0% found this document useful (0 votes)
53 views4 pages

123 PDF

The document is an accomplishment report for the proposed renovation, alteration, and addition of the Pamana Medical Center as of April 11, 2019. It details the completed work and financials across various project components, including general requirements, structural, architectural, plumbing, and electrical work for multiple floors. All listed items show 100% accomplishment with a total project cost of 35,085,533.50 for various construction and supply categories.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
53 views4 pages

123 PDF

The document is an accomplishment report for the proposed renovation, alteration, and addition of the Pamana Medical Center as of April 11, 2019. It details the completed work and financials across various project components, including general requirements, structural, architectural, plumbing, and electrical work for multiple floors. All listed items show 100% accomplishment with a total project cost of 35,085,533.50 for various construction and supply categories.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

Project : PROPOSED RENOVATION, ALTERATION AND ADDITION OF PAMANA MEDICAL CENTER

Subject : ACCOMPLISHMENT REPORT


Date : AS OF APRIL 11, 2019
Location : [Link] CALAMBA LAGUNA

REMAINING EQUIVALENT EQUIVALENT REMAINING


A GENERAL REQUIREMENTS ACCOMPLISHED TOTAL AMOUNT
BALANCE ACCOMPLISHED BALANCE

A.1 Mobilization/Demobilization/Perm
its
Mobilization By Contractor /
A.1 Permits by Owner, Contractor 100.00 226,172.63 - 226,172.63
legwork only
Demobilization 100.00 226,172.63 - 226,172.63
Demolition of existing struct.
,existing fence /obstructions(
clearing of trees ) , canopy &
A.2 restoration works- ( affected 100.00 3,511,626.55 - 3,511,626.55
roofing & gutter, trussess,
structural member, downspout &
drainage )
Full contractual compliance
(Relocation Survey, As built,
A.3 100.00 1,964,746.16 - 1,964,746.16
Gondula, Safety requirements -
PPE, Net, Canopy )
Bonds and Certificates-
100.00 2,292,755.45 - 2,292,755.45
(CARI,Performance and Guarntee)

Running Cost for Site Facilities &


100.00 2,602,950.06 - 2,602,950.06
Supervision ( Site Management )
Operation and Maintenance
A.7 Requirements ( General Cleaning , 100.00 1,041,063.30 - 1,041,063.30
Hauling & Disposal )
Temporary Electricity ( Provide by
A.8 Owner, Tapping meter by 100.00 9,727.02 - 9,727.02
Contractor )
Temporary Water Supply (
A.9 Provide by Owner, Tapping meter 100.00 4,863.51 - 4,863.51
by Contractor )
A.10 Lay out & Stake out 100.00 16,831.63 - 16,831.63
11,896,908.94 100.00 11,896,908.94 -
B. LOWER GROUND FLOOR
STRUCTURAL 100.00 23,517,211.20 - 23,517,211.20 -
ARCHITECTURAL 100.00 5,127,150.26 - 5,127,150.26 -
PLUMBING 100.00 1,566,172.03 - 1,566,172.03 -
ELECTRICAL 100.00 4,875,000.00 - 4,875,000.00 -
SUBTOTAL 35,085,533.50 100.00 35,085,533.50 -
OWNER SUPPLIED MATERIALS
DOOR AND JAMBS (WITHOUT
100.00 912,900.00 - 912,900.00
HARDWARES)
FLOORING 100.00 1,776,634.45 - 1,776,634.45
WINDOW 100.00 305,106.24 - 305,106.24
AIRCON 100.00 1,241,050.00 - 1,241,050.00
ELECTRICAL 100.00 877,305.20 - 877,305.20
PLUMBING 100.00 553,864.00 - 553,864.00
SUBTOTAL 5,666,859.89 100.00 5,666,859.89
C. UPPER GROUND FLOOR
STRUCTURAL 100.00 5,774,761.66 - 5,774,761.66 -
ARCHITECTURAL 100.00 5,127,150.26 - 5,127,150.26 -
PLUMBING 100.00 1,566,172.03 - 1,566,172.03 -
ELECTRICAL 100.00 4,875,000.00 - 4,875,000.00 -
SUBTOTAL 17,343,083.95 100.00 17,343,083.95 -
OWNER SUPPLIED MATERIALS
DOOR AND JAMBS (WITHOUT
100.00 788,200.00 - 788,200.00
HARDWARES)
FLOORING 100.00 645,619.60 - 645,619.60
WINDOW 100.00 1,232,084.85 - 1,232,084.85
AIRCON 100.00 1,484,000.00 - 1,484,000.00
ELECTRICAL 100.00 802,543.80 - 802,543.80
PLUMBING 100.00 1,244,268.00 - 1,244,268.00
SUBTOTAL 6,196,716.25 100.00 6,196,716.25
D. MEZZANINE
STRUCTURAL 100.00 5,774,761.66 - 5,774,761.66 -
ARCHITECTURAL 100.00 5,127,150.26 - 5,127,150.26 -
PLUMBING 100.00 1,566,172.03 - 1,566,172.03 -
ELECTRICAL 100.00 4,875,000.00 - 4,875,000.00 -
SUBTOTAL 17,343,083.95 100.00 17,343,083.95 -
OWNER SUPPLIED MATERIALS
DOOR AND JAMBS (WITHOUT
100.00 265,100.00 - 265,100.00
HARDWARES)
FLOORING 100.00 236,610.98 - 236,610.98
WINDOW 100.00 896,755.66 - 896,755.66
AIRCON 100.00 280,750.00 - 280,750.00
ELECTRICAL 100.00 470,354.80 - 470,354.80
PLUMBING 100.00 299,392.00 - 299,392.00
2,448,963.44 100.00 2,448,963.44
E. SECOND FLOOR
STRUCTURAL 100.00 5,774,761.66 - 5,774,761.66 -
ARCHITECTURAL 100.00 5,127,150.26 - 5,127,150.26 -
PLUMBING 100.00 1,566,172.03 - 1,566,172.03 -
ELECTRICAL 100.00 4,875,000.00 - 4,875,000.00 -
SUBTOTAL 17,343,083.95 100.00 17,343,083.95 -
OWNER SUPPLIED MATERIALS -
DOOR AND JAMBS (WITHOUT
100.00 641,100.00 - 641,100.00
HARDWARES)
FLOORING 100.00 733,353.76 - 733,353.76
WINDOW 100.00 334,608.93 - 334,608.93
AIRCON 100.00 761,000.00 - 761,000.00
ELECTRICAL 100.00 597,025.80 - 597,025.80
PLUMBING 100.00 171,788.00 - 171,788.00
3,238,876.49 100.00 3,238,876.49
F THIRD FLOOR
STRUCTURAL 100.00 5,774,761.66 - 5,774,761.66 -
ARCHITECTURAL 100.00 5,127,150.26 - 5,127,150.26 -
PLUMBING 100.00 1,566,172.03 - 1,566,172.03 -
ELECTRICAL 100.00 4,875,000.00 - 4,875,000.00 -
SUBTOTAL 17,343,083.95 100.00 17,343,083.95 -
OWNER SUPPLIED MATERIALS -
DOOR AND JAMBS (WITHOUT
100.00 359,500.00 - 359,500.00
HARDWARES)
FLOORING 100.00 631,012.50 - 631,012.50
WINDOW 100.00 460,726.77 - 460,726.77
AIRCON 100.00 630,550.00 - 630,550.00
ELECTRICAL 100.00 507,044.80 - 507,044.80
PLUMBING 100.00 299,052.00 - 299,052.00
2,887,886.07 100.00 2,887,886.07
G FOURTH FLOOR
STRUCTURAL 100.00 5,774,761.66 - 5,774,761.66 -
ARCHITECTURAL 100.00 5,127,150.26 - 5,127,150.26 -
PLUMBING 100.00 1,566,172.03 - 1,566,172.03 -
ELECTRICAL 100.00 4,875,000.00 - 4,875,000.00 -
SUBTOTAL 17,343,083.95 100.00 17,343,083.95 -
OWNER SUPPLIED MATERIALS -
DOOR AND JAMBS (WITHOUT
100.00 719,600.00 - 719,600.00
HARDWARES)
FLOORING 100.00 504,994.90 - 504,994.90
WINDOW 100.00 466,254.25 - 466,254.25
AIRCON 100.00 628,150.00 - 628,150.00
ELECTRICAL 100.00 518,413.80 - 518,413.80
PLUMBING 100.00 459,720.00 - 459,720.00
3,297,132.95 100.00 3,297,132.95
H FIFTH FLOOR
STRUCTURAL 100.00 5,774,761.66 - 5,774,761.66 -
ARCHITECTURAL 100.00 5,127,150.26 - 5,127,150.26 -
PLUMBING 100.00 1,566,172.03 - 1,566,172.03 -
ELECTRICAL 100.00 4,875,000.00 - 4,875,000.00 -
SUBTOTAL 17,343,083.95 100.00 17,343,083.95 -
OWNER SUPPLIED MATERIALS -
DOOR AND JAMBS (WITHOUT
100.00 719,600.00 - 719,600.00
HARDWARES)
FLOORING 100.00 501,899.04 - 501,899.04
WINDOW 100.00 466,254.25 - 466,254.25
AIRCON 100.00 628,150.00 - 628,150.00
ELECTRICAL 100.00 700,433.00 - 700,433.00
PLUMBING 100.00 459,720.00 - 459,720.00
3,476,056.29 100.00 3,476,056.29
I SIXTH FLOOR
STRUCTURAL 100.00 5,774,761.66 - 5,774,761.66 -
ARCHITECTURAL 100.00 5,127,150.26 - 5,127,150.26 -
PLUMBING 100.00 1,566,172.03 - 1,566,172.03 -
ELECTRICAL 100.00 4,875,000.00 - 4,875,000.00 -
SUBTOTAL 17,343,083.95 100.00 17,343,083.95 -
OWNER SUPPLIED MATERIALS -
DOOR AND JAMBS (WITHOUT
100.00 534,600.00 - 534,600.00
HARDWARES)
FLOORING 100.00 314,339.24 - 314,339.24
WINDOW 100.00 408,075.97 - 408,075.97
AIRCON 100.00 684,700.00 - 684,700.00
ELECTRICAL 100.00 423,106.60 - 423,106.60
PLUMBING 100.00 342,141.45 - 342,141.45
2,706,963.26 100.00 2,706,963.26
J. ROOF DECK
STRUCTURAL 100.00 4,487,708.46 - 4,487,708.46 -
ARCHITECTURAL 100.00 500,000.00 - 500,000.00 -
PLUMBING 100.00 600,000.00 - 600,000.00 -
ELECTRICAL 100.00 420,276.48 - 420,276.48 -
SUBTOTAL 6,007,984.94 100.00 6,007,984.94 -
OWNER SUPPLIED MATERIALS -
DOOR AND JAMBS (WITHOUT
100.00 30,000.00 - 30,000.00
HARDWARES)
FLOORING 100.00 50,000.00 - 50,000.00
WINDOW - -
AIRCON - -
ELECTRICAL 100.00 43,160.00 - 43,160.00
PLUMBING 100.00 20,000.00 - 20,000.00
143,160.00 100.00 143,160.00
K HELIPAD
STRUCTURAL 100.00 4,487,708.46 - 4,487,708.46 -
ARCHITECTURAL 100.00 300,000.00 - 300,000.00 -
PLUMBING 100.00 400,000.00 - 400,000.00 -
ELECTRICAL 100.00 420,276.48 - 420,276.48 -
SUBTOTAL 5,607,984.94 100.00 5,607,984.94 -
OWNER SUPPLIED MATERIALS -
DOOR AND JAMBS (WITHOUT
100.00 30,000.00 - 30,000.00
HARDWARES)
FLOORING 100.00 20,000.00 - 20,000.00
WINDOW - -
AIRCON - -
ELECTRICAL 100.00 20,000.00 - 20,000.00
PLUMBING 100.00 10,000.00 - 10,000.00
SUBTOTAL 80,000.00 100.00 80,000.00
GRAND TOTAL FOR OLD
100.00 180,000,000.00 100.00 180,000,000.00 -
CONTRACT
DOOR AND JAMBS (WITHOUT
UPDATED OSM COST 100.00 5,906,500.00 - 5,906,500.00
HARDWARES)
HARDWARES 100.00 2,440,586.40 - 2,440,586.40
FLOORING 100.00 5,414,464.47 - 5,414,464.47
WINDOW 100.00 7,224,291.92 - 7,224,291.92
AIRCON 100.00 6,338,350.00 - 6,338,350.00
INSTALLATION OF AIRCON 100.00 1,500,000.00 - 1,500,000.00
CLADDING 7,500,000.00 100.00 -
SIGNAGES 100.00 200,000.00 - 200,000.00
ELECTRICAL 100.00 4,959,387.80 - 4,959,387.80
PLUMBING 100.00 3,859,945.45 - 3,859,945.45
PUMPS 100.00 500,000.00 - 500,000.00
ELEVATOR AND DUMBWAITER 100.00 5,894,840.00 - 5,894,840.00
GENERATOR SET 100.00 7,000,000.00 - 7,000,000.00
CCTV 100.00 800,000.00 - 800,000.00
NURSE CALL 100.00 4,000,000.00 - 4,000,000.00
VENTILATION SYSTEM 100.00 624,860.71 - 624,860.71
MEDICAL GAS 100.00 4,900,000.00 - 4,900,000.00
PERMITS FOR OCCUPANCY 100.00 1,000,000.00 - 1,000,000.00
MERALCO CONTRACT 100.00 3,000,000.00 - 3,000,000.00
COST OF OSM 73,063,226.75 89.73 65,563,226.75
ADDITIONAL WORKS Old hospital Building 99.50 56,139,387.61 0.50 55,858,690.67

Demolition of Existing Slab Near at


100.00 26,667.01 - 26,667.01
Elevator Pit
Demolition of Existing Cantilever
Slab with Comfort Room at Front 100.00 15,222.33 - 15,222.33
Area
Additional Shear Wall with Water
100.00 197,149.96 - 197,149.96
Proofing
Change Order for Elevator
100.00 1,165,182.12 - 1,165,182.12
Foundation
Additional Retaining Wall at Front 100.00 393,270.53 - 393,270.53

Additional Floor Slab at Mezzanine


100.00 697,960.73 - 697,960.73
Level (Phase-I)
Additional Slab at Phase II UGL
100.00 193,002.79 - 193,002.79
(Line I-J" to 5a-3)
Additional Slab at Phase I LGF to
100.00 581,417.70 - 581,417.70
UGF (A'-B' to 2"-1a")
Additonal Drywall at Dialysis Area
100.00 207,658.61 - 207,658.61
with Demolition Work
Additional for Revised 4th and 5th
100.00 1,301,874.01 - 1,301,874.01
Floor
Additional Charge for Dismantling
of Existing installed Stair Railing at 100.00 127,863.17 - 127,863.17
Phase II-1
Additonal Exhaust System for
100.00 684,130.93 - 684,130.93
Toilets
Additional Concrete at Mezzanine
100.00 118,702.95 - 118,702.95
Level Near Elevator Lobby
Additional Costing for Elevator -
Installation of I-Beams (Structural 100.00 2,404,653.87 - 2,404,653.87
Works)
Installation of Fire Protection and
100.00 9,222,729.47 - 9,222,729.47
FDAS
Additional Driveway at UGF Front
100.00 59,593.31 - 59,593.31
Side Phase I
Additional Cost for Installation of
100.00 144,296.74 - 144,296.74
tile at LGF (driveway)
Installation of Side wall at
100.00 42,969.60 - 42,969.60
Mezzanine Level (Duco Finish)
Additional for Chapel 100.00 47,991.98 - 47,991.98
Additional for Radiology
Department (installation of door 100.00 123,002.06 - 123,002.06
and jambs)
Additional Cost for installation of
100.00 604,135.67 - 604,135.67
Roof at LGF (J-P to 2"-5a)
Additional Cost for Laboratory
100.00 27,960.00 - 27,960.00
Department
Additional cost for Structural of
100.00 2,709,104.06 - 2,709,104.06
STP including Pump Room
Painting Works at Front Side 100.00 516,286.20 - 516,286.20

Drop-off Curb and Retaining wall 100.00 1,530,695.20 - 1,530,695.20

Additional Cost for Structural of


Electrical Room and Generator Set 100.00 1,070,632.68 - 1,070,632.68
Room
Structural of Sump pit 100.00 905,883.98 - 905,883.98
Vault Room to Information
100.00 3,610.83 - 3,610.83
Technology Room
Door Header Alteration from 2.1
100.00 695.04 - 695.04
to 2 meters
Additional Concrete Gutter at
100.00 63,253.50 - 63,253.50
Mezzanine Floor
Additional Concrete Gutter at 6th
100.00 328,897.77 - 328,897.77
Floor
Additional windows at Fire Exit 100.00 8,880.80 - 8,880.80

Additional Work for Relocation of


toilet at 3rd Floor Near Visitor 100.00 7,432.07 - 7,432.07
Lounge
Relocation of Steel Railing at Fire
100.00 6,000.00 - 6,000.00
Exit
Change of Color of Nurse Station
100.00 31,033.24 - 31,033.24
from Grey to Glossy White
Manifold Room 100.00 143,133.03 - 143,133.03
Additional Driveway 100.00 112,490.05 - 112,490.05
Revision on Administrative Area
100.00 190,763.15 - 190,763.15
(architectural Cost Only)
Fire Exit Structure at Phase I 99.00 2,118,445.33 1.00 2,097,260.88
Additional Cost for Doctor's Clinic
100.00 176,839.82 - 176,839.82
Mock Up 1
Additional Cost for Doctor's Clinic
100.00 171,371.42 - 171,371.42
Mock Up 2
Additional Cost for Doctor's Clinic
100.00 144,029.42 - 144,029.42
Mock Up 3
Additional Metal Fire Rated Door 100.00 876,883.93 - 876,883.93

Additional Concrete for Driveway


100.00 1,060,735.68 - 1,060,735.68
at Front Side Gate
Additional Cost for Parking Area at
100.00 71,331.37 - 71,331.37
LGF from 100 to 180mm elevated
Additional Cost for Emergency Exit
100.00 72,487.79 - 72,487.79
Roof at Phase II
Revised Fourth Floor with
additonal 11 units (Plumbing 100.00 407,471.97 - 407,471.97
Works)
Architectural and other Changes
100.00 238,035.39 - 238,035.39
for Fire Exit
Revised Design Administrative
Department (Plumbing Works 100.00 16,847.59 - 16,847.59
Only)
Fabrication and Installation of
100.00 2,907,000.00 - 2,907,000.00
Doors
Additional Electrical Works for
100.00 1,055,321.10 - 1,055,321.10
Dialysis Area
Change Order for Electrical Works 100.00 6,004,634.64 - 6,004,634.64

Additonal Electrical Works for


Headboard of private and 100.00 58,770.53 - 58,770.53
Presidential Suites
Façade Cladding 100.00 7,000,000.00 - 7,000,000.00
Design Fee 100.00 2,584,631.35 - 2,584,631.35
Revised Fifth Floor with additonal
100.00 407,471.97 - 407,471.97
11 units (Plumbing Works)
Proposed 8" Diameter Pipe for the
replacement of Main Sewer Line 100.00 104,337.09 - 104,337.09
going to STP
COST OF ADDITIONAL WORKS 100.00 107,632,261.14 - 107,330,379.74
TOTAL AMOUNT 360,695,487.89 97.84 352,893,606.49

Prepared by: Noted and Checked by:

Engr. John Michael Z. Campitan, CE, SO Arch. Carlos Dychangco, UAP, MSCM

Approved by:

Ms. Isabel M. Sarampote, CPA Dr. Nicolas B. Donato, Jr., MD

You might also like