2019
Ground Second Fourth
Civil Works - Internal Works floor First Floor Floor Third Floor Floor Fifth Floor
Brick Work 100 100 100 100 100 100
Plastering 100 100 100 100 100 100
False Ceiling 100 100 100 100 100 100
Painting 100 100 100 100 100 100
Plumbing works 100 100 100 100 100 100
Plumbing and Sanitary Fixtures fixing 100 100 100 100 100 100
Tiling works (Floor & Dado) 100 100 100 100 100 100
Aluminium Joineries work 100 100 100 100 100 100
Steel Joineries Work 100 100 100 100 100 100
Wooden Joineries Works 100 100 100 100 100 100
Civil Worls - External Works
Plastering works 100
Painting works 100
Plumbing works 100
Structural glazing works 100
Water Proofing works 100
HVAC Works
SITC of Plant room equipment (Chillers, pumps, Hot
water generators etc)
SITC of AHU, Indoor units (Ductable, cassette), FCU 100 100 100 100 100 100
SITC of Ventilation fans
SITC of Ducting 100 100 99 100 100 100
SITC of Grills, Diffusers, Louvers, dampers etc 100 100 100 100 100 100
SITC of Chilled water, Condenser water piping,
insulation 100 100 100 100 100 100
SITC of HVAC panel, starter panel etc
HVAC Works
SITC of Plant room equipment (Chillers, pumps, Hot
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
water generators etc)
SITC of AHU, Indoor units (Ductable, cassette), FCU 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Ventilation fans 30.00 %
SITC of Ducting 60 % 80 % 80 % 80 % 80 % 50 %
SITC of Grills, Diffusers, Louvers, dampers etc 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Chilled water, Condenser water piping, insulation 80 % 80 % 80 % 80 % 80 % 80 % 60 %
SITC of HVAC panel, starter panel etc 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
HVAC Works
SITC of Plant room equipment (Chillers, pumps, Hot
70.00%
water generators etc)
SITC of AHU, Indoor units (Ductable, cassette), FCU 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Ventilation fans 30.00 %
SITC of Ducting 90.00% 90.00% 90.00% 90.00% 90.00% 90.00%
SITC of Grills, Diffusers, Louvers, dampers etc 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Chilled water, Condenser water piping, insulation 80 % 80 % 80 % 80 % 80 % 80 % 60 %
SITC of HVAC panel, starter panel etc 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
HVAC Works
SITC of Plant room equipment (Chillers, 3 Nos Chillers received and
pumps, Hot water generators etc) 60.00% installed at terrace
SITC of AHU, Indoor units (Ductable, cassette), FCU 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Ventilation fans 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
90% GI Duct received at site
SITC of Ducting 63.00% 60.00% 73.00% 72.00% 60.00% 50.00% 0.00% 70% PIR Duct received at site
SITC of Grills, Diffusers, Louvers, dampers etc 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Chilled water, Condenser water piping, insulation
80.00% 80.00% 80.00% 80.00% 80.00% 80.00% 40.00% 80% of MS Pipe received at site
SITC of HVAC panel, starter panel etc 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
HVAC Works
SITC of Plant room equipment (Chillers, 3 Nos Chillers received and
pumps, Hot water generators etc) 60.00% installed at terrace
SITC of AHU, Indoor units (Ductable, cassette), FCU 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Ventilation fans 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
90% GI Duct received at site
SITC of Ducting 63.00% 60.00% 73.00% 72.00% 60.00% 50.00% 0.00% 70% PIR Duct received at site
SITC of Grills, Diffusers, Louvers, dampers etc 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Chilled water, Condenser water piping, insulation
80.00% 80.00% 80.00% 80.00% 80.00% 80.00% 40.00% 80% of MS Pipe received at site
SITC of HVAC panel, starter panel etc 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
MOT Civil works completed by M/s GDCL,however third party agency for MOT interior work on turnkey works is not mobilized at site till date
CSSD Work is in progress
MGPS work is in progress
CT Scan Turnkey work in progress work in progress
Digital X-Ray Room Turnkey work in
Progress interior work is almost completed
Cath Lab Turnkey work in Progress work in progress
Lifts - out of 8 Nos. 4 nos. Lift supplied at site
Darbhanga Status as on 03.07.2019
Civil Works - Internal Works Ground Floor First Floor Second Floor Third Floor Fourth Floor Fifth Floor Terrace Floor Remarks
Brick Work 96.00% 100.00% 100.00% 100.00% 98.00% 98.00% 74.00%
Plastering 91.00% 98.00% 98.00% 98.00% 96.00% 96.00% 55.00%
30% Gypsum false ceiling
False Ceiling 5.00% 20.00% 5.00% 0.00% 0.00% 0.00% 0.00% material recieved at site
Putty & primer received at site &
Painting 20.00% 37.00% 17.00% 17.00% 17.00% 12.00% 2.00% work in progress
UPVC, Cpvc , CI Pipes received
at site and work has stopped
Plumbing works 50.00% 70.00% 55.00% 55.00% 40.00% 15.00% 0.00% since last month
Plumbing and Sanitary Fixtures fixing 0.00% 5.00% 0.00% 0.00% 0.00% 0.00% 0.00%
75% Vitrified Tiles, Ceramic Wall
Tiles, Kota Stone and granite
supplied and fixed at at site and
Tiling works (Floor & Dado) 55.00% 90.00% 80.00% 79.00% 68.00% 50.00% 40.00% 20% is awaited
Sub base frame material (90%) &
Main frame material (16%)
supplied at site & fixing in
Aluminium Joineries work 16.00% 22.00% 15.00% 15.00% 10.00% 10.00% 0.00% progress
Steel Joineries Works 0.00% 5.00% 5.00% 5.00% 5.00% 5.00% 0.00% 25% of material received at site
Wooden Joineries Works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
HVAC Works
SITC of Plant room equipment (Chillers, 3 Nos Chillers received and
pumps, Hot water generators etc) 60.00% installed at terrace
SITC of AHU, Indoor units (Ductable, cassette), FCU 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Ventilation fans 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
90% GI Duct received at site
SITC of Ducting 63.00% 60.00% 73.00% 72.00% 60.00% 50.00% 0.00% 70% PIR Duct received at site
SITC of Grills, Diffusers, Louvers, dampers etc 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Chilled water, Condenser water piping, insulation
80.00% 80.00% 80.00% 80.00% 80.00% 80.00% 40.00% 80% of MS Pipe received at site
SITC of HVAC panel, starter panel etc 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
MOT Civil works completed by M/s GDCL,however third party agency for MOT interior work on turnkey works is not mobilized at site till date
CSSD Work is in progress
MGPS work is in progress
CT Scan Turnkey work in progress work in progress
Digital X-Ray Room Turnkey work in
Progress interior work is almost completed
Cath Lab Turnkey work in Progress work in progress
Lifts - out of 8 Nos. 4 nos. Lift supplied at site and installation work is in progress
PDUGMC Rajkot site Work Status
Ground Second Fourth
Civil Works - Internal Works floor First Floor Floor Third Floor Floor Fifth Floor Sixth Floor
Brick Work 100 100 100 100 100 100 100
Plastering 100 100 100 100 100 100 100
MATERIAL AT SITE BUT 65% area
False Ceiling 30 35 30 40 30 30 0 on hold due to MGPS WORK
PUTTY AND PRIMER WORK IN
Painting 35 30 30 30 30 30 30 PROGRESS
Plumbing works 95 95 95 90 95 95 95
Plumbing and Sanitary Fixtures fixing 0 0 0 0 0 0 0
Tiling works (Floor & Dado) 98 98 98 95 95 95 95
Aluminium Joineries work 85 85 85 85 80 85 90
Steel Joineries Work 90 90 90 90 90 85 85
Wooden Joineries Works 90 90 90 90 90 90 90
Civil Worls - External Works
Plastering works 100
Painting works 30
Plumbing works 95
Structural glazing works 40
Water Proofing works 99
HVAC Works
HVAC PUMP DELIVER AT SITE,
SITC of Plant room equipment (Chillers, pumps, Hot WHILE CHILLAR DELIVERY
water generators etc) PENDING
SITC of AHU, Indoor units (Ductable, cassette), FCU 80 80 80 80 80 80 NA AHU DELIVERED
SITC of Ventilation fans UNDER MANUFACTURING
SITC of Ducting 95 95 95 95 95 50
SITC of Grills, Diffusers, Louvers, dampers etc 0 0 0 0 0 0 0
SITC of Chilled water, Condenser water piping,
insulation 85 85 85 85 85 85 20
SITC of HVAC panel, starter panel etc UNDER MANUFACTURING
MOT
CSSD
MGPS
Status as on 17.11.2018 (Muzzafarpur )
Ground Second Fourth Terrace
Civil Works - Internal Works Floor First Floor Floor Third Floor Floor Fifth Floor Floor
Brick Work 60.00% 100.00 % 100.00 % 100.00 % 70.00 % 90.00 % 90.00 %
Plastering 10.00 % 100.00 % 95.00 % 90.00 % 35.00% 70.00% 0.00%
False Ceiling 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Painting 0.00% 10.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Plumbing works 25.00% 40.00% 40.00% 40.00% 40.00% 40.00% 0.00%
Sanitary Fixtures fixing 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Tiling works (Floor & Dado) 0.00% 40.00% 5.00% 0.00% 0.00% 0.00% 0.00%
Aluminium Joineries work 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Steel Joineries Work 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Wooden Joineries Works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
HVAC Works
SITC of Plant room equipment (Chillers, pumps, Hot
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
water generators etc)
SITC of AHU, Indoor units (Ductable, cassette), FCU 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Ventilation fans 30.00 %
SITC of Ducting 60 % 80 % 80 % 80 % 80 % 50 %
SITC of Grills, Diffusers, Louvers, dampers etc 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Chilled water, Condenser water piping, insulation 80 % 80 % 80 % 80 % 80 % 80 % 60 %
SITC of HVAC panel, starter panel etc 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
HVAC Works
SITC of Plant room equipment (Chillers, 3 Nos Chillers received and
pumps, Hot water generators etc) 60.00% installed at terrace
SITC of AHU, Indoor units (Ductable, cassette), FCU 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Ventilation fans 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
90% GI Duct received at site
SITC of Ducting 63.00% 75.00% 73.00% 72.00% 55.00% 50.00% 0.00% 70% PIR Duct received at site
SITC of Grills, Diffusers, Louvers, dampers etc 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Chilled water, Condenser water piping, insulation
80.00% 80.00% 80.00% 80.00% 80.00% 80.00% 40.00% 80% of MS Pipe received at site
SITC of HVAC panel, starter panel etc 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
HVAC Works
SITC of Plant room equipment (Chillers, pumps, Hot
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
water generators etc)
SITC of AHU, Indoor units (Ductable, cassette), FCU 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Ventilation fan part
SITC of Ventilation fans 30.00 %
qty. supplied at site
Ducting Material (PIR
& GI) received at site,
SITC of Ducting 60 % 80 % 80 % 80 % 80 % 50 %
installation in
progress.
SITC of Grills, Diffusers, Louvers, dampers etc 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
MS pipe supplied &
installalation in
SITC of Chilled water, Condenser water piping, insulation 80 % 80 % 80 % 80 % 80 % 80 % 60 % progress at site.
Insulation material
received at site.
SITC of HVAC panel, starter panel etc 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
HVAC Works
HVAC PUMP
DELIVER AT SITE,
SITC of Plant room equipment (Chillers, pumps, Hot WHILE CHILLAR
water generators etc) DELIVERY PENDING
SITC of AHU, Indoor units (Ductable, cassette), FCU 80 80 80 80 80 80 NA AHU DELIVERED
UNDER
SITC of Ventilation fans MANUFACTURING
SITC of Ducting 95 95 95 95 95 50
SITC of Grills, Diffusers, Louvers, dampers etc 0 0 0 0 0 0 0
SITC of Chilled water, Condenser water piping,
insulation 85 85 85 85 85 85 20
UNDER
SITC of HVAC panel, starter panel etc MANUFACTURING
HVAC Works
3 Nos Chillers
received and
SITC of Plant room equipment (Chillers, installed at
pumps, Hot water generators etc) N.A N.A N.A N.A N.A N.A 50.00% terrace
SITC of AHU, Indoor units (Ductable, cassette), FCU 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Ventilation fans 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
90% GI Duct
received at site
70% PIR Duct
SITC of Ducting 63.00% 55.00% 73.00% 72.00% 55.00% 50.00% 0.00% received at site
SITC of Grills, Diffusers, Louvers, dampers etc 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
80% of MS Pipe
SITC of Chilled water, Condenser water piping, insulation
80.00% 80.00% 80.00% 80.00% 80.00% 80.00% 0.00% received at site
SITC of HVAC panel, starter panel etc 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
HVAC Works
HVAC PUMP
DELIVER AT SITE,
SITC of Plant room equipment (Chillers, pumps, Hot WHILE CHILLAR
water generators etc) DELIVERY PENDING
AHU DELIVERY
SITC of AHU, Indoor units (Ductable, cassette), FCU 80 80 80 80 80 80 NA PENDING
APPROVAL
SITC of Ventilation fans PENDING
SITC of Ducting 95 95 95 95 95 10
SITC of Grills, Diffusers, Louvers, dampers etc 0 0 0 0 0 0 0
SITC of Chilled water, Condenser water piping,
insulation 85 85 85 85 85 85 20
SITC of HVAC panel, starter panel etc UNDER APPROVAL
HVAC Works
SITC of Plant room equipment (Chillers, pumps, Hot
water generators etc)
SITC of AHU, Indoor units (Ductable, cassette), FCU
SITC of Ventilation fans
Ducting Material (PIR
SITC of Ducting 60 % 80 % 30 % 50 % 30 % 50 % & GI) received at site
SITC of Grills, Diffusers, Louvers, dampers etc
MS pipe supplied at
SITC of Chilled water, Condenser water piping, insulation 60 % 60 % 60 % 60 % 60 % 60 % 60 % site
SITC of HVAC panel, starter panel etc
Fire Fighting works
Ms pipe supplied at
site & installation in
SITC of piping network (Riser, Floor network, branches) 90 % 70 % 70 % 70 % 70 % 70 % 70 % progress
SITC of Fire fighting plant room equipment (pumps,
pressure vessel, diesel tank etc)
SITC of Sprinkler system (Sprinklers, Flexible extension,
Zonal control valves, installation control valves)
SITC of FHC equipment
MS pipe supplied at
site & installation in
SITC of internal/external hydrants 50 % 50 % 50 % 50 % 50 % 50 % progress
SITC of Signages
SITC of fire extinguishers
MOT
CSSD
MGPS
Status as on 10.07.2018
Civil Works - Internal Works Ground Floor First Floor Second Floor Third Floor Fourth Floor Fifth Floor Terrace Floor Remarks
Brick Work 85.00% 95.00% 95.00% 95.00% 85.00% 80.00% 10.00%
Plastering 75.00% 85.00% 85.00% 80.00% 75.00% 40.00% 0.00%
False Ceiling 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Putty received at
Painting 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% site
UPVC Pipes
Plumbing works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% received at site
Plumbing and Sanitary Fixtures fixing 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Vitrified Tiles,
Ceramic Wall
Tiles, Kota Stone
and granite
Tiling works (Floor & Dado) 15.00% 50.00% 30.00% 15.00% 0.00% 0.00% 0.00% supplied at site
Sub base frame
Aluminium Joineries work 5.00% 5.00% 5.00% 5.00% 0.00% 0.00% 0.00% supplied at site
Steel Joineries Works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Wooden Joineries Works 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
HVAC Works
SITC of Plant room equipment (Chillers, 3 Nos Chillers
pumps, Hot water generators etc) N.A N.A N.A N.A N.A N.A 50.00% received at site
SITC of AHU, Indoor units (Ductable, cassette), FCU 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Ventilation fans 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
90% GI Duct
received at site
70% PIR Duct
SITC of Ducting 60.00% 50.00% 70.00% 70.00% 50.00% 50.00% 0.00% received at site
SITC of Grills, Diffusers, Louvers, dampers etc 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
80% of MS Pipe
SITC of Chilled water, Condenser water piping, insulation
80.00% 80.00% 80.00% 80.00% 80.00% 80.00% 0.00% received at site
SITC of HVAC panel, starter panel etc 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Fire Fighting works
65% of Pipes
SITC of piping network (Riser, Floor network, branches)
80.00% 80.00% 20.00% 20.00% 20.00% 0.00% 0.00% received at site
SITC of Fire fighting plant room equipment
(pumps, pressure vessel, diesel tank etc) 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Sprinkler system (Sprinklers, Flexible
extension, Zonal control valves, installation
control valves) 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of FHC equipment 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of internal/external hydrants 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of Signages 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SITC of fire extinguishers 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%