Approximate Estimate of Building

The document provides a breakdown of the estimated costs to build a hospital with a plinth area of 10500 sqm. It lists the plinth area rate, percentages for architectural treatments, utilities installation, electricity, other services, contingencies, and supervision charges. It then calculates the total costs by multiplying the plinth area by rate and adding the costs for each category to get a final estimated total cost of Rs. 303,123,240.

Uploaded by

Pankaj Kapil
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
151 views4 pages

Approximate Estimate of Building

The document provides a breakdown of the estimated costs to build a hospital with a plinth area of 10500 sqm. It lists the plinth area rate, percentages for architectural treatments, utilities installation, electricity, other services, contingencies, and supervision charges. It then calculates the total costs by multiplying the plinth area by rate and adding the costs for each category to get a final estimated total cost of Rs. 303,123,240.

Uploaded by

Pankaj Kapil
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

Prepare an approximate estimate of a Hospital building having plinth area eq

1 Plinth area rate as Rs. 3200 per cum. 10500 sqm


2 Special Architectural treatment 2% of cost of building
3 Water supply and sanitory installation 5% of cost of building
4 Electric installation 14% of cost of building
5 Other services 6% of cost of building
6 Contingencies 3% of overall cost of building
7 Supervision charges 8% of overall cost of building

A Cost of building (Plinth area x rate)


33,600,000.00

B Cost of special architectural


672,000.00

C Water supply and sanitory installation


1,680,000.00

D Electric installation
4,704,000.00

E Other services
2,016,000.00

PLUMBING sanitary fixture


18396000
ELECTRICAL panel, transfarmer, DG Sets
104842500
HVAC work
68250000
FIREFIGHTING
16926000
LIFTS
22680000
SEWERAGE TREATMENT PLANT & EFFULENT TREATMENT PLANT (STP & ETP)
22785000
WATER TREATMENT PLANT & RO
4620000
SOLAR HOT WATER SYSTEM
3675000
LV SYSTEM (Fire Alarm, detection, Public Address , CCTV, Data Network, Access control, etc.)
28350000
BUILDING MANAGEMENT SYSTEM
6825000
SIGNAGES
1,312,500.00
Total of services
273,084,000.00
F Contingencies
8,192,520.00

G Supervision charges
21,846,720.00

Total Cost
303,123,240.00
g plinth area equal to 10500 sq.m