Professional Documents
Culture Documents
Problem 1
A generous university benefactor has agreed to donate a large amount of money for student
scholarships. The money can be provided in one lump sum of $12 million in Year 0 (the current year), or
in parts, in which $7 million can be provided at the end of Year 1, and another $7 million can be
A. Assuming the opportunity interest rate is 8%, what is the present value of the second alternative
mentioned above? Which of the two alternatives should be chosen and why?
rate of interest and n is number of year when amount will be received”. (Douglas, 2012) The present
value of the second alternative is 12,364,800. With 7,000,000 in year one, and 7,000,000 in year 2 with
an opportunity interest rate of 8%, After the first year, the value would be 6,440,000 (7,000,000 x .08 =
560,000, 7,000,000 - 560,000) After year 2, the value would be 12,364,800 (6,440,000 + 7,000,000 in
year 2 = 13,440,000 x .08 = 1,075,200). This amount should be chosen over the $12,000,000 lump sum
because it will allow the school to have 364,800 more than the $12,000.000
B. How would your decision change if the opportunity interest rate is 12%?
I would go with option two at this point, because with a larger interest rate, the total amount
would drop to 11,580,800, 419,200 less than the $12 lump sum alternative (7,000,000 x .12 = 840,000,
70000,000 - 840,000 = 616,000). In year two, 13,160,000 * .12 = 1,579,200 (13,160,000 - 1,579,200 =
C. Provide a description of a scenario where this kind of decision between two types of payment streams
Financial Managers use Present Value (NPV/FPV) calculations to manage and account for the
time value of money (NPV). One scenario is providing service is one year and receiving payments in later
year. As such, we assume the company provides a service in December 2011 and agrees to be paid $100
in December 2012.The time value of money tells us that the part of the $100 is interest, which is for
waiting one year for the $100. Perhaps only $91 of the $100 is service revenue earned in 2011and $9 is
interest earned in 2012. The calculation of present value will remove the interest, so that the amount of
the service revenue can be determined. Another example might involve the purchase of land: the
owners will either sell it to for $160,000 if he receives the money today, or for $200,000 if paid at the
end of two years. At the end of two years, he would have earned interest for two years on the amount
Problem 2
The San Diego LLC is considering a three-year project, Project A, involving an initial investment
Discount Rate 8%
Running head: ECONIMICS OF RISK AND UNCERTAINTY APPLIED PROBLEM 4
Describe your answer for each question in complete sentences, whenever it is necessary. Show all of
A. Describe and calculate Project A’s expected net present value (ENPV) and standard deviation (SD),
assuming the discount rate (or risk-free interest rate) to be 8%. What is the decision rule in terms of
ENPV? What will be San Diego LLC’s decision regarding this project? Describe your answer.
2,000,000= $36,000,000
Answer for scenario 1: ENPV = -80 + 36 / (1.08) +40 / (1.08) ^ 2 +54 / (1.08) ^ 3 = $30.5million. It is in San
B. The company is also considering another three-year project, Project B, which has an ENPV of $32
million and standard deviation of $10.5 million. Project A and B are mutually exclusive. Which of the two
projects would you prefer if you do not consider the risk factor? Explain.
Using the same calculations as presented in Answer A, we find that Project B has less ENPV. In
case of mutually exclusive projects, the intelligent choice is to choose projects with more ENPV. Thus,
project A over B.
Running head: ECONIMICS OF RISK AND UNCERTAINTY APPLIED PROBLEM 5
Describe the coefficient of variation (CV) and the standard deviation (SD) in connection with risk
attitudes and decision making. If you now also consider your risk-aversion attitude, as the CEO of the
San Diego LLC will you make a different decision between Project A and Project B?
If the decision maker for San Diego, LLC is risk averse, he will find the CV representing standard
deviation for Project B to have less deviation and thus choose B. The expected deviation for Project A is
Reference:
Inc.Walker, J. P., Gudort, C. A., & Talbott, J. C. (1990). San Diego: Bridgepoint Education Contibutin
Schneider, A. (2012). Managerial Accounting; Decision Making for the Service and Manufacturing
Sector.