC of LT Panels 100 100 100 100 100 100
SITC of HT Panel 100 N.A N.A N.A N.A N.A
SITC of Tranformer 95 N.A N.A N.A N.A N.A
SITC of DG Set 100
SITC of UPS 100
SITC of Solar Panel N.A N.A N.A N.A N.A N.A
External Lighting works along with Earthing Works 95

HVAC Works
SITC of Plant room equipment (Chillers, pumps, Hot
water generators etc)
SITC of AHU, Indoor units (Ductable, cassette), FCU 100 100 100 100 100 100
SITC of Ventilation fans
SITC of Ducting 100 100 99 100 100 100
SITC of Grills, Diffusers, Louvers, dampers etc 100 100 100 100 100 100
SITC of Chilled water, Condenser water piping,
insulation 100 100 100 100 100 100
SITC of HVAC panel, starter panel etc

Fire Fighting works


SITC of piping network (Riser, Floor network, branches) 100 100 100 100 100 100
SITC of Fire fighting plant room equipment (pumps,
pressure vessel, diesel tank etc) 100 N.A N.A N.A N.A N.A
PDUGMC Rajkot site Work Status as on 30.04.2019
Ground Second Fourth
Civil Works - Internal Works floor First Floor Floor Third Floor Floor Fifth Floor
Brick Work 100 100 100 100 100 100
SITC of Sprinkler system (Sprinklers, Flexible extension,
Zonal control valves, installation control valves) 100 100 100 100 100 100
SITC of FHC equipment 100 100 100 100 100 100
SITC of internal/external hydrants 100 100 100 100 100 100
SITC of Signages 100 100 100 100 100 100
SITC of fire extinguishers 100 100 100 100 100 100

MOT shell structure is ready but work is not start


CSSD shell structure is ready but work is not start
MGPS 95% work complete but 5 % is balance
Status as on 31.01.2019 (Muzzafarpur )
Ground Second Fourth
Civil Works - Internal Works Floor First Floor Floor Third Floor Floor Fifth Floor Terrace Floor
Brick Work 80.00% 100.00 % 100.00 % 100.00 % 85.00 % 95.00 % 90.00 %
Plastering 70.00% 100.00 % 100.00 % 100.00 % 75.00% 90.00% 0.00%
False Ceiling 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Painting 0.00% 10.00% 10.00% 10.00% 5.00% 5.00% 0.00%
Plumbing works 25.00% 40.00% 40.00% 40.00% 40.00% 40.00% 0.00%
Sanitary Fixtures fixing 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Tiling works (Floor & Dado) 0.00% 90.00% 80.00% 80.00% 20.00% 10.00% 0.00%
Aluminium Joineries work 0.00% 10.00% 5.00% 0.00% 0.00% 0.00% 0.00%
Steel Joineries Work 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Wooden Joineries Works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Civil Worls - External Works


Plastering works 55.00 %
Painting works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Plumbing works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Structural glazing works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Water Proofing works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 80.00%

Electrical - Internal Works


Electrical Conduit 40.00% 100.00% 100.00% 90.00% 60.00% 80.00% 0.00%
Electrical Wiring 70.00% 80.00% 80.00% 80.00% 80.00% 70.00% 70.00%
DB Fixing 70.00% 80.00% 80.00% 80.00% 70.00% 70.00% 70.00%
MCB fixing and DB connections 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Light Fittings- All 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
LV Fittings-FAS,Detectors,CCTV 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Switch and Sockets Fixing 70.00% 70.00% 70.00% 70.00% 70.00% 70.00% 0.00%
Rising Main fixing NA NA NA NA NA NA NA
Cable tray fixing 70.00% 100.00% 90.00% 90.00% 70.00% 70.00% 0.00%

Electrical - External Works


LT cable laying 70.00%
HT cable laying 70.00%
SITC of LT Panels 60.00%
SITC of HT Panel 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Tranformer 80.00%
SITC of DG Set 80.00%
SITC of UPS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Solar Panel 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
External Lighting works along with Earthing Works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

HVAC Works
SITC of Plant room equipment (Chillers, pumps, Hot
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
water generators etc)
SITC of AHU, Indoor units (Ductable, cassette), FCU 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Ventilation fans 30.00 %
SITC of Ducting 60 % 80 % 80 % 80 % 80 % 50 %
SITC of Grills, Diffusers, Louvers, dampers etc 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Chilled water, Condenser water piping, insulation 80 % 80 % 80 % 80 % 80 % 80 % 60 %
SITC of HVAC panel, starter panel etc 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Fire Fighting works


SITC of piping network (Riser, Floor network, branches) 90.00% 85.00% 85.00% 85.00% 85.00% 85.00% 80.00%
SITC of Fire fighting plant room equipment (pumps,
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
pressure vessel, diesel tank etc)
SITC of Sprinkler system (Sprinklers, Flexible extension,
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Zonal control valves, installation control valves)
SITC of FHC equipment 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of internal/external hydrants 50 .00% 50 .00% 50 .00% 50 .00% 50 .00% 50 .00% 0.00%
SITC of Signages 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Status as on 31.01.2019 (Muzzafarpur )
Ground Second Fourth
Civil Works - Internal Works Floor First Floor Floor Third Floor Floor Fifth Floor Terrace Floor
Brick Work 80.00% 100.00 % 100.00 % 100.00 % 85.00 % 95.00 % 90.00 %
SITC of fire extinguishers 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

MGPS Work in progress at all floors


MOT work in all 8 nos. in progress
CT Scan Turnkey work in progress
Digital X-Ray Room Turnkey work in Progress
CSSD Room Turnkey work is under mobilization
Cath Lab Turnkey work in Progress
Status as on 30.04.2019 (Muzzafarpur )
Ground Second Fourth
Civil Works - Internal Works Floor First Floor Floor Third Floor Floor Fifth Floor Terrace Floor
Brick Work 90.00% 100.00 % 100.00 % 100.00 % 90.00% 97.00% 90.00 % #VALUE! #VALUE!
Plastering 80.00% 100.00 % 100.00 % 100.00 % 80.00% 90.00% 40.00% 290.00% 48.33333333
False Ceiling 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0
Painting 10.00% 10.00% 10.00% 10.00% 10.00% 10.00% 0.00% 60.00% 10
Plumbing works 25.00% 40.00% 40.00% 40.00% 40.00% 40.00% 0.00% 225.00% 37.5
Sanitary Fixtures fixing 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0
Tiling works (Floor & Dado) 70.00% 90.00% 90.00% 90.00% 90.00% 90.00% 0.00% 520.00% 86.66666667
Aluminium Joineries work 0.00% 10.00% 10.00% 10.00% 0.00% 0.00% 0.00% 30.00% 5
Steel Joineries Work 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0
Wooden Joineries Works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0
0% 0
Civil Worls - External Works 0% 0
Plastering works 75.00 % 0 0
Painting works 5.00% 5.00% 0.8333333333
Plumbing works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0
Structural glazing works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0
Water Proofing works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 90.00% 90.00% 15
0% 0
Electrical - Internal Works 0% 0
Electrical Conduit 70.00% 100.00% 100.00% 100.00% 90.00% 80.00% 0.00% 540.00% 90
Electrical Wiring 70.00% 90.00% 80.00% 90.00% 80.00% 70.00% 70.00% 550.00% 91.66666667
DB Fixing 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 70.00% 670.00% 111.6666667
MCB fixing and DB connections 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0
Light Fittings- All 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0
LV Fittings-FAS,Detectors,CCTV 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0
Switch and Sockets Fixing 70.00% 70.00% 70.00% 70.00% 70.00% 70.00% 0.00% 420.00% 70
Rising Main fixing NA NA NA NA NA NA NA 0% 0
Cable tray fixing 70.00% 100.00% 100.00% 100.00% 100.00% 100.00% 0.00% 570.00% 95
0% 0
Electrical - External Works 0% 0
LT cable laying 75.00% 75.00% 12.5
HT cable laying 70.00% 70.00% 11.66666667
SITC of LT Panels 85.00% 85.00% 14.16666667
SITC of HT Panel 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0
SITC of Tranformer 80.00% 80.00% 13.33333333
SITC of DG Set 80.00% 80.00% 13.33333333
SITC of UPS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0
SITC of Solar Panel 70.00% 70.00% 11.66666667
External Lighting works along with Earthing Works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0
0% 0
HVAC Works 0% 0
SITC of Plant room equipment (Chillers, pumps, Hot
60.00%
water generators etc) 60.00% 10
SITC of AHU, Indoor units (Ductable, cassette), FCU 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0
SITC of Ventilation fans 30.00 % 0 0
SITC of Ducting 90.00% 90.00% 90.00% 90.00% 90.00% 90.00% 540.00% 90
SITC of Grills, Diffusers, Louvers, dampers etc 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0
SITC of Chilled water, Condenser water piping, insulation 80 % 80 % 80 % 80 % 80 % 80 % 60 % 0% 0
SITC of HVAC panel, starter panel etc 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0
0% 0
Fire Fighting works 0% 0
SITC of piping network (Riser, Floor network, branches) 90.00% 85.00% 85.00% 85.00% 85.00% 85.00% 80.00% 595.00% 99.16666667
SITC of Fire fighting plant room equipment (pumps,
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
pressure vessel, diesel tank etc) 0.00% 0
SITC of Sprinkler system (Sprinklers, Flexible extension,
70.00% 70.00% 70.00% 70.00% 70.00% 70.00%
Zonal control valves, installation control valves) 420.00% 70
SITC of FHC equipment 70.00% 70.00% 70.00% 70.00% 70.00% 70.00% 70.00% 490.00% 81.66666667
SITC of internal/external hydrants 70.00% 70.00% 70.00% 70.00% 70.00% 70.00% 70.00% 490.00% 81.66666667
SITC of Signages 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0
SITC of fire extinguishers 70.00% 70.00% 70.00% 70.00% 70.00% 70.00% 70.00% 490.00% 81.66666667
Lifts - out of 8 Nos. 4 nos. Lift supplied at site 0 0
MGPS Work in progress at all floors 0 0
MOT work in all 8 nos. in progress 0 0
CT Scan Turnkey work in progress 0 0
Digital X-Ray Room Turnkey work in Progress 0 0
CSSD Room Turnkey work is in progress 0 0
Cath Lab Turnkey work in Progress 0 0
Status as on 03.07.2019 (Muzzafarpur )
Ground Second Fourth
Civil Works - Internal Works Floor First Floor Floor Third Floor Floor Fifth Floor Terrace Floor
Brick Work 96.00% 100.00 % 100.00 % 100.00 % 96.00% 97.00% 90.00 %
Plastering 90.00% 100.00 % 100.00 % 100.00 % 90.00% 95.00% 50.00%
False Ceiling 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Painting 10.00% 10.00% 10.00% 10.00% 10.00% 10.00% 0.00%
Plumbing works 40.00% 40.00% 40.00% 40.00% 40.00% 40.00% 0.00%
Sanitary Fixtures fixing 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Tiling works (Floor & Dado) 80.00% 90.00% 90.00% 90.00% 90.00% 90.00% 0.00%
Aluminium Joineries work 10.00% 10.00% 10.00% 10.00% 10.00% 10.00% 0.00%
Steel Joineries Work 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Wooden Joineries Works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Civil Worls - External Works


Plastering works 90.00 %
Painting works 5.00%
Plumbing works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Structural glazing works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Water Proofing works 50.00% 50.00% 50.00% 50.00% 50.00% 50.00% 90.00%

Electrical - Internal Works


Electrical Conduit 70.00% 100.00% 100.00% 100.00% 90.00% 80.00% 0.00%
Electrical Wiring 70.00% 90.00% 80.00% 90.00% 80.00% 70.00% 70.00%
DB Fixing 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 70.00%
MCB fixing and DB connections 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Light Fittings- All 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
LV Fittings-FAS,Detectors,CCTV 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Switch and Sockets Fixing 70.00% 70.00% 70.00% 70.00% 70.00% 70.00% 0.00%
Rising Main fixing NA NA NA NA NA NA NA
Cable tray fixing 70.00% 100.00% 100.00% 100.00% 100.00% 100.00% 0.00%

Electrical - External Works


LT cable laying 75.00%
HT cable laying 70.00%
SITC of LT Panels 85.00%
SITC of HT Panel 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Tranformer 80.00%
SITC of DG Set 80.00%
SITC of UPS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Solar Panel 70.00%
External Lighting works along with Earthing Works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

HVAC Works
SITC of Plant room equipment (Chillers, pumps, Hot
70.00%
water generators etc)
SITC of AHU, Indoor units (Ductable, cassette), FCU 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Ventilation fans 30.00 %
SITC of Ducting 90.00% 90.00% 90.00% 90.00% 90.00% 90.00%
SITC of Grills, Diffusers, Louvers, dampers etc 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Chilled water, Condenser water piping, insulation 80 % 80 % 80 % 80 % 80 % 80 % 60 %
SITC of HVAC panel, starter panel etc 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Fire Fighting works


SITC of piping network (Riser, Floor network, branches) 90.00% 85.00% 85.00% 85.00% 85.00% 85.00% 80.00%
SITC of Fire fighting plant room equipment (pumps,
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
pressure vessel, diesel tank etc)
SITC of Sprinkler system (Sprinklers, Flexible extension,
70.00% 70.00% 70.00% 70.00% 70.00% 70.00%
Zonal control valves, installation control valves)
SITC of FHC equipment 70.00% 70.00% 70.00% 70.00% 70.00% 70.00% 70.00%
SITC of internal/external hydrants 70.00% 70.00% 70.00% 70.00% 70.00% 70.00% 70.00%
SITC of Signages 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Status as on 03.07.2019 (Muzzafarpur )
Ground Second Fourth
Civil Works - Internal Works Floor First Floor Floor Third Floor Floor Fifth Floor Terrace Floor
Brick Work 96.00% 100.00 % 100.00 % 100.00 % 96.00% 97.00% 90.00 %
Plastering 90.00% 100.00 % 100.00 % 100.00 % 90.00% 95.00% 50.00%
SITC of fire extinguishers 70.00% 70.00% 70.00% 70.00% 70.00% 70.00% 70.00%
Lifts - out of 8 Nos. 4 nos. Lift supplied at site
MGPS Work in progress at all floors
MOT work in all 8 nos. in progress
CT Scan Turnkey work in progress
Digital X-Ray Room Turnkey work in Progress
CSSD Room Turnkey work is in progress
Cath Lab Turnkey work in Progress
Darbhanga Status as on 31.01.2019
Civil Works - Internal Works Ground Floor First Floor Second Floor Third Floor Fourth Floor Fifth Floor Terrace Floor Remarks
Brick Work 95.00% 98.00% 98.00% 98.00% 96.00% 95.00% 55.00%
Plastering 90.00% 98.00% 98.00% 98.00% 96.00% 95.00% 45.00%
30% Gypsum falseceiling
False Ceiling 0.00% 15.00% 0.00% 0.00% 0.00% 0.00% 0.00% material recieved at site
Putty received at site & work in
Painting 20.00% 35.00% 15.00% 15.00% 15.00% 10.00% 0.00% progress 40%
UPVC, Cpvc , CI Pipes received
at site CHASING AND CUTTING
Plumbing works 25.00% 60.00% 40.00% 40.00% 35.00% 10.00% 0.00% WORK IN PROGRESS
Plumbing and Sanitary Fixtures fixing 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Vitrified Tiles, Ceramic Wall Tiles,
Kota Stone and granite supplied
Tiling works (Floor & Dado) 45.00% 85.00% 75.00% 70.00% 50.00% 45.00% 25.00% at site
Sub base frame supplied at site &
Aluminium Joineries work 16.00% 22.00% 15.00% 15.00% 10.00% 5.00% 0.00% fixing in progress
Steel Joineries Works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Wooden Joineries Works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Civil Worls - External Works


Plastering works 65.00%
Painting works 10.00%
Plumbing works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Structural glazing works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Water Proofing works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Electrical - Internal Works


Electrical Conduit 80.00% 90.00% 90.00% 80.00% 50.00% 0.00% 0.00%
Electrical Wiring 80.00% 80.00% 80.00% 60.00% 0.00% 0.00% 0.00% 60% of wires received at site
DB Fixing 60.00% 80.00% 80.00% 60.00% 0.00% 0.00% 0.00% 100% DB received at site
MCB fixing and DB connections 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 70% MCB received at site
Light Fittings- All 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Material for LV system like ;
Conduit & wire,PA system,
EPABX, Fire detection etc
LV Fittings-FAS,Detectors,CCTV 0.00% 10.00% 10.00% 10.00% 5.00% 0.00% 0.00% recieved
Switch and Sockets Fixing 0.00% 5.00% 0.00% 0.00% 0.00% 0.00% 0.00% 50% quantity recieved at site
Rising Main fixing NA NA NA NA NA NA NA
Cable tray fixing 0.00% 60.00% 0.00% 0.00% 0.00% 0.00% 0.00% 25% qty recieved at site

Electrical - External Works


LT cable laying 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
HT cable laying 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Capacitors & Floor Panel
SITC of LT Panels 20.00% 75.00% 75.00% 75.00% 75.00% 75.00% 75.00% Received at Site
SITC of HT Panel 80.00% N.A HT Panel recevied at site
SITC of Tranformer 0.00% N.A
3 Nos DG Sets recevied at site
SITC of DG Set 80.00% and installed on Foundation
3 Nos UPS(100 KVA) recevied at
SITC of UPS 75.00% site
SITC of Solar Panel 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
External Lighting works along with Earthing Works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

HVAC Works
SITC of Plant room equipment (Chillers, 3 Nos Chillers received and
pumps, Hot water generators etc) 60.00% installed at terrace
SITC of AHU, Indoor units (Ductable, cassette), FCU 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Ventilation fans 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
90% GI Duct received at site
SITC of Ducting 63.00% 60.00% 73.00% 72.00% 60.00% 50.00% 0.00% 70% PIR Duct received at site
SITC of Grills, Diffusers, Louvers, dampers etc 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Chilled water, Condenser water piping, insulation
80.00% 80.00% 80.00% 80.00% 80.00% 80.00% 40.00% 80% of MS Pipe received at site
SITC of HVAC panel, starter panel etc 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Fire Fighting works


SITC of piping network (Riser, Floor network, branches)
90.00% 80.00% 80.00% 20.00% 20.00% 0.00% 0.00% 80% of Pipes received at site
SITC of Fire fighting plant room equipment
(pumps, pressure vessel, diesel tank etc) 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Sprinkler system (Sprinklers, Flexible
extension, Zonal control valves, installation
control valves) 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of FHC equipment 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of internal/external hydrants 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Signages 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of fire extinguishers 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
MOT Civil works completed by M/s GDCL,however third party agency for MOT interior work on turnkey works is not mobilized at site till date
CSSD Civil works completed by M/s GDCL,however third party agency for CSSD interior work on turnkey works has only visited the site & work not started yet
MGPS work is in progress
CT Scan Turnkey work in progress work in progress
Digital X-Ray Room Turnkey work in
Progress interior work is almost completed
Cath Lab Turnkey work in Progress work in progress
Darbhanga Status as on 30.04.2019
Civil Works - Internal Works Ground Floor First Floor Second Floor Third Floor Fourth Floor Fifth Floor Terrace Floor Remarks
Brick Work 96.00% 100.00% 100.00% 100.00% 98.00% 98.00% 55.00%
Plastering 91.00% 98.00% 98.00% 98.00% 96.00% 95.00% 45.00%
30% Gypsum false ceiling
False Ceiling 1.00% 15.00% 0.00% 0.00% 0.00% 0.00% 0.00% material recieved at site
Putty received at site & work in
Painting 20.00% 35.00% 15.00% 15.00% 15.00% 10.00% 0.00% progress
UPVC, Cpvc , CI Pipes received
at site CHASING AND CUTTING
Plumbing works 50.00% 65.00% 55.00% 55.00% 35.00% 10.00% 0.00% WORK IN PROGRESS
Plumbing and Sanitary Fixtures fixing 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Vitrified Tiles, Ceramic Wall Tiles,
Kota Stone and granite supplied
Tiling works (Floor & Dado) 55.00% 85.00% 78.00% 79.00% 65.00% 45.00% 25.00% at site
Sub base frame material (90%) &
Main frame material (16%)
supplied at site & fixing in
Aluminium Joineries work 16.00% 22.00% 15.00% 15.00% 10.00% 10.00% 0.00% progress
Steel Joineries Works 0.00% 5.00% 5.00% 5.00% 5.00% 5.00% 0.00% 25% of material received at site
Wooden Joineries Works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Civil Worls - External Works


Plastering works 75.00%
Painting works 10.00%
Plumbing works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Structural glazing works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Water Proofing works 5.00% 10.00% 10.00% 0.00% 0.00% 0.00% 35.00%

Electrical - Internal Works


Electrical Conduit 80.00% 90.00% 90.00% 80.00% 70.00% 15.00% 0.00%
Electrical Wiring 80.00% 80.00% 80.00% 65.00% 10.00% 0.00% 0.00% 60% of wires received at site
DB Fixing 60.00% 80.00% 80.00% 60.00% 0.00% 0.00% 0.00% 100% DB received at site
MCB fixing and DB connections 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 70% MCB received at site
Light Fittings- All 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Material for LV system like ;
Conduit & wire,PA system,
EPABX, Fire detection etc
LV Fittings-FAS,Detectors,CCTV 0.00% 20.00% 20.00% 10.00% 5.00% 0.00% 0.00% recieved
Switch and Sockets Fixing 0.00% 5.00% 0.00% 0.00% 0.00% 0.00% 0.00% 50% quantity recieved at site
Rising Main fixing NA NA NA NA NA NA NA
Cable tray fixing 0.00% 60.00% 0.00% 0.00% 0.00% 0.00% 0.00% 25% qty recieved at site

Electrical - External Works


LT cable laying 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
HT cable laying 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Capacitors & Floor Panel
SITC of LT Panels 20.00% 75.00% 75.00% 75.00% 75.00% 75.00% 75.00% Received at Site
SITC of HT Panel 80.00% N.A HT Panel recevied at site
SITC of Tranformer 0.00% N.A
3 Nos DG Sets recevied at site
SITC of DG Set 80.00% and installed on Foundation
3 Nos UPS(100 KVA) recevied at
SITC of UPS 75.00% site
SITC of Solar Panel 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
External Lighting works along with Earthing Works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

HVAC Works
SITC of Plant room equipment (Chillers, 3 Nos Chillers received and
pumps, Hot water generators etc) 60.00% installed at terrace
SITC of AHU, Indoor units (Ductable, cassette), FCU 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Ventilation fans 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
90% GI Duct received at site
SITC of Ducting 63.00% 60.00% 73.00% 72.00% 60.00% 50.00% 0.00% 70% PIR Duct received at site
SITC of Grills, Diffusers, Louvers, dampers etc 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Chilled water, Condenser water piping, insulation
80.00% 80.00% 80.00% 80.00% 80.00% 80.00% 40.00% 80% of MS Pipe received at site
SITC of HVAC panel, starter panel etc 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Fire Fighting works


SITC of piping network (Riser, Floor network, branches)
90.00% 80.00% 80.00% 60.00% 40.00% 10.00% 0.00% 80% of Pipes received at site
SITC of Fire fighting plant room equipment
(pumps, pressure vessel, diesel tank etc) 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Sprinkler system (Sprinklers, Flexible
extension, Zonal control valves, installation
control valves) 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of FHC equipment 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of internal/external hydrants 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Signages 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of fire extinguishers 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

MOT Civil works completed by M/s GDCL,however third party agency for MOT interior work on turnkey works is not mobilized at site till date
CSSD Work is in progress
MGPS work is in progress
CT Scan Turnkey work in progress work in progress
Digital X-Ray Room Turnkey work in
Progress interior work is almost completed
Cath Lab Turnkey work in Progress work in progress
Lifts - out of 8 Nos. 4 nos. Lift supplied at site
Darbhanga Status as on 03.07.2019
Civil Works - Internal Works Ground Floor First Floor Second Floor Third Floor Fourth Floor Fifth Floor Terrace Floor Remarks
Brick Work 96.00% 100.00% 100.00% 100.00% 98.00% 98.00% 74.00%
Plastering 91.00% 98.00% 98.00% 98.00% 96.00% 96.00% 55.00%
30% Gypsum false ceiling
False Ceiling 5.00% 20.00% 5.00% 0.00% 0.00% 0.00% 0.00% material recieved at site
Putty & primer received at site &
Painting 20.00% 37.00% 17.00% 17.00% 17.00% 12.00% 2.00% work in progress
UPVC, Cpvc , CI Pipes received
at site and work has stopped
Plumbing works 50.00% 70.00% 55.00% 55.00% 40.00% 15.00% 0.00% since last month
Plumbing and Sanitary Fixtures fixing 0.00% 5.00% 0.00% 0.00% 0.00% 0.00% 0.00%
75% Vitrified Tiles, Ceramic Wall
Tiles, Kota Stone and granite
supplied and fixed at at site and
Tiling works (Floor & Dado) 55.00% 90.00% 80.00% 79.00% 68.00% 50.00% 40.00% 20% is awaited
Sub base frame material (90%) &
Main frame material (16%)
supplied at site & fixing in
Aluminium Joineries work 16.00% 22.00% 15.00% 15.00% 10.00% 10.00% 0.00% progress
Steel Joineries Works 0.00% 5.00% 5.00% 5.00% 5.00% 5.00% 0.00% 25% of material received at site
Wooden Joineries Works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Civil Worls - External Works


Plastering works 80.00%
Painting works 15.00%
Plumbing works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Structural glazing works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Water Proofing works 5.00% 10.00% 10.00% 0.00% 0.00% 0.00% 75.00%

Electrical - Internal Works


Electrical Conduit 80.00% 92.00% 92.00% 80.00% 80.00% 20.00% 0.00%
Electrical Wiring 80.00% 80.00% 80.00% 65.00% 10.00% 0.00% 0.00% 60% of wires received at site
DB Fixing 60.00% 80.00% 80.00% 60.00% 0.00% 0.00% 0.00% 100% DB received at site
MCB fixing and DB connections 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 70% MCB received at site
Light Fittings- All 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% All Light Fixtures received at site
Material for LV system like ;
Conduit & wire,PA system,
EPABX, Fire detection etc
LV Fittings-FAS,Detectors,CCTV 0.00% 20.00% 20.00% 10.00% 5.00% 0.00% 0.00% recieved
Switch and Sockets Fixing 0.00% 5.00% 0.00% 0.00% 0.00% 0.00% 0.00% 50% quantity recieved at site
Rising Main fixing NA NA NA NA NA NA NA
Cable tray fixing 0.00% 60.00% 20.00% 0.00% 0.00% 0.00% 0.00% 25% qty recieved at site

Electrical - External Works


LT cable laying 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
HT cable laying 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Capacitors & Floor Panel
SITC of LT Panels 20.00% 75.00% 75.00% 75.00% 75.00% 75.00% 75.00% Received at Site
SITC of HT Panel 80.00% N.A HT Panel recevied at site
SITC of Tranformer 0.00% N.A
3 Nos DG Sets recevied at site
SITC of DG Set 80.00% and installed on Foundation
3 Nos UPS(100 KVA) recevied at
SITC of UPS 75.00% site
SITC of Solar Panel 70.00% Material Received at site
Solar Hot Water(FPC) 70.00% Material Received at site
External Lighting works along with Earthing Works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

HVAC Works
SITC of Plant room equipment (Chillers, 3 Nos Chillers received and
pumps, Hot water generators etc) 60.00% installed at terrace
SITC of AHU, Indoor units (Ductable, cassette), FCU 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Ventilation fans 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
90% GI Duct received at site
SITC of Ducting 63.00% 60.00% 73.00% 72.00% 60.00% 50.00% 0.00% 70% PIR Duct received at site
SITC of Grills, Diffusers, Louvers, dampers etc 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Chilled water, Condenser water piping, insulation
80.00% 80.00% 80.00% 80.00% 80.00% 80.00% 40.00% 80% of MS Pipe received at site
SITC of HVAC panel, starter panel etc 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Fire Fighting works


SITC of piping network (Riser, Floor network, branches)
90.00% 80.00% 80.00% 60.00% 40.00% 22.00% 0.00% 80% of Pipes received at site
SITC of Fire fighting plant room equipment
(pumps, pressure vessel, diesel tank etc) 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Sprinkler system (Sprinklers, Flexible
extension, Zonal control valves, installation
control valves) 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of FHC equipment 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of internal/external hydrants 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Signages 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of fire extinguishers 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

MOT Civil works completed by M/s GDCL,however third party agency for MOT interior work on turnkey works is not mobilized at site till date
CSSD Work is in progress
MGPS work is in progress
CT Scan Turnkey work in progress work in progress
Digital X-Ray Room Turnkey work in
Progress interior work is almost completed
Cath Lab Turnkey work in Progress work in progress
Lifts - out of 8 Nos. 4 nos. Lift supplied at site and installation work is in progress
PDUGMC Rajkot site Work Status
Ground Second Fourth
Civil Works - Internal Works floor First Floor Floor Third Floor Floor Fifth Floor Sixth Floor
Brick Work 100 100 100 100 100 100 100
Plastering 100 100 100 100 100 100 100
MATERIAL AT SITE BUT 65% area
False Ceiling 30 35 30 40 30 30 0 on hold due to MGPS WORK
PUTTY AND PRIMER WORK IN
Painting 35 30 30 30 30 30 30 PROGRESS
Plumbing works 95 95 95 90 95 95 95
Plumbing and Sanitary Fixtures fixing 0 0 0 0 0 0 0
Tiling works (Floor & Dado) 98 98 98 95 95 95 95
Aluminium Joineries work 85 85 85 85 80 85 90
Steel Joineries Work 90 90 90 90 90 85 85
Wooden Joineries Works 90 90 90 90 90 90 90
Civil Worls - External Works
Plastering works 100
Painting works 30
Plumbing works 95
Structural glazing works 40
Water Proofing works 99

Electrical - Internal Works


Electrical Conduit 100 98 98 98 98 98 80
Electrical Wiring 95 95 95 95 95 90 75
DB Fixing 90 90 90 90 90 90 90
MCB fixing and DB connections 85 85 85 85 85 85 85
Light Fittings- All FIXTURES DELIVER AT SITE
LV Fittings-FAS,Detectors,CCTV 70 70 70 70 60 60 30
Switch and Sockets Fixing DELIVER AT SITE
Rising Main fixing 100 100 100 100 100 100 100
Cable tray fixing 95 95 95 95 95 90 90

Electrical - External Works


LT cable laying 95 95 95 95 95 95 50 DELIVER AT SITE
HT cable laying 0 N.A N.A N.A N.A N.A N.A DELIVER AT SITE
SITC of LT Panels 0 0 0 0 0 0 0
SITC of HT Panel 85 N.A N.A N.A N.A N.A N.A
SITC of Tranformer 85 N.A N.A N.A N.A N.A N.A
SITC of DG Set 90
SITC of UPS 90 DELIVER AT SITE
SITC of Solar Panel N.A N.A N.A N.A N.A N.A 90
External Lighting works along with Earthing Works 0 N.A N.A N.A N.A N.A N.A Material deliver at site

HVAC Works
HVAC PUMP DELIVER AT SITE,
SITC of Plant room equipment (Chillers, pumps, Hot WHILE CHILLAR DELIVERY
water generators etc) PENDING
SITC of AHU, Indoor units (Ductable, cassette), FCU 80 80 80 80 80 80 NA AHU DELIVERED
SITC of Ventilation fans UNDER MANUFACTURING
SITC of Ducting 95 95 95 95 95 50
SITC of Grills, Diffusers, Louvers, dampers etc 0 0 0 0 0 0 0
SITC of Chilled water, Condenser water piping,
insulation 85 85 85 85 85 85 20
SITC of HVAC panel, starter panel etc UNDER MANUFACTURING

Fire Fighting works


SITC of piping network (Riser, Floor network, branches) 95 95 95 95 95 95 50
SITC of Fire fighting plant room equipment (pumps,
pressure vessel, diesel tank etc) 80 N.A N.A N.A N.A N.A N.A DELIVER AT SITE
SITC of Sprinkler system (Sprinklers, Flexible extension,
Zonal control valves, installation control valves) 90 90 90 90 90 90 90 DELIVER AT SITE
SITC of FHC equipment 80 80 80 80 80 80 80 DELIVER AT SITE
SITC of internal/external hydrants 80 80 80 80 80 80 80 DELIVER AT SITE
SITC of Signages 0 0 0 0 0 0
SITC of fire extinguishers 85 85 80 80 80 80 80 DELIVER AT SITE

MOT
CSSD
MGPS
Status as on 17.11.2018 (Muzzafarpur )
Ground Second Fourth Terrace
Civil Works - Internal Works Floor First Floor Floor Third Floor Floor Fifth Floor Floor
Brick Work 60.00% 100.00 % 100.00 % 100.00 % 70.00 % 90.00 % 90.00 %
Plastering 10.00 % 100.00 % 95.00 % 90.00 % 35.00% 70.00% 0.00%
False Ceiling 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Painting 0.00% 10.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Plumbing works 25.00% 40.00% 40.00% 40.00% 40.00% 40.00% 0.00%

Sanitary Fixtures fixing 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Tiling works (Floor & Dado) 0.00% 40.00% 5.00% 0.00% 0.00% 0.00% 0.00%
Aluminium Joineries work 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Steel Joineries Work 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Wooden Joineries Works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Civil Worls - External Works


Plastering works 5.00 %
Painting works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Plumbing works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Structural glazing works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Water Proofing works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 50.00%

Electrical - Internal Works


Electrical Conduit 30.00% 100.00% 100.00% 90.00% 60.00% 80.00% 0.00%
Electrical Wiring 70.00% 80.00% 80.00% 80.00% 80.00% 70.00% 70.00%
DB Fixing 35.00% 80.00% 80.00% 80.00% 35.00% 35.00% 0.00%
MCB fixing and DB connections 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Light Fittings- All 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
LV Fittings-FAS,Detectors,CCTV 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Switch and Sockets Fixing 70.00% 70.00% 70.00% 70.00% 70.00% 70.00% 0.00%
Rising Main fixing NA NA NA NA NA NA NA
Cable tray fixing 70.00% 100.00% 90.00% 90.00% 70.00% 70.00% 0.00%

Electrical - External Works


LT cable laying 70.00%
HT cable laying 70.00%
SITC of LT Panels 60.00%
SITC of HT Panel 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Tranformer 80.00%
SITC of DG Set 80.00%
SITC of UPS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Solar Panel 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
External Lighting works along with Earthing Works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

HVAC Works
SITC of Plant room equipment (Chillers, pumps, Hot
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
water generators etc)
SITC of AHU, Indoor units (Ductable, cassette), FCU 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Ventilation fans 30.00 %
SITC of Ducting 60 % 80 % 80 % 80 % 80 % 50 %
SITC of Grills, Diffusers, Louvers, dampers etc 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Chilled water, Condenser water piping, insulation 80 % 80 % 80 % 80 % 80 % 80 % 60 %
SITC of HVAC panel, starter panel etc 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Fire Fighting works


SITC of piping network (Riser, Floor network, branches) 90.00% 85.00% 85.00% 85.00% 85.00% 85.00% 80.00%
Status as on 17.11.2018 (Muzzafarpur )
Ground Second Fourth Terrace
Civil Works - Internal Works Floor First Floor Floor Third Floor Floor Fifth Floor Floor
Brick Work 60.00% 100.00 % 100.00 % 100.00 % 70.00 % 90.00 % 90.00 %
SITC of Fire fighting plant room equipment (pumps,
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
pressure vessel, diesel tank etc)
SITC of Sprinkler system (Sprinklers, Flexible extension,
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Zonal control valves, installation control valves)
SITC of FHC equipment 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of internal/external hydrants 50 .00% 50 .00% 50 .00% 50 .00% 50 .00% 50 .00% 0.00%
SITC of Signages 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of fire extinguishers 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Darbhanga Status as on 29.10.2018
Civil Works - Internal Works Ground Floor First Floor Second Floor Third Floor Fourth Floor Fifth Floor Terrace Floor Remarks
Brick Work 90.00% 99.00% 99.00% 98.00% 94.00% 94.00% 25.00%
Plastering 85.00% 97.00% 98.00% 97.00% 92.00% 90.00% 0.00%
False Ceiling 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Putty received at site & work in
Painting 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% progress 50%
UPVC, Cpvc Pipes received at
site CHASING AND CUTTING
Plumbing works 10.00% 30.00% 30.00% 30.00% 20.00% 15.00% 0.00% WORK IN PROGRESS
Plumbing and Sanitary Fixtures fixing 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Vitrified Tiles, Ceramic Wall Tiles,
Kota Stone and granite supplied
Tiling works (Floor & Dado) 50.00% 85.00% 75.00% 60.00% 20.00% 30.00% 0.00% at site
Sub base frame supplied at site &
Aluminium Joineries work 20.00% 25.00% 15.00% 10.00% 0.00% 0.00% 0.00% fixing in progress
Steel Joineries Works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Wooden Joineries Works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Civil Worls - External Works


Plastering works 25.00%
Painting works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Plumbing works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Structural glazing works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Water Proofing works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Electrical - Internal Works


Electrical Conduit 75.00% 90.00% 85.00% 60.00% 30.00% 0.00% 0.00%
Electrical Wiring 50.00% 50.00% 60.00% 20.00% 0.00% 0.00% 0.00% 50% of wires received at site
DB Fixing 60.00% 60.00% 60.00% 30.00% 0.00% 0.00% 0.00% 100% DB received at site
MCB fixing and DB connections 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 70% MCB received at site
Light Fittings- All 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Material for LV system like ;
Conduit & wire,PA system,
EPABX, Fire detection etc
LV Fittings-FAS,Detectors,CCTV 0.00% 7.00% 7.00% 7.00% 7.00% 0.00% 0.00% recieved
Switch and Sockets Fixing 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Rising Main fixing 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Cable tray fixing 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Electrical - External Works


LT cable laying 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
HT cable laying 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Capacitors & Floor Panel
SITC of LT Panels 20.00% 75.00% 75.00% 75.00% 75.00% 75.00% 75.00% Received at Site
SITC of HT Panel 80.00% N.A N.A N.A N.A N.A N.A HT Panel recevied at site
SITC of Tranformer 0.00% N.A N.A N.A N.A N.A N.A
3 Nos DG Sets recevied at site
SITC of DG Set 80.00% and installed on Foundation
3 Nos UPS(100 KVA) recevied at
SITC of UPS 75.00% site
SITC of Solar Panel 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
External Lighting works along with Earthing Works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

HVAC Works
SITC of Plant room equipment (Chillers, 3 Nos Chillers received and
pumps, Hot water generators etc) 60.00% installed at terrace
SITC of AHU, Indoor units (Ductable, cassette), FCU 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Ventilation fans 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
90% GI Duct received at site
SITC of Ducting 63.00% 75.00% 73.00% 72.00% 55.00% 50.00% 0.00% 70% PIR Duct received at site
SITC of Grills, Diffusers, Louvers, dampers etc 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Chilled water, Condenser water piping, insulation
80.00% 80.00% 80.00% 80.00% 80.00% 80.00% 40.00% 80% of MS Pipe received at site
SITC of HVAC panel, starter panel etc 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Fire Fighting works


SITC of piping network (Riser, Floor network, branches)
80.00% 80.00% 20.00% 20.00% 20.00% 0.00% 0.00% 65% of Pipes received at site
SITC of Fire fighting plant room equipment
(pumps, pressure vessel, diesel tank etc) 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Sprinkler system (Sprinklers, Flexible
extension, Zonal control valves, installation
control valves) 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of FHC equipment 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of internal/external hydrants 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Signages 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of fire extinguishers 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Status as on 31.08.2018
Ground Second Fourth Terrace
Civil Works - Internal Works Floor First Floor Floor Third Floor Floor Fifth Floor Floor
Brick Work 60.00% 100.00 % 100.00 % 100.00 % 70.00 % 90.00 % 90.00 %
Plastering 10.00 % 100.00 % 90.00 % 90.00 % 20.00% 60.00% 0.00%
False Ceiling 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Painting 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% Putty supplied at site
Material (CI pipe &
Fittings, GI pipe &
Plumbing works 25.00% 40.00% 40.00% 40.00% 40.00% 40.00% 0.00% fittings,UPVC pipe,
CPVC pipe & fittings
supplied at site
Sanitary Fixtures fixing 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
100 % quantity of
Vitrified Tiles, Ceramic
Wall Tiles, Kota
Stone, Ceramic Floor
Tiling works (Floor & Dado) 0.00% 30.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Tiles supplied at site
and 30% quantity of
Granite supplied at
site.
Aluminium Joineries work 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Steel Joineries Work 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Wooden Joineries Works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Civil Worls - External Works


Plastering works 5.00 %
Painting works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Plumbing works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Structural glazing works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Water Proofing works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 40.00%

Electrical - Internal Works


Electrical Conduit 30.00% 100.00% 100.00% 90.00% 60.00% 80.00% 0.00%
100 % qty. of Wire
Electrical Wiring 70.00% 80.00% 80.00% 80.00% 80.00% 70.00% 70.00% supplied at Site &
wiring in progress
80 % Qty. of DB
DB Fixing 35.00% 80.00% 80.00% 80.00% 35.00% 35.00% 0.00%
Supplied at Site
MCB fixing and DB connections 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Light Fittings- All 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
LV Fittings-FAS,Detectors,CCTV 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Switch & Socket
Switch and Sockets Fixing 70.00% 70.00% 70.00% 70.00% 70.00% 70.00% 0.00%
supplied at site
Rising Main fixing NA NA NA NA NA NA NA
Cable Tray Supplied
Cable tray fixing 70.00% 100.00% 90.00% 90.00% 70.00% 70.00% 0.00% at site & installation in
Progress

Electrical - External Works


Lt Cable supplied at
LT cable laying 70.00%
site
HT Cable supplied at
HT cable laying 70.00%
site
Out of 10 panel 8 Panel
SITC of LT Panels 60.00%
supplied at site
Manufacturing in
SITC of HT Panel 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
progress
SITC of Tranformer 80.00% Supplied at Site
SITC of DG Set 80.00% Supplied at Site
SITC of UPS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Solar Panel 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
External Lighting works along with Earthing Works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

HVAC Works
SITC of Plant room equipment (Chillers, pumps, Hot
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
water generators etc)
SITC of AHU, Indoor units (Ductable, cassette), FCU 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Ventilation fan part
SITC of Ventilation fans 30.00 %
qty. supplied at site
Ducting Material (PIR
& GI) received at site,
SITC of Ducting 60 % 80 % 80 % 80 % 80 % 50 %
installation in
progress.
SITC of Grills, Diffusers, Louvers, dampers etc 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
MS pipe supplied &
installalation in
SITC of Chilled water, Condenser water piping, insulation 80 % 80 % 80 % 80 % 80 % 80 % 60 % progress at site.
Insulation material
received at site.
SITC of HVAC panel, starter panel etc 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Fire Fighting works


Ms pipe supplied at
SITC of piping network (Riser, Floor network, branches) 90.00% 80.00% 80.00% 80.00% 80.00% 80.00% 80.00% site & installation in
progress
SITC of Fire fighting plant room equipment (pumps, Pumps submittal
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
pressure vessel, diesel tank etc) approved
SITC of Sprinkler system (Sprinklers, Flexible extension,
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Zonal control valves, installation control valves) Submittal approved
SITC of FHC equipment 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
MS pipe supplied at
SITC of internal/external hydrants 50 .00% 50 .00% 50 .00% 50 .00% 50 .00% 50 .00% 0.00% site & installation in
progress
SITC of Signages 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of fire extinguishers 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
PDUGMC Rajkot site Work Status
Ground Second Fourth
Civil Works - Internal Works floor First Floor Floor Third Floor Floor Fifth Floor Sixth Floor
Brick Work 100 99 99 98 99 98 99
Plastering 100 98 98 98 98 98 98
MATERIAL AT SITE
BUT NOT START
DUE TO MGPS
False Ceiling 30 35 30 40 30 30 0 WORK
PUTTY AND PRIMER
WORK IN
Painting 35 30 30 30 30 30 30 PROGRESS
Plumbing works 90 90 85 85 85 85 80
Plumbing and Sanitary Fixtures fixing 0 0 0 0 0 0 0
Tiling works (Floor & Dado) 90 90 90 90 90 80 90
Aluminium Joineries work 80 80 85 60 70 80 90
Steel Joineries Work 70 70 70 70 75 75 75
Wooden Joineries Works 90 90 90 90 85 90 90
Civil Worls - External Works
Plastering works 95
Painting works 30
Plumbing works 95
Structural glazing works 20
Water Proofing works 95

Electrical - Internal Works


Electrical Conduit 100 98 98 98 98 90 80
Electrical Wiring 95 95 95 95 95 85 75
DB Fixing 85 85 85 85 85 85 80
MCB fixing and DB connections 85 85 85 85 85 85 85
FIXTURES DELIVER
Light Fittings- All AT SITE
LV Fittings-FAS,Detectors,CCTV 60 60 60 60 50 50 20
Switch and Sockets Fixing DELIVER AT SITE
Rising Main fixing 100 100 100 100 100 100 100
Cable tray fixing 95 95 95 95 95 90 90

Electrical - External Works


LT cable laying 95 95 95 95 50 50 50 DELIVER AT SITE
HT cable laying 0 N.A N.A N.A N.A N.A N.A DELIVER AT SITE
SITC of LT Panels 0 0 0 0 0 0 0
SITC of HT Panel 80 N.A N.A N.A N.A N.A N.A
SITC of Tranformer 80 N.A N.A N.A N.A N.A N.A
SITC of DG Set 90
SITC of UPS 90 DELIVER AT SITE
SITC of Solar Panel N.A N.A N.A N.A N.A N.A 90
External Lighting works along with Earthing Works 0 N.A N.A N.A N.A N.A N.A Material deliver at site

HVAC Works
HVAC PUMP
DELIVER AT SITE,
SITC of Plant room equipment (Chillers, pumps, Hot WHILE CHILLAR
water generators etc) DELIVERY PENDING
SITC of AHU, Indoor units (Ductable, cassette), FCU 80 80 80 80 80 80 NA AHU DELIVERED
UNDER
SITC of Ventilation fans MANUFACTURING
SITC of Ducting 95 95 95 95 95 50
SITC of Grills, Diffusers, Louvers, dampers etc 0 0 0 0 0 0 0
SITC of Chilled water, Condenser water piping,
insulation 85 85 85 85 85 85 20
UNDER
SITC of HVAC panel, starter panel etc MANUFACTURING

Fire Fighting works


SITC of piping network (Riser, Floor network, branches) 95 95 95 95 95 95 50
SITC of Fire fighting plant room equipment (pumps,
pressure vessel, diesel tank etc) 80 N.A N.A N.A N.A N.A N.A DELIVER AT SITE
SITC of Sprinkler system (Sprinklers, Flexible extension,
Zonal control valves, installation control valves) 90 90 90 90 90 90 90 DELIVER AT SITE
SITC of FHC equipment 80 80 80 80 80 80 80 DELIVER AT SITE
SITC of internal/external hydrants 80 80 80 80 80 80 80 DELIVER AT SITE
SITC of Signages 0 0 0 0 0 0
SITC of fire extinguishers 70 70 70 70 70 70 70 DELIVER AT SITE
Status as on 31.08.2018
Civil Works - Internal Works Ground Floor First Floor Second Floor Third Floor Fourth Floor Fifth Floor Terrace Floor Remarks
Brick Work 88.00% 96.00% 96.00% 96.00% 90.00% 85.00% 10.00%
Plastering 75.00% 90.00% 90.00% 90.00% 80.00% 75.00% 0.00%
False Ceiling 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Putty received at
site & work in
Painting 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% progress 30%
UPVC Pipes
received at site
CHASING AND
CUTTING WORK
Plumbing works 10.00% 20.00% 10.00% 10.00% 10.00% 10.00% 0.00% IN PROGRESS
Plumbing and Sanitary Fixtures fixing 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Vitrified Tiles,
Ceramic Wall
Tiles, Kota Stone
and granite
Tiling works (Floor & Dado) 35.00% 75.00% 50.00% 45.00% 0.00% 20.00% 0.00% supplied at site
Sub base frame
supplied at site &
Aluminium Joineries work 15.00% 20.00% 5.00% 5.00% 0.00% 0.00% 0.00% fixing in progress
Steel Joineries Works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Wooden Joineries Works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Civil Worls - External Works


Plastering works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Painting works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Plumbing works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Structural glazing works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Water Proofing works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Electrical - Internal Works


Electrical Conduit 70.00% 80.00% 80.00% 60.00% 20.00% 0.00% 0.00%
50% of wires
Electrical Wiring 50.00% 50.00% 60.00% 20.00% 0.00% 0.00% 0.00% received at site
100% DB
DB Fixing 60.00% 60.00% 60.00% 30.00% 0.00% 0.00% 0.00% received at site
70% MCB
MCB fixing and DB connections 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% received at site
Light Fittings- All 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Material for LV
system like ;
Conduit & wire,
PA system,
EPABX, Fire
detection etc
LV Fittings-FAS,Detectors,CCTV 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% recieved
Switch and Sockets Fixing 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Rising Main fixing 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Cable tray fixing 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Electrical - External Works


LT cable laying 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
HT cable laying 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Capacitors &
Floor Panel
SITC of LT Panels 20.00% 75.00% 75.00% 75.00% 75.00% 75.00% 75.00% Received at Site
HT Panel
SITC of HT Panel 80.00% N.A N.A N.A N.A N.A N.A recevied at site
SITC of Tranformer 0.00% N.A N.A N.A N.A N.A N.A
3 Nos DG Sets
recevied at site
and installed on
SITC of DG Set 80.00% N.A N.A N.A N.A N.A N.A Foundation
3 Nos UPS(100
KVA) recevied at
SITC of UPS N.A N.A N.A N.A N.A N.A 75.00% site
SITC of Solar Panel 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
External Lighting works along with Earthing Works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

HVAC Works
3 Nos Chillers
received and
SITC of Plant room equipment (Chillers, installed at
pumps, Hot water generators etc) N.A N.A N.A N.A N.A N.A 50.00% terrace
SITC of AHU, Indoor units (Ductable, cassette), FCU 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Ventilation fans 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
90% GI Duct
received at site
70% PIR Duct
SITC of Ducting 63.00% 55.00% 73.00% 72.00% 55.00% 50.00% 0.00% received at site
SITC of Grills, Diffusers, Louvers, dampers etc 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
80% of MS Pipe
SITC of Chilled water, Condenser water piping, insulation
80.00% 80.00% 80.00% 80.00% 80.00% 80.00% 0.00% received at site
SITC of HVAC panel, starter panel etc 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Fire Fighting works


65% of Pipes
SITC of piping network (Riser, Floor network, branches)
80.00% 80.00% 20.00% 20.00% 20.00% 0.00% 0.00% received at site
SITC of Fire fighting plant room equipment
(pumps, pressure vessel, diesel tank etc) 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Sprinkler system (Sprinklers, Flexible
extension, Zonal control valves, installation
control valves) 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of FHC equipment 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of internal/external hydrants 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Signages 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of fire extinguishers 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Status as on 10.07.2018
Second Fourth
Civil Works - Internal Works Ground floor First Floor Floor Third Floor Floor Fifth Floor Sixth Floor
Brick Work 98 97 98 98 95 95 95
Plastering 98 95 95 94 95 92 92
MATERIAL AT SITE
BUT NOT START
DUE TO MGPS
False Ceiling 0 0 0 0 0 0 0 WORK
PUTTY AND PRIMER
WORK IN
Painting 20 20 20 20 20 20 20 PROGRESS
Plumbing works 90 85 85 85 85 85 80
Plumbing and Sanitary Fixtures fixing 0 0 0 0 0 0 0
Tiling works (Floor & Dado) 80 80 85 80 80 60 0
Aluminium Joineries work 30 20 20 20 20 10 0
Steel Joineries Work 0
Wooden Joineries Works 0

Civil Worls - External Works


Plastering works 95
Painting works 0
Plumbing works 95
Structural glazing works 0
Water Proofing works 95

Electrical - Internal Works


Electrical Conduit 100 96 96 96 96 85 70
Electrical Wiring 95 95 95 95 95 0 0
DB Fixing 80 80 80 80 80 80 80
MCB fixing and DB connections 80 80 80 80 80 80 80
FIXTURES DELIVER
Light Fittings- All AT SITE
LV Fittings-FAS,Detectors,CCTV 50 50 50 50 45 45 0
Switch and Sockets Fixing DELIVER AT SITE
Rising Main fixing 100 100 100 100 100 100 100
Cable tray fixing 90 90 90 90 90 90 90

Electrical - External Works


LT cable laying DELIVER AT SITE
HT cable laying DELIVER AT SITE
SITC of LT Panels 0 0 0 0 0 0 0
SITC of HT Panel 80 N.A N.A N.A N.A N.A N.A
SITC of Tranformer 80 N.A N.A N.A N.A N.A N.A
SITC of DG Set 90
SITC of UPS 70 DELIVER AT SITE
SITC of Solar Panel N.A N.A N.A N.A N.A N.A 70
External Lighting works along with Earthing Works 0 N.A N.A N.A N.A N.A N.A

HVAC Works
HVAC PUMP
DELIVER AT SITE,
SITC of Plant room equipment (Chillers, pumps, Hot WHILE CHILLAR
water generators etc) DELIVERY PENDING
AHU DELIVERY
SITC of AHU, Indoor units (Ductable, cassette), FCU 80 80 80 80 80 80 NA PENDING
APPROVAL
SITC of Ventilation fans PENDING
SITC of Ducting 95 95 95 95 95 10
SITC of Grills, Diffusers, Louvers, dampers etc 0 0 0 0 0 0 0
SITC of Chilled water, Condenser water piping,
insulation 85 85 85 85 85 85 20
SITC of HVAC panel, starter panel etc UNDER APPROVAL

Fire Fighting works


SITC of piping network (Riser, Floor network, branches) 95 95 95 95 95 95 50
SITC of Fire fighting plant room equipment (pumps,
pressure vessel, diesel tank etc) 70 N.A N.A N.A N.A N.A N.A DELIVER AT SITE
SITC of Sprinkler system (Sprinklers, Flexible extension,
Zonal control valves, installation control valves) 90 90 90 90 90 90 90 DELIVER AT SITE
SITC of FHC equipment 70 70 70 70 70 70 70 DELIVER AT SITE
SITC of internal/external hydrants 70 70 70 70 70 70 70 DELIVER AT SITE
SITC of Signages 0 0 0 0 0 0
SITC of fire extinguishers 70 70 70 70 70 70 70 DELIVER AT SITE
Status as on 10.07.2018
Ground Second Fourth Terrace
Civil Works - Internal Works Floor First Floor Floor Third Floor Floor Fifth Floor Floor
Brick Work 5% 100 % 100 % 100 % 60 % 90 % 90 %
Plastering 100 % 40 % 50 % 35 %
False Ceiling
Painting Putty supplied at site
Material (CI pipe &
Fittings, GI pipe &
fittings, CPVC pipe &
Plumbing works 25 % 40 % 15 % 15 % fittings supplied at site
Sanitary Fixtures fixing
Vitrified Tiles, Ceramic
Wall Tiles, Kota
Stone, Ceramic Floor
Tiling works (Floor & Dado) 5% Tiles supplied at site
Aluminium Joineries work
Steel Joineries Work
Wooden Joineries Works

Civil Worls - External Works


Plastering works 5%
Painting works
Plumbing works
Structural glazing works
Water Proofing works 25 %

Electrical - Internal Works


Electrical Conduit 30 % 100 % 100 % 90 % 30 % 80 %
100 % qty. of Wire
supplied at Site &
Electrical Wiring 70 % 80 % 70 % 70 % 70 % 70 % 70 % wiring in progress
50 % Qty. of DB
DB Fixing 35 % 35 % 35 % 35 % 35 % 35 % Supplied at Site
MCB fixing and DB connections
Light Fittings- All
LV Fittings-FAS,Detectors,CCTV
Switch & Socket
Switch and Sockets Fixing 70 % 70 % 70 % 70 % 70 % 70 % supplied at site
Rising Main fixing NA NA NA NA NA NA
Cable Tray Supplied
at site & installation in
Cable tray fixing 70 % 100 % 70 % 70 % 70 % 70 % Progress

Electrical - External Works


LT cable laying
HT cable laying
Inspection at Kollkata
SITC of LT Panels on 19/07/2018
Manufacturing in
SITC of HT Panel progress
Inspection at
Vadodara on
SITC of Tranformer 18/07/2018
Inspection at
Pantnagar, Rudrapur
SITC of DG Set on 23/07/2018
SITC of UPS
SITC of Solar Panel
External Lighting works along with Earthing Works

HVAC Works
SITC of Plant room equipment (Chillers, pumps, Hot
water generators etc)
SITC of AHU, Indoor units (Ductable, cassette), FCU
SITC of Ventilation fans
Ducting Material (PIR
SITC of Ducting 60 % 80 % 30 % 50 % 30 % 50 % & GI) received at site
SITC of Grills, Diffusers, Louvers, dampers etc
MS pipe supplied at
SITC of Chilled water, Condenser water piping, insulation 60 % 60 % 60 % 60 % 60 % 60 % 60 % site
SITC of HVAC panel, starter panel etc
Fire Fighting works
Ms pipe supplied at
site & installation in
SITC of piping network (Riser, Floor network, branches) 90 % 70 % 70 % 70 % 70 % 70 % 70 % progress
SITC of Fire fighting plant room equipment (pumps,
pressure vessel, diesel tank etc)
SITC of Sprinkler system (Sprinklers, Flexible extension,
Zonal control valves, installation control valves)
SITC of FHC equipment
MS pipe supplied at
site & installation in
SITC of internal/external hydrants 50 % 50 % 50 % 50 % 50 % 50 % progress
SITC of Signages
SITC of fire extinguishers

MOT
CSSD
MGPS
Status as on 10.07.2018
Civil Works - Internal Works Ground Floor First Floor Second Floor Third Floor Fourth Floor Fifth Floor Terrace Floor Remarks
Brick Work 85.00% 95.00% 95.00% 95.00% 85.00% 80.00% 10.00%
Plastering 75.00% 85.00% 85.00% 80.00% 75.00% 40.00% 0.00%
False Ceiling 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Putty received at
Painting 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% site
UPVC Pipes
Plumbing works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% received at site
Plumbing and Sanitary Fixtures fixing 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Vitrified Tiles,
Ceramic Wall
Tiles, Kota Stone
and granite
Tiling works (Floor & Dado) 15.00% 50.00% 30.00% 15.00% 0.00% 0.00% 0.00% supplied at site
Sub base frame
Aluminium Joineries work 5.00% 5.00% 5.00% 5.00% 0.00% 0.00% 0.00% supplied at site
Steel Joineries Works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Wooden Joineries Works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Civil Worls - External Works


Plastering works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Painting works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Plumbing works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Structural glazing works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Water Proofing works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Electrical - Internal Works


Electrical Conduit 70.00% 80.00% 80.00% 60.00% 20.00% 0.00% 0.00%
50% of wires
Electrical Wiring 50.00% 50.00% 60.00% 20.00% 0.00% 0.00% 0.00% received at site
100% DB
DB Fixing 60.00% 60.00% 60.00% 30.00% 0.00% 0.00% 0.00% received at site
70% MCB
MCB fixing and DB connections 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% received at site
Light Fittings- All 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
LV Fittings-FAS,Detectors,CCTV 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Switch and Sockets Fixing 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Rising Main fixing 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Cable tray fixing 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Electrical - External Works


LT cable laying 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
HT cable laying 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Capacitors &
Floor Panel
SITC of LT Panels 20.00% 75.00% 75.00% 75.00% 75.00% 75.00% 75.00% Received at Site
HT Panel
SITC of HT Panel 80.00% N.A N.A N.A N.A N.A N.A recevied at site
SITC of Tranformer 0.00% N.A N.A N.A N.A N.A N.A
3 Nos DG Sets
recevied at site
and installed on
SITC of DG Set 80.00% N.A N.A N.A N.A N.A N.A Foundation
3 Nos UPS(100
KVA) recevied at
SITC of UPS N.A N.A N.A N.A N.A N.A 75.00% site
SITC of Solar Panel 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
External Lighting works along with Earthing Works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

HVAC Works
SITC of Plant room equipment (Chillers, 3 Nos Chillers
pumps, Hot water generators etc) N.A N.A N.A N.A N.A N.A 50.00% received at site
SITC of AHU, Indoor units (Ductable, cassette), FCU 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Ventilation fans 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
90% GI Duct
received at site
70% PIR Duct
SITC of Ducting 60.00% 50.00% 70.00% 70.00% 50.00% 50.00% 0.00% received at site
SITC of Grills, Diffusers, Louvers, dampers etc 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
80% of MS Pipe
SITC of Chilled water, Condenser water piping, insulation
80.00% 80.00% 80.00% 80.00% 80.00% 80.00% 0.00% received at site
SITC of HVAC panel, starter panel etc 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Fire Fighting works
65% of Pipes
SITC of piping network (Riser, Floor network, branches)
80.00% 80.00% 20.00% 20.00% 20.00% 0.00% 0.00% received at site
SITC of Fire fighting plant room equipment
(pumps, pressure vessel, diesel tank etc) 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Sprinkler system (Sprinklers, Flexible
extension, Zonal control valves, installation
control valves) 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of FHC equipment 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of internal/external hydrants 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Signages 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of fire extinguishers 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%